Professional Documents
Culture Documents
Nguyen-Chileshe BEPAM Paper
Nguyen-Chileshe BEPAM Paper
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/280231384
CITATIONS READS
5 311
2 authors, including:
Nicholas Chileshe
University of South Australia
224 PUBLICATIONS 567 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Reverse logistics supply chain and building information modelling: An integrated and standardised
approach for testing, grading and re-processing of salvaged construction industry products View
project
Designing for reverse logistics (DfRL) within the building life cycle: Practices, drivers and barriers View
project
All content following this page was uploaded by Nicholas Chileshe on 17 August 2015.
The user has requested enhancement of the downloaded file. All in-text references underlined in blue are added to the original document
and are linked to publications on ResearchGate, letting you access and read them immediately.
The current issue and full text archive of this journal is available on Emerald Insight at:
www.emeraldinsight.com/2044-124X.htm
BEPAM
5,4
Revisiting the construction
project failure factors in Vietnam
Tan Phat Nguyen
398 Viet Tan Trading Service and Construction Company Pleiku,
Gia Lai Province, Vietnam, and
Received 6 October 2013 Nicholas Chileshe
Revised 16 January 2014 School of Natural and Built Environments, University of South Australia,
5 June 2014
Accepted 4 August 2014 Adelaide, Australia
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
Abstract
Purpose The Vietnam construction industry has considerably developed since 1986 as a result of
Doi Moi or all-round renovation process. However, despite the pace of economic reforms, a number of
challenges continue to plague the construction industry. The purpose of this paper is to revisit
the factors causing construction project failure in Vietnam. Some of the selected best practices from
Brazil, Russia, India, China and South Africa (BRICS) and China, Indonesia, Vietnam, Egypt, Turkey,
South Africa (CIVETS) are discussed.
Design/methodology/approach Using a mixed method approach, data were collected from
construction stakeholders in Vietnam using a postal survey questionnaire and semi-structured interviews.
The quantitative data were subjected to descriptive statistics using ranking and frequencies analysis, and
qualitative data employed content analysis.
Findings Despite the lack of systematic approach to managing projects risks, there is a high level of
acknowledgement regarding the importance of risk management practices. The highly ranked critical
factors still causing construction project failure in Vietnam are: disregard of the significance of project
planning process and project planning; lack of experience in executing complicated project; poor
design capacity and frequent design changes; lack of knowledge and ability in managing construction
projects; lack of financial capacity of owner; poor performance of contractors; lack of a systematic
approach to managing the project and entire organisation; corruption and bribery in construction
projects; the delays in payment; and economic volatility and high inflation.
Practical implications The identified and revisited project failure factors could be used as a road
map for the revaluation, and development of appropriate project management practices.
Originality/value The construction sector has undergone through significant structural changes
following Doi Moi. This study provides the opportunity to realign the strategies for addressing
project failure factors and learning from comparative studies in BRICS and CIVETS countries.
Keywords Performance, Vietnam, Construction industry, Critical factors, Risk management,
Project management, Project failure
Paper type Research paper
1. Introduction
While factors causing failure of construction projects has been studied in other
countries, the revisiting of studies undertaken in the context of Vietnam deserves
particular attention. It cannot be denied that the Vietnam construction industry (VCI)
has grown considerably, and significantly contributed to the Vietnam economy during
Doi Moi (renewal) process. A study conducted by the National Institute for Urban
and Rural Planning and Tang (2004, cited in Anson et al., 2004), established that the
Built Environment Project and
Asset Management share of the industry and construction sectors increased by 7.6 per cent reflecting a
Vol. 5 No. 4, 2015
pp. 398-416
major structural change. Vietnams economy has been growing impressively for the
Emerald Group Publishing Limited
2044-124X
last two decades. The annual average rate of the economy has been at 7.3 per cent and
DOI 10.1108/BEPAM-10-2013-0042 the capital income increased fivefold from 1990 to 2010 (World Bank, 2011).
