COST ESTIMATION Of UNDER GROUND WATER RESERVER

OF FACTORY BUILDING FOR HYPOID LINGERIES LTD.


AT
124-125, DARUS SALAM,MIRPUR ROAD, DHAKA 1216

A. CIVIL WORKS :
SL Description of items Unit Quantity Rate Amount
1 Shore protection RFT 135.00 3000 405,000.00
2 Earth work in excavation of all kinds of soils of foundation
trenches including leveling ramming and preparing the
base, bailing out water and shoring if necessary providing
center line and bench mark pillars, removing the spoils etc. cf 11115 15 166,725.00

3 R.C.C works for concrete having minimum cylinder


crushing strength (1:1.5:3) 3000 Psi at 28 days with
Bangladeshi cement, best quantity of Sylhet sand F.M
2.5) 20mm ( ) down graded shingles including
screening, centering, pile pointing or rod in position
mixing the aggregates with mixer machine casting etc
( excluding the cost of reinforcement and its fabrication) CFT 2470 500 1,235,000.00
(Min compressive strength of cement at 7 days = 62% ) .
all complete as per structural drawing & structural note.

4 Supplying fabrication and fixing to details as per design


deformed bar reinforcement in concrete with straightening
and cleaning rust, if any, bending and binding in position
with supply of G.I wires etc . complete in all respect in all KG 5500 85 467,500.00
floors ( 60 grade )(BSRM/KSRM/AKS)

5 Sand filling from EGL with fine local sand (F.M 0.8) in cf 2500 16 40,000.00
12 layer watering & consolidation each layer upto the
finished level.

6 Engineer and Consultant Cost, Site arrangment, Contructor 0 320 300,000.00


profite othere over head cost.

Total Civil works : Tk. 2,614,225.00