PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT ACBs


IDCT PMCC- 4A

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 1 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 28.06.17

1. Board Details

1 STATION NAME/BOARD UNIT 3 & 4 4A


2 AREA/LOCATION PMCC
3 DRAWING NUMBER
4 RATING 2500A
2. Verification of Name Plate Details

Feeder Rated STC Closing Spring Charging


Identification No. for 1 Tripping Coil
Sl.No. Make Current Motor (Kw & V)
& Description sec coil Voltage Voltage
1F INCOMER 1 121576 C&S 2500 1 220V DC 220V DC 220V AC/DC
10F INCOMER 2 121575 C&S 2500 1 220V DC 220V DC 220V AC/DC

Acceptance Criteria: Ratings, Make & Type shall be as per approved Drg.
3. IR Measurement

IR(Closed Condition) Results(O Remarks


Feeder
IdentificationNo. k/Not Ok)
& Description
R Y B

R-E R-Y Y-E Y-B B-E B-R


1F INCOMER 1 280M >1G >1G >1G >1G >1G OK
10F INCOMER 2 >1G >1G >1G >1G >1G >1G OK

Acceptance Criteria: There shall be no Short Circuit

NAME DESIGNATION SIGNATURE DATE


TEST ENGR. SURESH.M ENGR
BGRESL RATHINAKUMAR.D DPTY.MNGR
OPGCL PUNIT A.M
PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT ACBs


IDCT PMCC- 4A

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 2 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 28.06.17

Feeder Identification No. IR (Open Condition) Results


& Description R Y B (Ok/ Remarks
R-R Y-Y B-B Not Ok)
1F INCOMER 1 >1G >1G >1G OK
10F INCOMER 2 >1G >1G >1G OK

Acceptance Criteria: There shall be no Short Circuit

4 . Measurement of Closing Coil & Trip Coil Resistance

Coil Resistance(in )
Feeder Identification
Trip Coil Closing Coil Result (Healthy/Not Helathy)
No.& Description
1F INCOMER 1 89.4 91.2 OK
10F INCOMER 2 89.4 89.9 OK

Acceptance Criteria: There shall not be any open Circuit/ Interturn winding short (Value is for
reference)

5. CRM Measurement

IR (Closed Condition)
FeederIdentification No.
& Description R Y B Remarks
R-R Y-Y B-B
1R INCOMER 1 20 09 09 OK
10F INCOMER 2 09 10 10 OK

Note
This value is only for reference

NAME DESIGNATION SIGNATURE DATE


TEST ENGR. SURESH.M ENGR
BGRESL RATHINAKUMAR.D DPTY.MNGR
OPGCL PUNIT A.M
PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT ACBs


IDCT PMCC- 4A

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 3 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 28.06.17

6 .Breaker Operation

Acceptance: Trouble free operation


ACB (Manual & Electrical Operation)
Rack in Manual Manual Electrical Limit Counter Results Remarks
Feeder
& Rack (On/off) spring (On/Off ) switch(Te Operation
Identification (Ok/No
out Charging st
No. &
/Service/I t Ok)
Description
solate)

1F INCOMER1 OK OK OK OK OK OK OK
10F OK OK OK OK OK OK OK
INCOMER2

7. Indications

Feeder DC Spring Breaker Breaker Breaker Lockout CB CB in Breaker BUS BUS


Identification upply Charged On Off Trip relay in service Trip A- B-
No. & Healthy Healthy Test Pos. circuit U/V U/V
Description Pos. Healthy
1F OK OK OK OK OK OK OK OK OK OK OK
INCOMER1
10F OK OK OK OK OK OK OK OK OK OK OK
INCOMER2

Acceptance: Trouble free function of Indicators with regards to respective operation

8.Remarks

Test results of all the ACBs in the board found satisfactory.

NAME DESIGNATION SIGNATURE DATE


TEST ENGR. SURESH.M ENGR
BGRESL RATHINAKUMAR.D DPTY.MNGR
OPGCL PUNIT A.M
PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT ACBs


IDCT PMCC- 4A

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 4 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 28.06.17

NAME DESIGNATION SIGNATURE DATE


TEST ENGR. SURESH.M ENGR
BGRESL RATHINAKUMAR.D DPTY.MNGR
OPGCL PUNIT A.M