ID TaskTask Name Duration Start Finish
Mode 06 Nov '16 20 Nov '16 04 Dec '16 18 Dec '16 01 Jan '17 15 Jan '17 29 Jan '17 12 Feb '17 26 Feb '17
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T
13 Slab shutt with 17.1 days Tue 27-12-16 Sun 15-01-17
steel
14 Ramp Area Slab 13.4 days Mon 26-12-16 Tue 10-01-17
(S.F)
15 4th floor slab 21.4 days Wed 11-01-17 Sun 05-02-17