A. Topping Slab :
9.8.3.1 Slab thickness shall be not less than one-twelfth the clear distance
between ribs, nor less than 50 mm. ( without filler )
We use t = 70 mm
9.8.1.2 Width of ribs shall be at least 100 mm at any location along the
depth.
9.8.1.3 Overall depth of ribs shall not exceed 3.5 times the minimum width.
9.8.1.4 Clear spacing between ribs shall not exceed 750 mm.
Take width of ribs (tf) = 120 mm
6.3.2.1 Width of slab effective as a T-beam flange shall not exceed one-
quarter of the span length of the beam, and the effective overhanging flange
width on each side of the web shall not exceed:
Hollow blocks are made from light weight concrete. The most common
concrete hollow block sizes are 40 * 25 cm in plane and heights of 14, 17,
20 and 24 cm. Use 24 cm hollow blocks.
Design Procedure :
The minimum thickness needed for the whole plan is the worst case; this is
happened in the largest span.
Choose the maximum span length L= 5.8 m, its one end continuous, so;
h min = L/18.5
h min = 580.91/18.5 = 31.4 cm
3.3 Live Load depends on the function for which floor is constructed,
according to Jordanian code for residential buildings take live load = 2
kN\
Total dead load = 2.965 + 2.38 + 1.75 + 1.73 + 1.37 =10.2 kN\
7.6.1.1 Area of shrinkage and temperature reinforcement shall provide at least the
following of reinforcement area to gross concrete area, but not less than 0.0014:
Use 210 2
5. For Rib 1 result from PROKON to get the maximum values of shear and
moment:
Vu = 43.6 kN
+ Mu =
- Mu =
6. Check rib strength for beam shear :
Vu = 43.6 kN
Vc
Vs
Vc
Vs = = 30.1 kN
= 137.5 or 600 mm
2
Smax = 137.5 mm
120 120
Av ,min/s =0.062 *25 =135.3 OR Av,min/s = 0.35* =152.73 mm
275 275
Avmin = 21 2