Professional Documents
Culture Documents
Converting Primary/Secondary Chilled Water Systems To All Variable Flow
Converting Primary/Secondary Chilled Water Systems To All Variable Flow
Engineering Report
3. Control valves must be closed 5. Control the VFD on the water circulated to the AHUs
when the AHU they serve is air handler pump from a in cold weather when the
off unless water is circulated differential pressure sensor chillers are off. A modulating
in the coils in cold weather (DP-1) across the branch two-way control valve may
to prevent freezing, when the serving the most remote be used instead of a check
chillers are off. AHU. If the air handler valve valve. Control this valve from
positions are known, reset DP- a differential pressure sensor
4. Interlock the chiller (primary) across the chiller evaporators.
1 from the most demanding air
pumps to run with the chiller The valve must be sized for the
handling unit valve. This will
they serve. These pumps may minimum flow of the largest
keep the pump head as low as
be manifolded together, as chiller, a close-off rating at least
possible.
shown in Fig.1 or each pump as high as the air handler pump
may be piped to a chiller. 6. Install a check valve, CV- cut-off head and for a pressure
When operating in the Max- 1, in the existing decoupler drop at or less than the setting
Cap range the chiller pumps are connecting the chilled water of differential pressure sensor
in series with the air handler supply and return mains DP-1. The differential pressure
pump and flow through the (points A-B), to prevent across points A-B will never be
chiller pumps may increase return water from mixing less than the setting of DP-1.
above the design flow of a with supply water. The check
primary/secondary system. valve may be line size and may 7. Install a two position chilled
have a manual or automatic water isolation valve in the
opening mechanism so that branch to each chiller. These
the valve can be opened and valves may be line size, metal
seated butterfly valves unless
Chiller
they will also be used as a
Isolation service valve. If they are used
Valves
DP-1 for servicing, then tight shut-
off valves must be used.
T
CHILLER #1 COIL 8. Stage the chillers on from
T
temperature sensor TS-1 with
the set point at the design
COIL supply water temperature
CHILLER #2
T to the air handlers. Staging
COIL
the chillers on from supply
temperature enables the chillers
CHILLER #3 T
to operate in the Max-Cap
COIL variable flow range to produce
Chiller
Pumps T
their maximum capacity
depending on the entering
Check COIL
Valve condenser water temperature.
T The on-line chiller(s) will load
A
Decoupler
B COIL fully (above rated capacity
CV-1 whenever the outdoor Wet
Coil bulb temperature is below
Valves
FLOW
VFD design) before the next chiller
TS-1
SENSOR
FS-1 is brought on-line. The chart
AIR HANDLER PUMP in Figure 2 depicts the typical
performance of a 1,000-ton
Figure 1 TS-2 chiller as the evaporator flow
2 Engineering Report
chiller isolation valve and stop
the chiller pump when the
Typical Performance of a 1,000-ton Chiller Operating building load drops far enough
in the Max-Cap Range with a Constant Evaporator below the capacity of an on-
T of 12F and an Increasing Evaporator Flow line chiller to avoid cycling
CDS CW Evaporator Increase Total Net the chiller back on too quickly.
Deg. F Tons GPM PD (FT) in EPTE kW kW/TON Load is proportional to flow
85 1,000 2,000 20.6 -- 580.0 .58 times delta T. Flow can be
80 1,090 2,178 24.0 2.1 601.6 .55 measured by flow sensor FS-1
75 1,130 2,258 25.7 3.2 602.1 .53 and delta T from temperature
70 1,156 2,310 26.8 3.9 605.0 .52
65 1,182 2,362 27.9 4.6 595.6 .50
sensors TS-1 and TS-2.
60 1,207 2,412 29.0 5.3 596.7 .49 Flow can also be measured with
55 1,233 2,464 30.0 6.0 597.8 .48 a differential pressure sensor
Notes: across the chiller evaporator if
CDS = Condenser Water Supply
CW = Chilled Water
dependable flow characteristics
EPTE = Evaporator Pump Transport Energy (kW) of the chillers are known.
12. Vary the speed and cycle the
Figure 2 cooling tower fans (and tower
bypass valve if used) from
increased from 2,000 to 2,464 0.58 to 0.49 and the capacity a temperature sensor in the
GPM and the condenser water increased 11.6% from 1,000 to condenser water supply to the
supply temperature decreased 1,166 tons. (See Figure 3.) chillers.
from 85F to 55F. The increase
10. Since both the chilled water 13. Reset the condenser water
in evaporator pump water supply temperature with the
flow and the delta T vary, the
transport energy (EPTE) is outdoor wet bulb temperature.
actual kw/ton may be less than
added to the chiller KW to Do not reset below that
that shown in Figures 2 and 3.
arrive at the total and net KW recommended by the chiller
per ton. The net kw/ton for this 11. To stage a chiller off, close the manufacturer.
machine has decreased from
0.58 to 0.48 and the cooling
capacity has increased from
1,000 to 1,233 tons (23.3%). Typical Performance of a 1,000-ton Chiller Operating
(See Figure 2.) in the Max-Cap Range with a Variable Evaporator
DT and a Constant Evaporator Flow of 2,000 GPM
9. For each chiller, set the control
point for the temperature CDS Total CWR CWS Delta KW per
sensor in the supply water off Deg. F kW Tons Deg. F Deg. F T Ton
the chiller 3 below design. 85.0 580.0 1,000 56.0 44.0 12.0 .58
If the design is 44F, set the 80.0 592.9 1,078 56.4 43.5 12.9 .55
75.0 587.8 1,109 56.3 43.0 13.3 .53
chiller sensors at 41F. This .52
70.0 585.0 1,125 56.0 42.5 13.5
will enable the chillers to 65.0 569.5 1,139 55.7 42.0 13.7 .50
operate in the more efficient 60.0 565.0 1,153 55.3 41.5 13.8 .49
Max-Cap variable temperature 55.0 571.3 1,166 55.0 41.0 14.0 .49
range. The chart in figure 3 Notes:
CDS = Condenser Water Supply
depicts the performance of CWR = Chilled Water Return
a typical 1,000 ton chiller as CWS = Chilled Water Supply
the delta T increased from 12
to 14 degrees. The kw/ton for Figure 3
this machine decreased from
Engineering Report 3
14. All equipment interlocks, flow
and temperature stabilization
time delays, chiller isolation
valve timing, condenser water
controls, etc., must be specified
as recommended by the chiller
manufacturers, to complete
the sequence of control for an
all variable flow chilled water
system.
Gil Avery, PE
Kele, Inc.
12/31/08
gil.avery@kele.com
4 Engineering Report