According to Uyen (2003, cited in Nguyen et al., 2004a), the VCI has been one of the Construction
main sectors contributing to the growth of the Vietnam economy in recent years. project failure
However, despite its contribution, the industry has been fronted with many difficulties
and constraints which negatively impact on the effectiveness of many construction
factors
projects. As demonstrated by Uyen (2003, cited in Nguyen et al., 2004a), 30 per cent of the
total construction capital is not used properly for construction purposes during project
duration because of poor project management. In Vietnam, construction projects are often 399
confronted with many complexities which often involve a range of uncertainties including
deadlines, additional cost targets and quality (Nguyen et al., 2004a). In order for the VCI to
improve and manage construction projects successfully and smoothly, there is a need of
re-visiting some of the problems causing construction project failure. Measures to redress
these challenges include the implementation of risk assessment and management
practices (Nguyen et al., 2004a, 2007).
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
2. Literature review
2.1 Overview and status of construction project management in Vietnam
There is a plethora of studies pointing to the construction project management-related
problems in Vietnam (Nguyen et al., 2004b; Luu et al., 2008a; Ling et al., 2009; Ling and
Hoang, 2010). By and large, some of the studies have reported on and acknowledged the
situation of poor management in construction projects in emerging countries, including
Vietnam (Luu et al., 2008a). In order to fulfil the second objective of the paper, namely
that of revisiting the factors causing construction failure through identification
and ranking, a literature review of the selected studies published during the period
2004 -2010 was undertaken. The results of this summary are shown in Table I.
The rationale and justification for selecting this time frame of 15 years after
the commencement of the Doi Moi renovation policies in 1986 was to enable the
full implementation and growth of the advocated policies. While the summary in
Table I shows the listing of the factors, the actual findings and nature of the selected
studies are incorporated within the discussion section for the ranking of the critical
factors.
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
5,4
400
Table I.
BEPAM
Critical factors
construction projects
causing the failure of
Studiesa,b
ID Critical factors causing the failure 1 2 3 4 5 6 7 8 No. AF (%) R
2.2 RM in construction projects in Vietnam and selected BRICS and CIVETS countries
Given the established linkages between RM and project success, the following 401
subsection provides a summary of the studies within the area of RM as conducted in
Vietnam. The majority of the studies conducted focused on delays and cost overruns in
projects; RM implementation (Nguyen et al., 2004a, b, 2007; Le-Hoai et al., 2008; Luu et al.,
2008b). These issues investigated have also attracted the interest of many researchers
and practitioners in BRICS and CIVETS countries. In addition, time and cost constraints
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
2.3 Review of selected project failure studies within the BRICS and CIVETS countries
The list of the selected comparative studies as drawn from BRICS and CIVETS
countries are summarised in Table II.
It should be acknowledged that while there is a plethora of studies on factors
causing failure of construction projects, this study only focused one CIVETS country,
namely Vietnam. Due to the similarities of these emerging economies, reference is also
made to some of the other studies conducted in those CIVETS countries. In making
the comparisons, the following assumptions as highlighted by Olawale and Sun
(2010, cited in Park and Papadopoulou, 2012) were considered, that:
While causes of cost overruns share common characteristics in projects worldwide, they are
also affected by country-specific conditions (Olawale and Sun, 2010, cited in Park and
Papadopoulou, 2012, p. 197).
