FOUNDATION CALCULATION SHEET

One-Stop Solution for Foundation

TITLE DESCRIPTION
PROJECT/JOB NO. Panithi
PROJECT/JOB NAME ACI
CLIENT NAME MKS
SITE NAME 5-6
DOCUMENT NO.
REFERENCE NO.
STRUCTURE NAME F-450
LOAD COMBINATION GROUP

REV DATE DESCRIPTION PREP'D CHK'D APPR'D APPR'D

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 1

FOUNDATION LISTS
Group Name No. Description No. Description
ISO-1 1 F1

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 2

CONTENTS

1. GENERAL
1.1 CODE & STANDARD
1.2 MATERIALS & UNIT WEIGHT
1.3 SUBSOIL CONDITION & SAFETY FACTORS
1.4 LOAD COMBINATION

2. DRAWING
2.1 LOCATION PLAN & DETAIL SKETCH

3. FOUNDATION DATA
3.1 FOOTING AND SECTION DATA
3.2 PIER DATA
3.3 LOAD CASE
3.4 LOAD COMBINATION

4. CHECK OF STABILITY
4.1 CHECK OF PILE REACTION

5. DESIGN OF FOOTING
5.1 DESIGN MOMENT AND SHEAR FORCE
5.2 REQUIRED REINFORCEMENT
5.3 ONE WAY SHEAR FORCE
5.4 TWO WAY SHEAR FORCE
5.5 PILE PUNCHING SHEAR FORCE

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 3

1. GENERAL
1.1 CODE & STANDARD
Items Description
Design Code American Concrete Institute (ACI 318) [Metric]
Horizontal Force for Wind AMERICAN SOCIETY OF CIVIL ENGINEERS [ASCE 7-02]
Horizontal Force for Seismic AMERICAN SOCIETY CIVIL ENGINEERS [ASCE 7-02]
Unit System Input : MKS, Output : MKS, Calculation Unit : IMPERIAL

1.2 MATERIALS & UNIT WEIGHT


Items Value
2
Concrete (f'c : compressive strength) 173.000 kgf/cm
2
Lean Concrete (Lf'c : compressive strength) 0.000 kgf/cm
2
Reinforcement (D9 ~ D16 , yield strength) 3000.000 kgf/cm
2
Reinforcement (D19 ~ , yield strength) 3000.000 kgf/cm
3
Rs (Soil unit weight) 2.000 ton/m
3
Rc (Concrete unit weight) 2.400 ton/m
2.000 106 kgf/cm
2
Es (Steel Modulus of Elasticity)
2
Ec (Concrete Modulus of Elasticity) 250998.000 kgf/cm

- Pile Capacity
Items Value
Pile Name PHC Pile-50
Footing List F1
Diameter 500 mm
Length 21 m
Thick 20 mm
Shape Circle
Capacity ( Ha , Ua , Va ) 2 , 10 , 50 tonf

1.3 SUBSOIL CONDITION & SAFETY FACTORS


Items Description
Allowable Increase of Soil (Wind) 0%
Allowable Increase of Soil (Seismic) 0%
Allowable Increase of Soil (Test) 0%
Allowable Increase of Pile Horizontal (Wind) 0%
Allowable Increase of Pile Horizontal (Seismic) 0%
Allowable Increase of Pile Horizontal (Test) 0%
Allowable Increase of Pile Vertical (Wind) 0%
Allowable Increase of Pile Vertical (Seismic) 0%
Allowable Increase of Pile Vertical (Test) 0%
Allowable Increase of Pile Uplift (Wind) 0%
Allowable Increase of Pile Uplift (Seismic) 0%
Allowable Increase of Pile Uplift (Test) 0%

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 4

Safety factor against overturning for OVM1(FO1) 2


Safety factor against overturning for OVM2(FO2) 2
Safety factor against overturning for OVM3(FO3) 2
Safety factor against overturning for OVM4(FO4) 2
Safety factor against sliding for the SL1(FS1) 1.5
Safety factor against sliding for the SL2(FS2) 1.5
Safety factor against sliding for the SL3(FS3) 1.5
Safety factor against sliding for the SL4(FS4) 1.5
Friction factor (m) .35

1.4 LOAD COMBINATION


Index Load Case Name Load Case Description
1 DL DEAD LOAD
2 LL LIVE LOAD

Comb . ID Load Combination for stability


1 1.0 SW + 1.0 DL + 1.0 LL
2 1.0 SW + .75 DL + .75 LL + .75 WL
Comb . ID Load Combination for Reinforcement
101 1.4 SW + 1.4 DL + 1.7 LL
102 1.05 SW + 1.05 DL + 1.275 LL + 1.275 WL

