Professional Documents
Culture Documents
Voltage Sag in Three Phase System
Voltage Sag in Three Phase System
Voltage Sag in Three Phase System
Bollen
Voltage Sags
in Three-Phase Systems
A voltage sag is a short-duration (up to a few
sseconds) reduction in voltage magnitude.
The voltage temporarily drops to a lower value,
e.g., from 230 V down to 170 V, and comes back
again after approximately 150 ms. Despite their
short duration, such events can cause serious
problems for a wide range of equipment. Pro-
cess-control equipment, computers, and adjust-
able-speed drives are most notorious for their
sensitivity.
Voltage sags are a three-phase phenomenon, in
which all three-phase voltages are involved and
sometimes even the neutral-to-ground voltage. In
this article, we will only consider the phase volt-
ages.
Note that most publications introduce a volt-
age sag as a drop in voltage in one phase. The
three-phase aspects are introduced later as a kind
of anomaly. Such a description fits single-phase
loads and single-phase laterals in rural distribu-
tion systems. But most of the power system is
three phase, and the loads that have the biggest
problems with voltage dips, i.e., adjustable-speed
drives, are three-phase loads. In such cases, a
more general description is needed. In this article,
voltage sags will be treated as a three-phase phe-
nomenon from the beginning. Such a three-phase
approach will also make it easier to understand
what happens with single-phase loads.
events per year more severe than a given magnitude and dura- Improvements in the power system
tion. A system index is typically a weighted average of the sites Mitigation at the interface between system and load
for which information is available. The ongoing activities in dif- Improving end-use equipment.
ferent working groups are a balancing act between the need to Reducing the number of faults tackles the problem at the
have indices that are suitable for a wide range of customers and source. It will not only reduce the number of voltage sags but,
loads, and on the other hand a small number of indices. Ideally, especially for distribution systems, also the number of interrup-
one would like to be able to capture the voltage sag performance tions. This is not always an easy task, and the costs could be very
of a system in one single index; something like the THD for high. Keep in mind that voltage sags at a certain location can be
waveform distortion. due to faults at distances up to hundreds of kilometers.
When collecting data to calculate site and system indices Improving the power system does not reduce the number of
(typically event magnitude and duration), two fundamentally voltage sags, but it makes them less severe. An apparently
different methods are being used. Statistical methods observe straightforward method is to reduce the fault clearing time.
the behavior of the system and calculate averages from the ob- Again, this may require large investments at the transmission
servations. This requires a certain number of monitors that ob- level. At the distribution level, the margin for speeding up is
serve the system for a certain time. To get accurate results, a much larger, although it may increase the risk of protection
large number of monitors and a long measurement period are maloperation. A method used regularly in distribution networks
needed. Monitoring will always give the real picture, but the re- is to remove long overhead feeders from busses feeding sensi-
sults have limited application for other locations and for future tive loads. Other system improvements, such as adding multiple
prediction. infeeds and strategically locating generators, are normally only
10 IEEE Power Engineering Review, September 2001
Normal Backup
Supply Supply
100 I II
Faults in Other Motors + Transformers
A B
50 Faults in Other
Distribution
Networks C
Fuses
1 2 3
Interruptions
0
0.1 1
Duration (Seconds)
1 2 3
Figure 6. Voltage sags and interruptions, different origins Figure 8. Principle of the static transfer switch
feasible in industrial systems. A solution often neglected in the 100 ms, are mainly due to faults in the transmission system. Mit-
literature is system grounding. Using high-impedance ground- igating these at the system side is very difficult, whereas mitiga-
ing will prevent voltage sags due to single-phase faults from tion at load side is possible in most cases. The same holds for the
propagating through a Dy-transformer. This is common practice shallow events: switching of motors and transformers, remote
in European distribution and subtransmission systems as well as distribution system faults. Preventing an individual event is not
in many industrial systems. very difficult, but there are simply too many remote locations to
The most commonly used method is to install additional cover them all.