BEPAM Studies/researchersa Country Context Aim of study and findings
5,4
Rwelamila et al. (2012) b, c
South BRICS/ See literature review section
Africa CIVET
Santoso et al. (2003) Indonesia CIVET Aimed at identifying, ranking and categorisation of
high-potential risks in high-rise building projects in
Jakarta. Established the need for the avoidance or
402 reduction of client interference combined with good
communication and teamwork between contractors
and consultants had the potential to minimise defects
Hassanein and Egypt CIVET This study was aimed at identifying the most
Afify (2007) significant risks relevant to construction contracts of
two power station projects in Egypt. One of the notable
finding was that contractors possessing past
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
The implication from the Olawale and Sun (2010) study is that, in achieving the third
objective of this current study, the significance attached to the ranking of the factors causing
construction project failure, and RM practices would need to be interpreted within the
prevailing country-specific environment and conditions. For example, as observed by
National Institute for Urban and Rural Planning and Tang (2004), the goals of the economic
reforms initiated in Vietnam in 1986 were aimed at creating a socialist-oriented market
economy which might be different from the prevailing economic policies in other CIVETS
and BRICS countries, as such the perceptions of the construction stakeholders on of the Construction
importance of RM practices, and of certain factors affecting the projects would be different. project failure
It is also acknowledged that the ability of these emerging economies to benefit from new
technological development varies considerably (Ruddock and Ruddock, 2012). For example,
factors
based on the three levels of technology capacity, China and India are considered as
Scientifically proficient whereas Brazil, Colombia, Indonesia, Turkey and South Africa fall
into the Scientifically developing countries (Ruddock and Ruddock, 2012, p. 35). 403
Closer examination of Tables I and II shows some similarities in the factors causing
construction project failure. For example, the factor of ambiguousness of contractual
terms and conditions (see Table V, ID: 14) has the potential of delaying construction
projects. This can be matched to the observations made by IIters (2012) study within
the context of Turkey which found that careful contractor selection (experience and
technical capability), adversarial approach in handling conflicts and communication
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
3. Research method
The research methodology adopted in this study is similar to that of von Meding et al.
(2013) and Kurniawan et al. (2014, p. 11) and included the following four steps: literature
review; pilot interviews; questionnaire survey; and statistical analysis. The justification
for adopting a mixed methods approach was to increase the reliability and validity of
the research (Easterbrook et al., 2008). The main purpose of the survey was to identify
and rank the revisited factors causing project failure in Vietnam; to examine the level of
importance, and determine the extent of usage and application of RM approaches and
techniques. Part of the interview was to provide feedback on the reoccurrence of
the construction project failure factors, and second, act as a reference for compiling the
survey questionnaire. Recent studies such as Kurniawan et al. (2014) have used such an
approach. The second rationale for conducting interviews was to achieve face validity.
BEPAM As opined by Lucko and Rojas (2010, p. 127), validation ensured that each phase of the
5,4 chosen research methodology adhered to the highest standards of quality, in addition
to allowing for a richer feedback.
3.4 Interviews
The interview process was carried out between September and October 2012, and held
in Ho Chi Minh City, the largest city in Vietnam. The duration of the interviewees which
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
lasted for 1-1.5 h was undertaken and conducted following five stages as suggested by
Birmingham and Wilkinson (2003, p. 44): draft the interview; pilot the interview
questions; select the interviewees; conduct the interviews; and analyse the interview
data. While it is beyond the scope of this paper to provide detailed information on each
of the stages, the following subsection presents a brief summary of some of the issues
associated with five highlighted stages.
A total of ten semi-structured interviews were conducted. The interviewees were
drawn from industry and academia. In meeting the first stage (see Wilkinson, 2003), a
set of criteria for drafting interview questions was undertaken. This was to ensure that
the questions posed were relevant to the research circumstance, comprehensive, easy to
understand as well as facilitate collecting useful feedback. In view of that, interview
questions were structured in the following distinct sections:
(1) background information;
(2) importance of RM;
(3) practice of RM; and
(4) constraints and risks.
The detailed information as posed in each section are presented and integrated within
the discussions of the findings.
3.4.1 Profile of the interviewees. Table IV presents the profile of the interviewees
according to the designations. The selection criteria for the interviewees are also
included in the footnote.
As can be seen from Table IV, the majority four (40 per cent) of the interviewees were
practicing project managers (interviewees A, B, I, and J). This had the potential of
enhancing the validity of the data as they are people (project managers) who profoundly
understand and provide the essential issues relating to the management of the projects in
practice. Relative to the working experience, the majority (50 per cent) of the interviewees
fell within the five to ten years category whereas an even number, two (20 per cent) were
in the one to five years and 11-15 years categories. Only a minority (one) of the
interviewees had been working in the construction industry for more than 20 years.
only interviewees located within the largest city in Vietnam, namely Ho Chi Minh City; the types of the
companies that the interviewees were involved with had to be listed as private companies or foreign
organisations operating in the Vietnam construction industry (VCI); commanders of construction
Table IV. projects implementing in Vietnam, and interviewees working for government bodies relating to the
Interviewee profile construction field
the VCI. However, while there is a fair representation of project managers, their
knowledge of project management issues might be affected by the lack of experience.