Copyright (c) GS E&C. All Rights Reserved


4/5/2555 Page 5

2. DRAWING REFERENCE DWGS


NO. DWG NO. DWG TITLE

A01

NOTES
* OUTPUT UNIT : mm

01

1 ACI PROJECT

FOUNDATION LOCATION PLAN


F-450

SQUAD CHECK
F1

Y
PROCESS PIPING VESSELS STRUCT. ELEC. INST.

Z X SCALE JOB NO. MICROFILM NO.

AS SHOWN Panithi

Copyright (c) GS E&C. All Rights Reserved


4/5/2555 Page 6

OUTPUT UNIT : mm

Copyright (c) GS E&C. All Rights Reserved


4/5/2555 Page 7

REFERENCE DWGS
NO. DWG NO. DWG TITLE
2500 CL FOOTING
1250

TYP.
50
500
1250

15-D20
2500

1500
NOTES
* PILE
4-??500 PHC Pile-50

500
* OUTPUT UNIT : mm

500 1200
300 500 15-D20

FOUNDATION PLAN FOOTING REINF. PLAN

ACI PROJECT
25 GR.

300
100 75

TOG EL. + 1000

50
TYP.
1000

@200
D12

D19

400 FOUNDATION DETAIL FOR


100

D12 F1

SQUAD CHECK
900

36-D19
PEDESTAL
150

PROCESS PIPING VESSELS STRUCT. ELEC. INST.


LEAN CONC. 50 THK

SECTION
SCALE JOB NO. MICROFILM NO.

REV. DATE DESCRIPTION DRWNCHKD APPD APPD APPD


AS SHOWN Panithi

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 8

3. FOUNDATION DATA
3.1 FOOTING AND SECTION DATA
( mm ) Ft. Name F1
Ft. Type ISO
2
2500 Area 6.250 m
Ft. Thickness 900.00 mm
3
Ft. Volume 5.625 m
Ft. Weight 13.500 tonf
Soil Height 0.00 mm
3
Soil Volume 0.000 m
300 400 Soil Weight 0.000 tonf
2500

Buoyancy Not Consider


Self Weight (except Pr.SW) 13.500 tonf

1000
900

The Origin coordinate


The Center of Gravity (0,0) mm
The Center of Pile (75,0) mm

Section Data
( mm )
Ft.Name Direction Ft. Volume Soil Volume Pier Wt
3 3
F1 All Direct 5.625 m 0.000 m 0.288 tonf

Sec.Name Section Area Ft. Weight Soil Weight Total Weight


2
S1 6.250 m 13.500 tonf 0.000 tonf 13.788 tonf

3.2 PIER DATA


Off X , Off Y is offset position from the Center of the footing
If Pier Shape is Circle or Circle wall, Pl is a Diameter. and Pw is a Inner Diameter
Area is pier concrete area
Weight is pier and inner soil weight in case circle wall except Tank1 Type(Circle Ring Footing Shape)
2
Unit( Length : mm , Weight : tonf , Area : m )
Ft.Name Pr.Name Shape Pl Pw Ph Area Weight Off X Off Y
F1 1 Rectangle 300.000 400.000 1000.000 0.120 0.288 0.000 0.000

3.3 LOAD CASE


Fz
Fy
Mz
Input the point loads in the global coordinate system direction. Positive directions of moments (shown in the sketch)
My are based on the right hand rule.
Fx
Mx

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 9

Index Load Case Name Load Case Description


1 DL DEAD LOAD
2 LL LIVE LOAD

Unit( tonf , tonf-m )


Ft.Name Pr.Name Load Case Fx Fy Fz Mx My
1 0 0 -70 0 0
1
F1 2 0 0 -90 0 0
Footing SW 0.000 0.000 -13.500 0.000 0.000

3.4 LOAD COMBINATION


In Pier Top In Footing Bottom In Footing Bottom Center
without Self Weight with Pier Self Weight, with Pier & Footing Self Weight & Soil Weight,
But without Footing Self Weight, Case PileType
in centroid of Pile Group
Case NonPileType
in centroid of Footing

