Milestones Description Milestone Criteria Planned Date

M0 Start Project Budget Release October 2017


PRS or SRS reviewed 5st October to
Stakeholders identified 12th October
Impl. Proposal reviewed
M1 Start Planning October 2017
Suppliers selection 13th October to
Quotation reviewing for 21th October
books
M2 Start Execution October 2017
Final Requirements 23th October to
agreed, project plan 31st October
reviewed, resources
committed
M3 Confirm Execution November 2017
Buying of books pcs 1st November to
shelfs 20th November
Racks chairs etc.
M4 Start Introduction & November 2017
construction
Start setup , construction 21st November
renovation lighting etc. to 15th January
M5 Final executing January 2018
Recruiting library staff test 16th January to
interviews , finalizing other 10th February
things too
M6 Testing the library February 2018
Pilot testing , making 12th February to
things under observation 16th February

M7 Training sessions

Giving introduction and 19th February to


training session to all , 28th February
telling how to operate
things
M8 Closing ceremony of project March 2018

Closing speech by a 1st march


special personal and guest

Note :- timeline is been made on average observation not a pessimistic nor optimistic
approach is been applied in this timeline