As demonstrated by McEnrue, there is a positive relationship between the length of a
managers job experience and objective indices of performance. Furthermore, it should
be pointed out that the majority of the state-owned and private organisations lack
requisite professional and managerial competencies to compete with foreign firms and
foreign professionals (Osabutey et al., 2012).
5. Survey results
5.1 Ranking of the critical factors causing construction project failure
In order to achieve the second objective of this study, this section presents a discussion
on the severity of the revisited factors. The total severity ranking scores (TSRS),
mean ranking score (MRS) and severity ranking index (SRI) were computed from the
following expressions.
5.1.1 TSRS:
X
max900
TSRS Wi
min45
where Wi is the TSRS assigned to the factor by the respondents, and r lies from 1 to
20, i.e. 1 o r o 20 (considering that the scale used in the questionnaire was a based on
the severity of extent sliding scale where 1 implies most serious and 20 implies least
serious). As such the minimum possible score that a factor could achieve was 45 (based
on the number of respondents), and the maximum 20 45 900.
5.1.2 MRS. The MRS were computed from the following expressions:
X
20
Wi
MRS
r1
N
Wi is the TSRS (min 20, max 900) obtained from the first expression; N the total Construction
number of the respondents (45 in this case). project failure
5.1.3 SRI. Based on the MRS, these ranged from 1 to 20. Finally, the SRI was factors
obtained by dividing the MRS with the total number of the critical factors (N 20)
as follows:
P
W 407
SRI
AN
where W is the ranking as assigned by each respondent in a range 1-20, where 1 implies
most serious, and 20 implies least serious; A the highest weight for the ranking (20); and
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
ID Critical factors causing the failure of construction projects TSRS MRS SRI R
(Table III) and the selected comparative studies from BRICS and CIVETS (Table II).
5.1.6 Poor design capacity and the frequent design changes. Poor design capacity
and the frequent design changes was the third ranked factor construction project
failure factor (MRS 8.36; SRI 0.418; TSRS 376). The importance of this factor is
further demonstrated by its frequency of citation in previous studies undertaken in
Vietnam (Table I), and has continued to affect the construction projects in Vietnam as
evidenced by previous studies (Le-Hoai et al., 2008; Luu et al., 2008a, b; Ling and Bui,
2010; Ling et al., 2009; Ling and Hoang, 2012).
5.1.7 Ranking of other construction project failure factors. Based on the MRS and
SRI, lack of knowledge and ability in managing the construction projects was the fourth
highest ranked. The implication of this finding is that despite the importance of project
management education in increasing the knowledge of the Vietnamese stakeholders, the
training of human resources for the VCI still remains problematic. This is further evidenced
by previous studies in Vietnam (Ling et al., 2009; Ling and Bui, 2010; Luu et al., 2008b). The
comparative studies on BRICS and CIVETS countries also drew similar findings. The fifth
jointly ranked factors were lack of knowledge and ability in managing the construction
projects and lack of financial capacity of owner. This finding is also consistent with
project failure factors literature on Vietnam (Ling et al., 2009) and within the BRICS and
CIVET countries (Hassanein and Afify, 2007; Shakantu, 2012). For example, Ling et al.
(2009) found that, Vietnamese construction companies are lagging behind foreign
companies not only in management capability, but also in financial capacity, experience in
complex projects, knowledge in advanced design and construction technology.