3.4.1 Load Combination in Pier Top (Without SW)


Unit( tonf , tonf-m )
Ft.Name Pr.Name L.Comb. SFx SFy SFz SMx SMy
1 0.000 0.000 -160.000 0.000 0.000
2 0.000 0.000 -120.000 0.000 0.000
F1 1
101 0.000 0.000 -251.000 0.000 0.000
102 0.000 0.000 -188.250 0.000 0.000

3.4.2 Load Combination in Footing Bottom (With Pier SW)


Unit( tonf , tonf-m )
Ft.Name Pr.Name L.Comb. SFx SFy SFz SMx SMy
1 0.000 0.000 -160.000 0.000 0.000
2 0.000 0.000 -120.000 0.000 0.000
F1 1
101 0.000 0.000 -251.000 0.000 0.000
102 0.000 0.000 -188.250 0.000 0.000

3.4.3 Load Combination in Footing Bottom Center (With Pier & Footing SW)
Load Combination of Elastic Condition
p : PileType
- C.G. of Load is coordinate from left bottom. Unit : mm Unit( tonf , tonf-m )
Ft.Name L.Comb. SFx SFy SFz SMx SMy C.G. of Loads
1 0.000 0.000 -173.500 0.000 -13.012 1250.0 , 1250.0
F1 p
2 0.000 0.000 -133.500 0.000 -10.012 1250.0 , 1250.0

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 10

Load Combination of Ultimate Condition


p : PileType
- C.G. of Load is coordinate from left bottom. Unit : mm Unit( tonf , tonf-m )
Ft.Name Sec.Na L.Comb. SFx SFy SFz SMx SMy C.G. of Loads
101 0.000 0.000 -251.000 0.000 -18.825 1250.0 , 1250.0
F1 p S1
102 0.000 0.000 -188.250 0.000 -14.119 1250.0 , 1250.0

3.4.4 Pile Reaction Table

Footing Name F1
2500 Section Name -

Pile Name PHC Pile-50

Pile Shape Circle

Pile Number 4 EA
1 2
Pile Diameter 500 mm
2500

LC Type Stability

Origin Point (0,0) mm


The Center of Gravity (0,0) mm
The Center of Pile (75,0) mm
3 4

Vertical Critical LC : 1

LC : 1, ( 1.0 SW + 1.0 DL + 1.0 LL ) Unit (mm,tonf)


Pile Geometry Bi-Axial Shear (Hor)
No. Name Ra Ua Ha
X Y XY-Dir. XY-Dir.
1 PHC Pile-50 -450 750 47.03 0 50 10 2
2 PHC Pile-50 750 750 38.67 0 50 10 2
3 PHC Pile-50 -750 -750 49.12 0 50 10 2
4 PHC Pile-50 750 -750 38.67 0 50 10 2

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 11

4. CHECK OF STABILITY
4.1 CHECK OF PILE REACTION (Bi-Axial)
4.1.1 Formula
if footing is checked in Buoyancy SFz means SFz - Fb
SFz SMy X SMx Y
a. Vertical - Bi Axial : R =
S Xi S Yi
2 2
Np
- Ru = Rmax
- Uf = Min[ 0 , Rmin ]
- Ru < Va -> OK
(SHxi + SHyi )
2 2

b. Horizontal - Hmax = < Ha -> OK


Np
c. Uplift - Uf < Ua -> OK
Ver. / Uf. = Vertical / Uplift

4.1.2 Check of Vertical & Uplift Reaction


SXi (m ) SYi (m )
2 2 2 2
Ft.Name Np(EA) Fl (mm) Fw (mm)
F1 4 2500 2500 1.87 2.25

Unit( tonf )
Ft.Name L.Comb. Pile R Max R Min Ru Uf Ra Ua Result
1 PHC Pile- 49.123 38.672 49.123 0 50 10 OK
F1
2 PHC Pile- 37.798 29.756 37.798 0 50 10 OK

4.1.3 Check Of Horizontal Reaction


Ft.Name L.Comb. Pile Hmax (tonf) Ha (tonf) Result
PHC Pile-
F1 2 0 2 OK
50

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 12

5. DESIGN OF FOOTING
5.1 DESIGN MOMENT AND SHEAR FORCE
Footing design is in accordance with unltimate strength method at footing bottom.
Calculated total pier load as
SQ = SFz - Self Weight Factor (Soil Weight + Footing Weight)
Ft.Name : Footing Name , Sec.Name : Strip Name for Footing Reinforcement Design
Dir. : Direction , L.Comb. : Load Combination Index , Sl or Sw : Strip X or Y width

