Item Description Qty Unit Tax Duties Unit Price (USD) Price (USD) Price (RM)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

4.

6 20% 20%
Unit Price Price Price
Item Description Qty Unit Tax Duties
(USD) (USD) (RM)
Zinc Ribbon
1 5.90 300 meter 1,770.00 8,142.00 1628.4 1628.4
Standarad size

Total Cost
Item Description Unit Price Qty Unit
(RM)
Permanent
2 350.00 18 pcs 6,300.00
Reference Cell
Concrete Test Post
3 600.00 12 pcs 7,200.00
c/w pole
4 Royston Handicap 25.00 24 pcs 600.00
5 Sleeve 3,000.00
6 2.5 mm cable 1.08 400 rolls 432.00
7 10mm PVC/PVC 4.50 300 rolls 1,350.00
8 25mm PVC/PVC 9.50 400 rolls 3,800.00
9 Cadweld charges 340.00
10 Polyken Primer 350.00
11 Conduit 200.00
23,572.00

35,890.80
4.6
Seafreight Total Cost
Charges (RM)
920.00 12,318.80
Item Description Daily Rate Duration Total Remark
1 CP supervisor 150.00 14 2,100.00 Contract
2 Helper 100.00 14 1,400.00 Contract
3 Helper 100.00 14 1,400.00 Contract
4 Engineer 150.00 14 2,100.00 HMS
7,000.00
Miscellaneous
6 Diesel 30.00 14 420.00
7 Toll 100.00
8 Meal 50 10 500.00
9 Tools 100.00
10 Backhoe 500 10 5,000.00
11 CIPS 1,000.00
12 DCVG 1,000.00
8,120.00

Summary

Material 35,890.80
Manpower 15,120.00
PGB 20,000.00
Total Cost 71,010.80
HMS 95,864.58
Profit 24,853.78
Margin 25.93 %
QUOTATION 96,000.00

Note
1. Two crossing of road crossing
SUMMARY

MATERIAL 35,890.80

MANPOWER 15,120.00

PGB 20,000.00

SUBCON 874,900.00 87,490.00 962,390.00 963,000.00