Based on the SRI, some interesting findings emerged. These two factors, corruption
and bribery in construction projects (SRI 0.476), and bureaucratic government
system in relation to regulations on project procedures (SRI 0.629) though were
ranked eighth and 17th, respectively, deserve to be singled out due to their importance
to the VCI and the BRICS and CIVET countries. Previous studies within the CIVETS
and BRICS countries have highlighted both factors as areas of concern (Nguyen et al.,
2004b; Ling and Hoang, 2010; Ofori, 2012; Rwelamila, 2012). One plausible
explanation for the improved ranking of corruption and bribery in construction
projects could be attributed to Vietnams involvement in the construction sector
transparency initiative (CoST) principles between 2008 and 2010. This CoST
initiative was designed to increase transparency and accountability in public-sector-
construction projects (Ofori, 2012). However, as opined by Ofori (2012, p. 83), in the
construction industry, ethics, professionalism and best practice are also words one
hears frequently these days.
BEPAM Further evidence of the contradiction results regarding the factor of bureaucratic
5,4 government system in relation to regulations on project procedures are provided by
Ling et al. (2009) and Ling and Hoang (2010) studies. Both highlighted the weaknesses
with the legal system in Vietnam. For example, Ling et al. (2009) identified some of
the problems as complicated and burdensome regulatory procedures which caused
severe difficulties and confusion for both local and foreign practitioners. However, the
410 interpretation of these findings should be treated with caution due to potential of the
bias. As can be seen from Table III, nearly a quarter (24.4 per cent) of the respondents
was drawn from the government departments and state-owned companies. As such,
there might be inflated responses from government officials about the highlighted
two factors.
In order to meet the first objective of the study, namely to investigate the RM
practices issues associated with construction projects in Vietnam, a number of
questions related to the importance, awareness and usage of RM were posed to both
the survey respondents and interviewees. The following sub-section presents
a summary of the findings.
5.2.1 Importance of RM. Based on the overall mean score (MS 4.556), the
respondents perception on the importance of RM was found to be very high.
The higher rating was distributed as follows: the majority 26 (57.7 per cent) of the
respondents rated this as very important, whereas 18 (40.0 per cent) rated this as
important. Only a minority, one (2.2 per cent) were neutral. This finding is highly
relevant given the linkages between effective RM practices and improved project
performance. The consequence of risks in Vietnam construction projects is similar to
common situations of construction projects worldwide (Hassanein and Afify, 2007).
5.2.2 Adoption and usage of RM practices. However, despite the high levels of
awareness of the importance of RM, this had not translated to the adoption and usage of
the techniques among the survey respondents and those interviewed. Totally, 50 per cent
of the survey respondents reported to have used RM approaches in managing their
projects. According to interviewee A, the importance of RM was overshadowed by
the difficulties associated with its application in practice. In addition, the following
challenges still existed: lack of project management capabilities; RM knowledge of
participants in managing construction projects; and stagnation of the management
system in the organisations. The findings from the interviews are also consistent with
RM studies in BRICS and CIVET countries (Li et al., 2007; Zou et al., 2010; Nkado, 2010;
Hassanein and Afify, 2007; Tabish and Jha, 2011; Wang and Yuan, 2011). For instance,
the Egypt study by Hassanein and Afify (2007) identified the contractors possessing
past experience as better placed to identify the relevant risk. Similarly, in China, Li et al.
(2007) singled out the cultural issues, whereas Li et al. (2007) highlighted the difficulties
with managing the awareness and attitude to risks. Furthermore, risk attitude has been
identified to be influenced by the experience of the practitioners (Wang and Yuan,
2011), thus highlighting the potential problems for VCI (Table III).
It was established from the interviewees that, their organisations lacked the
systematic approach to managing risk due to lack of knowledge and experience.