5.1.1 Data Unit( mm , tonf , tonf-m )


Ft.Name Sec.Na Dir. L.Comb. Fl or Fw Sl or Sw SFz SM SQ
F1 p 101 2500.00 2500.00 251.000 -18.83 251.000
S1 X
102 2500.00 2500.00 188.250 -14.12 188.250
101 2500.00 2500.00 251.000 0.000 251.000
S1 Y
102 2500.00 2500.00 188.250 0.000 188.250

5.1.2 Design Parameters


Yield Strength - D9 ~ D16 : fy1 , D19 ~ : fy2
f_cl : Clear Cover for edge of footing reinforcement
f_clt : Clear Cover for top of footing reinforcement
fp_clb : Clear Cover for bottom of footing reinforcement (Pile Foundation)
Loc. : Location of Critical Point from left side of footing

2
Unit(kgf/cm ,mm)
f(Flexure) f(Shear) f'c fy1 fy2 f_cl f_clt fp_clb
.9 .85 173.00 3000.00 3000.00 50.0 50.0 150.0

5.2 REQUIRED REINFORCEMENT


5.2.1 Reinforcement Formula
- Shrinkage and temperature reinforcement ---- ACI CODE 7.12.2
As = fac b h , fac = following
Area of shrinkage and temperature reinforcement shall provide at least the following ratio
of reinforcement area to gross concrete area, but not less than 0.0014
(a) Slabs where Grade 40 or 50 deformed bars are used .....................................................................0.0020
(b) Slabs where Grade 60 deformed bars or welded wire reinforcement are used.................................0.0018
(c) Slabs where reinforcement with yield stress exeeding 60,000 psi measured at a yield
0.0018 60,000
strain of 0.35 percent is used ....................................................................................................
fy
- Required Reinforcement by Analysis
As As2
- At every section of flexural members where tensile reinforcement is required
As As5 As4 ---- ACI Eq (10-3)
- The requirements of Eq (10-3) need not be applied, if every section As provided is
at least one -third greater then that required by analysis ---- ACI CODE 10.5.3
As2 = r.req b d
As3 = 1.333 r.req b d
200
As4 = bd
fy
3 fck
As5 = bd
fy
Asmax = 0.75 rb b d

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 13

fck 0.003 Es
rb = 0.85 b 1
fy 0.003 Es + fy
Selected As = Max ( As1 , As2 , Min ( As3 , Max ( As4 , As5 ) ) )
If Selected As < Using As < Asmax , then OK!!

Note : The reinforcement is calculated bases on the maximum moment under the foundation in each direction.
But, the 'ISO' , 'OCT' , 'HEX' , 'COMB' , 'TANK1' foundations are calaulated as face pier
Where,
Mu 0.85 fck 2Rn
Rn =
fbd2
, f = .9 , r.req =
fy ( 1- 1-
0.85fck )
5.2.2 Check of Footing Reinforcement
Footing Name : F1 GroupType : Isolated
- X direction (All Width)

Sec.Nam L.Comb. Using Bar (mm) Loc. (m) Width b (m) d (cm) As (cm )
2

102 top Not Used 1.250 2.500 85.000 0.000


S1
101 botom 15 - D20 @ 171.43 1.400 2.500 74.000 47.124

Sec.Nam L.Comb. Mu (tonf-m) Rn r.Req


102 top - - -
S1
101 bottom 67.135 5.449 0.0019

Sec.Nam L.Comb. As1(cm )


2
As2(cm )
2
As3(cm )
2
As4(cm )
2
As5(cm )
2
Asmax(cm )
2

102 top - - - - - -
S1
101 bottom 45.000 34.248 45.653 86.712 64.520 385.394

Sec.Nam L.Comb. Using As(cm )


2
Select As(cm )
2
Result
102 top - - -
S1
101 bottom 47.124 45.653 OK

- Y direction (All Width)

Sec.Nam L.Comb. Using Bar (mm) Loc. (m) Width b (m) d (cm) As (cm )
2

102 top Not Used 1.250 2.500 83.000 0.000


S1
101 botom 15 - D20 @ 171.43 1.450 2.500 72.000 47.124

Sec.Nam L.Comb. Mu (tonf-m) Rn r.Req


102 top - - -
S1
101 bottom 69.025 5.918 0.0020

Sec.Nam L.Comb. As1(cm )


