Work Planning For - Consultancy Service To Examine .Becharaji - Chanasama - Ranuj Rly Gauge Conversion
Work Planning For - Consultancy Service To Examine .Becharaji - Chanasama - Ranuj Rly Gauge Conversion
Work Planning for Consultancy service to examine.Becharaji -Chanasama - Ranuj Rly Gauge conversion
Tendered Amount Rs. = 2,13,000,00.00 Length of line 65.0 km Work Order given on - 08-11-2017
Time limit 3 months meter gauge to Broad gauge
Sr.No. Activity Month November December January February March
Stage Stage-1A Stage-1B Stage-2A Stage-2B Stage-3A Stage-3B
Date 08-13 14-21 22-30 01-07 08-15 16-23 24-31 01-07 08-15 16-23 24-31 01-07 08-15 16-23 24-29 01-07 08-15 16-23
Quantity
Stage -1 Prepare QAP
Collection of data
Review of data
Reconnissance Survey
Preperation of LS & CS
Location Survey
Stage-2A
Technical fesibility Report
(Draft)
Stage-2B
Technical fesibility Report
(Final)
Preperation of Drawings
Estimation work
Specification & RA
Stage-3B
Detailed Project Report
(Final)
An
Work Planning for Consultancy service to examine.Becharaji -Chanasama - Ranuj Rly Gauge conversion
Tendered Amount Rs. = 2,13,000,00.00 Length of line 65.0 km Work Order given on - 08-11-2017
Time limit 3 months meter gauge to Broad gauge
Sr.No. Activity Month November December January February March
Stage Stage-1A Stage-1B Stage-2A Stage-2B Stage-3A
Date 08-13 14-21 22-30 01-07 08-15 16-23 24-31 01-07 08-15 16-23 24-31 01-07 08-15 16-23 24-29 01-07
Quantity
Stage -1 Prepare QAP
Collection of data
Review of data
Reconnissance Survey
Total Station
Fixing TBM/PBM
Drilling
Sampling
Testing
Reporting
Testing of Samples
Preperation of LS & CS
Preparing of LS
Preparing of CS
Location Survey
ROB
RUB
Signaling
ROB
RUB
Signaling
Stage-2A
Technical fesibility Report
(Draft)
Stage-2B
Technical fesibility Report
(Final)
ROB
RUB
Signaling
Preperation of Drawings
ROB
RUB
Signaling
Station Yard
Estimation work
ROB
RUB
Signaling
Station Yard
Specification & RA
Stage-3A
Detailed Project Report
(Draft)
Stage-3B
Detailed Project Report
(Final)
Annexure-1
March
Stage-3B
08-15 16-23
1/16/2017 2/5/2017
3/2/2017 S2
6/10/2017 S3
7/15/2017 S4