This was evident in the case of interviewee A and attributed the lack of expertise and
knowledge to his organisation failure to create a systematic approach to managing
risk through usage of tools and techniques. In contrast, interviewee J acknowledged the
progress made towards RM implementation. Some positive aspects of managing risks Construction
were further acknowledged by 50 per cent of the interviewees who identified project failure
insurance contracts for accidents during the project implementation phase as a way
to manage to risk.
factors
5.2.3 Responsibility for managing risk. Nearly half of the survey respondents
acknowledged having a department or individual responsible for RM. Interestingly,
despite this acknowledgement, the majority of the interviewees could not describe the 411
processes associated with the systematically management of risks during the project
duration. Some of the interviewees attributed this failure to the senior managements
lack of recognition of the benefits of RM. As observed by interviewee A, most the
leaders of the organisations did not recognise the benefits of RM. Rather, they executed
the projects until extreme risks occurred thereby leading to failure of projects and not
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
6. Recommendations
Drawing upon the approach used by Ling and Nguyen (2013) in providing
recommendations on waste management in Vietnam, some of the highly ranked
construction project failure factors (Table V), and prevailing best practices and strategies
found in BRICS and CIVETS countries (Table II), the following recommendations for
practitioners, government and academia in Vietnam are offered relative to the top ranked
construction project failure factors, and issues surrounding the awareness, usage and
adoption of RM parctices.
Previous studies in VCI also highlighted the significance of this ongoing challenge
(Table I) given the higher frequency of citation. Previous studies such as Ling and
Hoang (2012) recommended the adoption of appropriate procurement approaches by
the contractors, such as design and build would minimise late design changes.
The rationale being that the full responsibility for both design-and-build would be
transferred to the relevant stakeholders, such as the contractors.
7. Conclusion
By adopting a mixed methods approach through the provision of the feedback on the
reoccurring construction project failure factors, and analysing the questionnaire
survey, this has re-affirmed that the factors causing construction project failure have
not abated. Based on the generated statistics and categorisation of severity (Table V),
the following three factors were identified as critical (SRI 0.430): disregard of the
significance of project planning process and poor project planning, lack of experience in
executing complicated projects, and poor design capacity and the frequent design
changes. A comparison with other selected studies from the BRICS and CIVETS
countries (Table II) drew similar findings. The quantitative study further revealed
some interesting findings with the following construction project failure factors
considered as the less severe: the ineffectiveness in resolving disputes and conflicts Construction
among project stakeholders; the instability and inefficiency of government policies and project failure
legal system; and low ethics in doing business of project participants. While strides
have been made in acknowledging the importance of RM practices, only half of the
factors
respondents used RM approaches in managing their projects. This suggests that,
regardless of the advocated and noted benefits of systematic RM (Zou et al., 2010),
the adoption and usage of the RM concept continues to draw little attention for 413
construction projects in Vietnam.
potential for the realignment the strategies for addressing project failure factors and
learning from comparative studies in BRICS and CIVETS countries, as well as
re-thinking the prevailing strategies post Doi Moi renovation. The second
contribution lies within the proposed levels of classification of the severity of
construction project failure factors in VCI. The proposed indices such as SRI, MRS,
and TSRS as computed (Table V) could help the practitioners to gain a better
understanding of the extent of severity of the construction project failure factors.
By enhancing their knowledge regarding the severity, appropriate strategies for
overcoming them could thus be developed.
There are a number of ways in which this research has implications for research,
practice and society. First, practitioners and stakeholders can use the findings for
developing appropriate strategies in overcoming the project failure factors. By drawing
upon some best practice from CIVETS and BRICS countries, the identified and
revisited project failure factors could be used as a road map for the re-development of
appropriate project management practices, such as RM techniques.
Second, given the lack of awareness and limited usage of RM practices and
approaches, practitioners can map the existing levels awareness of RM practices with
usage among the construction stakeholders within the VCI, and identify the best
practices from corresponding BRICS and CIVETS countries.
construction projects, International Journal of Law in the Built Environment, Vol. 4 No. 1,
pp. 45-59.
Kurniawan, F., Ogunlana, S. and Motawa, I. (2014), Stakeholders expectations in utilising
financial models for public-private partnership projects, Built Environment Project and
Asset Management, Vol. 1 No. 1, pp. 4-21.