2
As2(cm )
2
As3(cm )
2
As4(cm )
2
As5(cm )
2
Asmax(cm )
2

102 top - - - - - -
S1
101 bottom 45.000 36.252 48.324 84.368 62.776 374.978

Sec.Nam L.Comb. Using As(cm )


2
Select As(cm )
2
Result
102 top - - -
S1
101 bottom 47.124 48.324 NG

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 14

Title

Bending Moment Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 X 101
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMy Moment intia 4
-251.000 tonf -18.825 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Mubottom = 67.135 tonf-m , Mutop = 0 tonf-m

00

00

00

050
0

2457
50

80

11

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

71.066 68.042

111.892

[B.M.D] [ tonf-m ]

-67.1
-50.4
-33.6
-16.8
0
16.8
33.6
50.4
67.14
67.1

[B/L.M.D] [ tonf-m / ft ]

-26.9
-20.1
-13.4
-6.7
0
6.7
13.4
20.1
26.85
26.9

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 15

Title

Bending Moment Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 X 102
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMy Moment intia 4
-188.250 tonf -14.119 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Mubottom = 50.351 tonf-m , Mutop = 0 tonf-m

00

00

00

050
0

2457
50

80

11

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

53.3 51.032

83.919

[B.M.D] [ tonf-m ]

-50.4
-37.8
-25.2
-12.6
0
12.6
25.2
37.8
50.35
50.4

[B/L.M.D] [ tonf-m / ft ]

-20.1
-15.1
-10.1
-5
0
5
10.1
15.1
20.14
20.1

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 16

Title

Bending Moment Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 Y 101
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMx Moment intia 4
-251.000 tonf 0.000 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Mubottom = 69.025 tonf-m , Mutop = 0 tonf-m

50

50

00

050
0

2457
50

10

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

125.5 125.5

[B.M.D] [ tonf-m ]

-69
-51.8
-34.5
-17.3
0
17.3
34.5
51.8
69.03
69

[B/L.M.D] [ tonf-m / ft ]

-27.6
-20.7
-13.8
-6.9
0
6.9
13.8
20.7
27.61
27.6

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 17

Title

Bending Moment Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 Y 102
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMx Moment intia 4
-188.250 tonf 0.000 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Mubottom = 51.769 tonf-m , Mutop = 0 tonf-m

50

50

00

050
0

2457
50

10

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

94.125 94.125

[B.M.D] [ tonf-m ]

-51.8
-38.8
-25.9
-12.9
0
12.9
25.9
38.8
51.77
51.8

[B/L.M.D] [ tonf-m / ft ]

-20.7
-15.5
-10.4
-5.2
0
5.2
10.4
15.5
20.71
20.7

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 18

5.3 ONE WAY SHEAR FORCE


5.3.1 One-Way Shear Formula
ACI 318-05 CODE 11.3.1.1
- For members subject to shear and flexure only.
- f Vc = .85 2 fck B'w d (eq 11-3)
- Vu <= f Vc , then OK!!

5.3.2 Check of One-Way Shear


Footing Name : F1 GroupType : Isolated PileType : True

Unit : mm
2500
2500

2475

2475

- X direction One-Way Shear (All Width)


Sec.Nam L.Comb. Loc. (mm) d (mm) Bw (mm) fVc (tonf) Vu (tonf) Result
S1 101 2475 740 2500 109.682 0 OK
- Y direction One-Way Shear (All Width)
Sec.Nam L.Comb. Loc. (mm) d (mm) Bw (mm) fVc (tonf) Vu (tonf) Result
S1 101 2475 720 2500 106.718 0 OK

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 19

Title

Shear Force Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 X 101
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMy Moment intia 4
-251.000 tonf -18.825 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Vu = 0 tonf

00

00

00

050
0

2457
50

80

11

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

71.066 68.042

111.892

[S.F.D] [ tonf ]

139.1
104.3
69.6
34.8
0
-34.8
-69.6
-104.3
-139.1

[S/L.F.D] [ tonf / ft ]

55.6
41.7
27.8
13.9
0
-13.9
-27.8
-41.7
-55.6

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 20

Title

Shear Force Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 X 102
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMy Moment intia 4
-188.250 tonf -14.119 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Vu = 0 tonf

00

00

00

050
0

2457
50

80

11

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

53.3 51.032

83.919

[S.F.D] [ tonf ]

104.3
78.2
52.2
26.1
0
-26.1
-52.2
-78.2
-104.3

[S/L.F.D] [ tonf / ft ]

