This document provides details on the concrete and formwork requirements for the expansion of Robinsons Place Ilocos Norte located in San Francisco, Ilocos Norte. As of May 28, 2015, 3,870 cubic meters of concrete had been poured, leaving a balance of 15,215.6 cubic meters to be poured over the remaining 24.4 weeks at a target rate of 622.9 cubic meters per week. The formwork requirements total 45,441.9 square meters with a weekly target of 1,272.4 square meters. A total manpower of 640.7 men is required, with a start date of March 9, 2015 and finish date of November 14, 2015 for the topping off of
This document provides details on the concrete and formwork requirements for the expansion of Robinsons Place Ilocos Norte located in San Francisco, Ilocos Norte. As of May 28, 2015, 3,870 cubic meters of concrete had been poured, leaving a balance of 15,215.6 cubic meters to be poured over the remaining 24.4 weeks at a target rate of 622.9 cubic meters per week. The formwork requirements total 45,441.9 square meters with a weekly target of 1,272.4 square meters. A total manpower of 640.7 men is required, with a start date of March 9, 2015 and finish date of November 14, 2015 for the topping off of
This document provides details on the concrete and formwork requirements for the expansion of Robinsons Place Ilocos Norte located in San Francisco, Ilocos Norte. As of May 28, 2015, 3,870 cubic meters of concrete had been poured, leaving a balance of 15,215.6 cubic meters to be poured over the remaining 24.4 weeks at a target rate of 622.9 cubic meters per week. The formwork requirements total 45,441.9 square meters with a weekly target of 1,272.4 square meters. A total manpower of 640.7 men is required, with a start date of March 9, 2015 and finish date of November 14, 2015 for the topping off of
LOCATION : Brgy. 1, San Francisco, San Nicolas Ilocos Norte
SUBJECT : Concrete and Formworks Requirements DATE : 27 May 2015
CONCRETE WORKS QTY. UNIT REMARKS
Total Concrete Volume 19,085.6 cu.m.
Concreted as of May 28, 2015 3,870.0 cu.m. Balance Concrete Volume 15,215.6 cu.m. No. of Weeks Required 35.7 wks. Start Date to Topping of Remaining Weeks 24.4 wks. To date to Topping of Weekly Target 622.9 cu.m. Base on the balance volume Cement per week 9,965.8 bags FORMWORKS QTY. UNIT
Total Formwork Requirements 45,441.9 sq.m.
Weekly Formworks 1,272.4 sq.m. Projected Formworks Requirements 6,361.9 sq.m. Assume 5 Rotations of Forms
MANPOWER QTY. UNIT
Formworks Capacity 2.4 MH/m
Total Manhour per Week 2,990.1 MH Manpower (8-hr per Week) 53.4 Men Manpower Req't 160.2 Men 1:2 (Carp:Labor) 4 Portion Preparation, 1 Portion Total Requirement 640.7 Men Stripped
Start Date March 09, 2015
Finish Date/ Topping of November 14, 2015 ### PROJECT : Robinsons Place Tuguegarao SUBJECT : Concrete and Formworks Requirements DATE : 9 February 2017
CONCRETE WORKS QTY. UNIT REMARKS
Total Concrete Volume 24,900.0 cu.m.
Concreted as of February 9, 2017 8,601.0 cu.m. Balance Concrete Volume 16,299.0 cu.m. No. of Weeks Required 49.9 wks. Start Date to Topping of Remaining Weeks 19.4 wks. To date to Topping of Weekly Target 838.9 cu.m. Base on the balance volume Cement per week 13,422.7 bags FORMWORKS QTY. UNIT
Total Formwork Requirements 59,285.7 sq.m.
Weekly Formworks 1,189.1 sq.m. Projected Formworks Requirements 5,945.6 sq.m. Assume 5 Rotations of Forms Total Formwork Delivered on Site 8,400.0 sq.m. Installed Formworks 6,000.0 sq.m. On Rotation Unused Formworks 2,400.0 sq.m.
MANPOWER QTY. UNIT
Formworks Capacity 2.4 MH/m
Total Manhour per Week 2,794.4 MH Manpower (10-hr per day per Week) 40 Men Manpower Req't 120 Men 1:2 (Carp:Labor) 4 Portion Preparation, 1 Portion Total Requirement 479 Men Stripped