Le-Hoai, H.L., Lee, Y.D. and Jun Yong Lee, J.Y. (2008), Delay and cost overruns in Vietnam large
construction projects: a comparison with other selected countries, KSCE Journal of Civil
Engineering, Vol. 12 No. 6, pp. 367-377.
Li, J., Li, B., Lin, B. and Nguyen, V. (2007), Key issues and challenges of risk management and
insurance in Chinas construction industry, Industrial Management & Data Systems,
Vol. 107 No. 3, pp. 382-396.
Ling, F.Y.Y. and Bui, T.T.D. (2010), Factors affecting construction project outcomes: case study
of Vietnam, Journal of Professional Issues in Engineering Education and Practice, Vol. 136
No. 3, pp. 148-155.
Ling, F.Y.Y. and Hoang, V.T.P. (2010), Political, economic, and legal risks faced in international
projects: case study of Vietnam, Journal of Professional Issues in Engineering Education
and Practice, Vol. 136 No. 3, pp. 56-164.
Ling, F.Y.Y. and Hoang, V.T.P. (2012), Project risks faced in international construction projects
in developing countries: case study of Vietnam, in Ofori, G. (Ed.), Contemporary Issues in
Construction in Developing Countries, Spoon Press, Taylor & Francis, London and
New York, NY, pp. 347-375.
Ling, F.Y.Y. and Nguyen, D.S.A. (2013), Strategies for construction waste management in Ho Chi
Minh City, Vietnam, Built Environment Project and Asset Management, Vol. 3 No. 1,
pp. 141-156.
Ling, F.Y.Y., Pham, V.M.C. and Hoang, T.P. (2009), Strengths, weaknesses, opportunities, and
threats for architectural, engineering, and construction firms: case study of Vietnam,
Journal of Construction Engineering and Management, Vol. 135 No. 10, pp. 1105-1113.
Liu, J., Li, B., Lin, B. and Nguyen, V. (2007), Key issues and challenges of risk management and
insurance in Chinas construction industry an empirical study, Industrial Management
& Data Systems, Vol. 107 No. 3, pp. 382-396.
Lucko, G. and Rojas, E.M. (2010), Research validation: challenges and opportunities in the
construction domain, Journal of Construction Engineering and Management, Vol. 136
No. 1, pp. 127-135.
Luu, T.V., Kim, S.Y. and Huynh, T. (2008a), Improving project management performance of
large contractors using benchmarking approach, International Journal of Project
Management, Vol. 26 No. 7, pp. 758-769.
Luu, T.V., Kim, S.Y., Cao, H. and Park, Y. (2008b), Performance measurement of construction Construction
firms in developing countries, Construction Management and Economics, Vol. 26 No. 4,
pp. 373-386.
project failure
National Institute for Urban and Rural Planning and Tang, B.S. (2004), Vietnam, in Anson, M.,
factors
Chiang, Y.H. and Raftery, J. (Eds), The Construction Sector in the Asian Economics, Spoon
Press, Taylor & Francis, Abingdon and New York, NY, pp. 359-487.
Nguyen, L.D., Ogunlana, S. and Lan, D.T.X. (2004a), A study on project success factors in large 415
construction projects in Vietnam, Engineering, Construction and Architectural
Management, Vol. 11 No. 6, pp. 404-413.
Nguyen, L.D., Ogunlana, S., Truong, Q. and Lam, K.C. (2004b), Large construction projects in
developing countries: a case study from Vietnam, International Journal of Project
Management, Vol. 22 No. 7, pp. 553-561.
Nguyen, V.T., Ogunlana, S.O. and Dey, P.K. (2007), Risk management in oil and gas construction
Downloaded by University of South Australia At 15:07 17 August 2015 (PT)
Zou, P.X.W., Chen, Y. and Chan, T. (2010), Understanding and improving your risk management
capability: assessment model for construction organizations, Journal of Construction
Engineering and Management, Vol. 136 No. 8, pp. 854-863.
Further reading
McEnrue, M.P. (1988), Length of experience and the performance of managers in the
establishment phase of their careers, The Academy of Management Journal, Vol. 31 No. 1,
pp. 175-185.
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com