41.7
31.3
20.9
10.4
0
-10.4
-20.9
-31.3
-41.7

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 21

Title

Shear Force Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 Y 101
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMx Moment intia 4
-251.000 tonf 0.000 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Vu = 0 tonf

50

50

00

050
0

2457
50

10

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

125.5 125.5

[S.F.D] [ tonf ]

125.5
94.1
62.8
31.4
0
-31.4
-62.8
-94.1
-125.5

[S/L.F.D] [ tonf / ft ]

50.2
37.6
25.1
12.5
0
-12.5
-25.1
-37.6
-50.2

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 22

Title

Shear Force Diagram 2500

Foundation name Section name Direction L/C ID


F1 S1 Y 102
Analysis Method 1 2
Conventional Rigid Method with reaction (Method 1)

2500
SFz SMx Moment intia 4
-188.250 tonf 0.000 tonf-m 3.2552 m
Area 2 Contact Area Critical Point Method 3 4
6.250 m Critical Max Point
Critical Value
Vu = 0 tonf

50

50

00

050
0

2457
50

10

14

20
0

2
[ mm ]

[Loading]

[ tonf , tonf/m ]

94.125 94.125

[S.F.D] [ tonf ]

94.1
70.6
47.1
23.5
0
-23.5
-47.1
-70.6
-94.1

[S/L.F.D] [ tonf / ft ]

37.6
28.2
18.8
9.4
0
-9.4
-18.8
-28.2
-37.6

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 23

5.4 TWO WAY SHEAR FORCE


5.4.1 Two-Way Shear Formula
Vu = SFz Shade Ratio
(a) f Vc1 = .85 2 (1 + 2/b c) fck bo d (eq 11-33) <- Vc1
(b) f Vc2 = .85 2 (1 + as d / 2 bo) fck bo d (eq 11-34) <- Vc2
(c) f Vc3 = .85 4 fck bo d (eq 11-35) <- Vc3
f Vc = Min(f Vc1 , f Vc2 , f Vc3) ACI 318-05 CODE 11.12.2.1
Vu f Vc , then OK
where
b = ratio of long side to short side of the column, concentrated load or reaction area
as = 40 for interior colimns
= 30 for edge columns
= 20 for corner columns
bo = perimeter of critical section
Footing Area - Punching Area
Shade Ratio =
Footing Area

5.4.2 Check of Two-WayShear

2
Ft.Name F1 Punching Area 11856.000 cm

2500 Pr.Name 1 Pile effect 3.937 / 4

Shape Rectangle f Vc1 478.214 tonf

L.Comb. 101 f Vc2 840.604 tonf


2500

Pl 300 mm f Vc3 382.571 tonf


1

Pw 400 mm f Vc 382.571 tonf

bo / d 4360 / 740 mm Vu 247.018 tonf

bc / as 1.333333 / 40 Result OK

5.5 PILE PUNCHING SHEAR FORCE


5.5.1 Pile Punching Shear Formula
Vu = SFz Shade Ratio
(a) f Vc1 = .85 2 (1 + 2/bc) fck bo d (eq 11-33) <- Vc1
(b) f Vc2 = .85 2 (1 + as d / 2 b o) fck bo d (eq 11-34) <- Vc2
(c) f Vc3 = .85 4 fck bo d (eq 11-35) <- Vc3
f Vc = Min(f Vc1 , f Vc2 , f Vc3) ACI 318-05 CODE 11.12.2.1
Vu f Vc , then OK
where
b = ratio of long side to short side of the column, concentrated load or reaction area
as = 40 for interior colimns
= 30 for edge columns
= 20 for corner columns
b o = perimeter of critical section
Footing Area - Punching Area
Shade Ratio =
Footing Area

Copyright (c) GS E&C. All Rights Reserved


4/5/2555

Project Na. : ACI


Calculation Sheet
of Project No. : Panithi

Foundation Client : MKS Page 24

5.5.2 Check of Pile Punching Shear

Ft.Name F1 Punching Area 10831.080 cm2

2500 Pile No. 3 bc / as 1 / 20

Shape Circle f Vc1 307.069 tonf

1 2 L.Comb. 101 f Vc2 427.016 tonf


2500

PileName PHC Pile-50 f Vc3 204.713 tonf

Diameter 500mm f Vc 204.713 tonf


3 4
bo 2333.02mm Vu 76.417 tonf

d 740mm Result OK

Copyright (c) GS E&C. All Rights Reserved