Professional Documents
Culture Documents
F Mtuwthf Mtuwthf Mtuwthf Mtuwthf Mtuwthf
F Mtuwthf Mtuwthf Mtuwthf Mtuwthf Mtuwthf
A O WWWWW W W U P L L L L
Project Summary
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ORIGINAL PLAN GANTT CHART
MARCH APRIL
Duration
ACTIVITY Predecessor F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M
(working days) 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13
A. Management Approval
3
of Project
B. Ordering of Machines A 1
C. Management Approval
A 5
of Installation Project
D. Laying Off Foundation A 7
E. Ordering of 22
A
Necessary Equipment (incl. hdays & weekends)
F. Unpacking of Machines C 1
G. Physical Inspection of
F 1
Delivered Machines & Cab
H. Injection Machine Installation G 10
I. Drilling Machine Installa H 16
J. Cable Works and Power
H 2
Supply Connect for Injecti
K. Cable Works and Power
I 2
Supply Connect for Drillin
L. Testing Injection Machin J 3
M. Testing Drilling Machin K 4
N. Commissioning M 1
2. Testing of each machine shall occur during weekends to avail the expertise of electrician who happens to be available only
during weekends
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ORIGINAL PLAN GANTT CHART
APRIL MAY
Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ORIGINAL PLAN GANTT CHART
JUNE JULY
Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th
31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Tota
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ORIGINAL PLAN GANTT CHART
Total Duration
F Sa Su M of Project
17 18 19 20 (calendar days)
22
1
1
17
22
27
2
Total: 102
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ALTERNATE PLAN GANTT CHART
MARCH APRIL
Duration
ACTIVITY Predecessor F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M
(working days) 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13
A. Management Approval
3
of Project
B. Ordering of Machines A 1
C. Ordering of 22
A
Necessary Equipment (incl. hdays& weekends)
D. Laying Off Foundation A 7
E. Management Approval
A 5
of Installation Project
F. Unpacking of Machines C 1
G. Physical Inspection of
F 1
Delivered Machines & Cab
H. Injection Machine Installation G 10
I. Drilling Machine Installa H 16
J. Cable Works and Power
H 2
Supply Connect for Injecti
K. Cable Works and Power
I 2
Supply Connect for Drillin
L. Testing Injection Machin J 3
M. Testing Drilling Machin K 4
N. Commissioning M 1
3.
Date of Start 20-Mar-15
Date of Finish 13-Jul-15
Total No. of Days 114
Assumptions:
1. All national holidays are excluded from the project except those days which are declared special non working holidays upon
the duration of the project;
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ALTERNATE PLAN GANTT CHART
2. Testing of each machine shall occur during weekends to avail the expertise of electrician who happens to be available only
during weekends
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ALTERNATE PLAN GANTT CHART
APRIL MAY
Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
A O W W W W W W W U P L L L L R R
L - Upon having ascertained that the spare parts are good to go, 4 days
the fitter has to be away for Sick Leave (Calendar Days)
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ALTERNATE PLAN GANTT CHART
JUNE JULY
Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th
31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Tota
CE 537 5:30-7:30 pm
DAAROL, MICHELLE A INSTALLING AN ASSEMBLY LINE FOR A PACKAGING MACHINE
ENGR. JAY LOUIE FERNANDO
BSCE - IV ALTERNATE PLAN GANTT CHART
Total Duration
F Sa Su M of Project
17 18 19 20 (calendar days)
22
1
1
42
16
27
2
Total: 114
D. Subgrade Preparation
a. Roadway
b. Concrete Flare
E. Aggregate Base Course
a. Roadway
b. Concrete Flare
c. Shoulder
a. Roadway
b. Concrete Flare
a. Roadway
b. Concrete Flare
c. Shoulder