equipment at the system-load or system-customer interface. Ex- On the other side of the chart, it is very difficult to make
amples are the UPS (a must for any essential low-power equip- equipment immune to interruptions, whereas system-side solu-
ment, but batteries become a problem for larger load), the tions are easier (albeit not always cheap). The majority of inter-
motor-generator set (sometimes forgotten, but still an excellent ruptions originate in the distribution network. Reducing the
alternative), the ferroresonance transformer, the dynamic volt- number or duration of interruptions requires improvements in
age restorer (DVR), and the static-transfer switch. The latter two the distribution network.
solutions are discussed in more detail. From this reasoning, the following general guidelines can be
Improving end-use equipment has a larger potential than of- extracted: sags down to 75%, 100 ms should be solved by equip-
ten thought, but a combination of factors has kept this potential ment improvement; sags from 60%, 500 ms and more severe
untapped. The result is that the customer is often left with just should be solved by system improvement. Anything in between
one option: installing mitigation equipment. is worth discussing. In the future, these two limits should move
In Figure 6, different origins of voltage sags are indicated in a towards each other, e.g., through an equipment immunity stan-
magnitude-duration plot. For completeness, interruptions are dard.
also indicated. The events with the shortest duration, up to about A recently introduced solution for mitigating voltage sags for
large loads is the DVR. The principle is shown in
Figure 7. The voltage sag in the system is miti-
2
x 104
gated by injecting the difference between the de-
1.5
sired voltage and the actual voltage. This
1
0.5
Injected
injection requires a power-electronics converter,
0
Voltage a high-power source of energy, and a fast control
0.5
1
system. Sources of energy currently in use
1.5 include capacitors and superconducting coils.
2
0 200 400 600 800 1000 1200 1400 1600 To mitigate long and deep sags, a large energy
Voltage Sag Constant Load reservoir is needed.
in the System Voltage
2
x 104
x 104
Another rather new solution is the very fast
1.5
2
1.5
medium-voltage transfer switch (see Figure 8).
1
1 When a voltage sag (or interruption) occurs in
0.5
0
VSC 0.5
the supply, the load is switched to the alternate
0
0.5
0.5
supply. Using thyristors will give a transfer time
1
1.5
1 less than one cycle (manufacturers claim 4 ms),
1.5
2
0 200 400 600 800 1000 1200 1400 1600 2
whereas using vacuum switches will take one or
0 200 400 600 800 1000 1200 1400 1600
Energy
two cycles for the transfer. The transfer switch
Storage cannot mitigate sags that originate in the trans-
mission system, as those will affect both feeders. The two-cycle [2] M.H.J. Bollen, Understanding Power Quality ProblemsVoltage
switch can be combined with 100-ms energy storage against Sags and Interruptions. Piscataway, NJ: IEEE Press, 2000.
transmission system sags. [3] L.E. Conrad and M.H.J. Bollen, Voltage sag co-ordination for reli-
able plant operation, IEEE Trans. Ind. Applicat., vol. 33, pp.
The Future 1459-1464, Nov. 1997.
Solving the voltage sag problem requires cooperation between [4] L.E. Conrad, K. Little, and C. Griff, Predicting and preventing
utilities and end-users, with support from equipment manufactur- problems associated with remote fault-clearing voltage dips, IEEE
ers and standards-setting organizations. It is possible to make Trans. Ind. Applicat., vol. 27, pp. 167-172, Jan. 1991.
better equipment when the demand for it is high enough. Stan- [5] M.F. McGranaghan, D.R. Mueller, and M.J. Samotej, Voltage sags
dards are needed that guide utilities, end-users, and equipment in industrial power systems, IEEE Trans. Ind. Applicat., vol. 29, pp.
manufacturers. It is also important that everybody becomes aware 397-403, Mar. 1993.
of voltage sags as a potential problem. Education of electrical and [6] L. Zhang and M.H.J. Bollen, Characteristic of voltage dips (sags)
mechanical engineers is very important to achieve this aim. in power systems,IEEE Trans. Power Delivery, vol. 15, pp.
827-832, Apr. 2000.
Further Reading
[1] M.H.J. Bollen, Characterisation of voltage sags experienced by
three-phase adjustable-speed drives, IEEE Trans. Power Delivery,
vol. 12, pp. 1666-1671, Oct. 1997.