Professional Documents
Culture Documents
RBI For Ageing Plant PDF
RBI For Ageing Plant PDF
RBI For Ageing Plant PDF
Managing ageing plant through inspection. All of this activity, which is meant
to ensure plant integrity, is carried out
www.hazardexonthenet.net
Ageing plant 29
RBI Method
The actual methodology used to carry out
RBI studies can be taken from the best
practice published by the Health and Safety
Executive (HSE): CRR 363/2001; Best
practice for risk based inspection as a part
of plant integrity management [1]. The
overview process for conducting an RBI is
shown in Figure 1.1. The discussion of each
stage can be found in reference [1].
atmospheric air introduced to the system Using site knowledge and expertise from
when inspecting produces corrosive the inspection company, all potential
sulphuric acid. This serves to diminish degradation mechanisms were then formally
plant ageing. assessed. A sample of the assessment is
99 Reduce exposure of personnel shown in Table 1.
(inspectors and operators) to toxic
atmospheres arising from inspections. Vessel History
99 Achieve financial savings; realised from The historical inspection records for
reducing the need to facilitate an internal the vessel were reviewed; all inspection
inspection every two years which requires certificates and comments were studied in
logistical costs and irreversible damage to detail and taken into account as part of the
the filter causing approximately 10,000 assessment. Furthermore, other identical
in parts costs. vessels in other production lines as well as
those in other sister plants were taken into
Team consideration. The main conclusions were:
The study was carried out in several 99 The only known degradation mechanism
meetings over a period of a month. The is internal corrosion.
RBI in Action team included the site Maintenance Leader, 99 This corrosion is mainly concentrated at the
A real-life example of applying the RBI Process Safety Leader, an Operator and an bottom half of the vessel and at tangents
method is given but it is for demonstration expert from the inspection company. The to the filters on the shell of the vessel.
purposes and so does not include the entire final document was then approved by the 99 The vessel appears to have a life of 10-
assessment details. Principal Engineer of the inspection company. 12 years before requiring refurbishment
work.
An RBI study was carried out on a large
(>11 cu.m.) mist-eliminator pressure vessel Degradation Mechanism Identification & Assessment
in a Sulphonation process subject to
Description: Mist Eliminator for Sulphonation Plant on Train 1.
Material of Construction : Carbon Steel
a review of the process, the historical and 1 Corrosion Internal -Loss of wall thickness -Internal corrosion allowance by
design
-Develop full
thickness
-Moisture in process air reacting with -Vessel failure and loss of
current condition of the vessel, a mechanical SO3 to produce sulphuric acid.
Problem cited is exacerbated
containment -Vessel inside building inspection
program
-Personnel injury due to (protection against CUI)
integrity risk assessment and a proposal for with over temp.
toxic exposure -Routine external inspection by
-During shut downs when opening operators
-Production loss
inspection based on the RBI method. vessel to atmosphere and
introducing the system to moist
-Periodic statutory inspections
air which reacts to produce -Restricted access to area
sulphuric acid -Emergency shutdown
The main reason for the RBI study was to External procedures
-Corrosion under insulation (CUI)
explore the feasibility and scope in reducing -Exposed areas in-contact with
atmospheric conditions
internal visual inspections. This in turn would 2 Fatigue -Cycling (pressure/temperature) -Similar to consequences -Inherent safety; stable running
loading during start-up. of No.1 except no temperatures.
lead to other benefits: -Physical vibration arising from nearby loss of wall
thickness.
-Continuous running with
equipment minimal few shutdowns per
99 Decrease the risk of internal corrosion year.
-Vessel isolated from nearby
by minimising air exposure, because plant.
Embrittlement,
the reaction chemistry between the Creep, Buckling etc.
www.hazardexonthenet.net
30 Ageing Plant Probability of Failure
Ageing plant 31
Consequence of Failure
Highly Very
Probable Possible Unlikely
Probable Unlikely
Very High
High Probability of Failure Given the vessel is located inside a building Recommendations & RBI can lead to profitable operations through and so care should be taken in ensuring a
Conclusions
Consequence of Failure
HighlyModerate Very
Probable
Probable Possible Unlikely
Unlikely which requiresofauthorisation
Probability Failure for access; it effective maintenance and should be part competent team is formed before making
Probability Probability
Probability
of Failure ofof Failure
Failure
Low was rated as 1. All plants are subject to ageing, and of an integrated strategy for managing the radical changes. Further reading can be
Failure
Highly Very
Failure
Very High Highly Probable Possible Unlikely Very
Consequence of Failure
Failure
Highly Highly Probable ProbableProbable Probable Possible Very Very
Unlikely Unlikely
High
Very Low Probable
ProbableProbable
Possible Possible UnlikelyUnlikely Unlikely
UnlikelyUnlikely addressing this risk should be seen as an risk of ageing plants. Implementing the RBI found in CRR 363/2001.
Very High Similarly, the consequence rating for all opportunity to interrogate the inspection methodology does require expertise
ofof
Table
Moderate 2: Risk matrix used for the assessment VeryHigh High Probability of Failure
Very High Very
of Failureof
Consequence
High
other categories Possible(i.e. impact on production, regime of the plant. Currently, statutory
Consequence
Highly Very
Consequence
Low High
Rating
High High
Description Moderate Probable
Probable Unlikely
Unlikely References
Very Low Moderate Moderate
Moderate hazards of material etc.) was considered. inspections of pressurised equipment are 1. CRR 363/2001, Best practice for risk based inspection as a part of plant integrity management, HSE.
Highly probable Allowable lossVery is already
Low High used up
Table 2: Risk matrix used for the assessment Low Low
Low These ratings were added up and the total prescriptive and under the influence of 2. SAFeds Approach to Ageing Plant, May 2012, Miles Gardiner.
Consequence
Table 2: Risk matrix
Probable used for the assessment
remaining life 3 - 5 years High
Very Low
Very Low 3. RR823, Plant Ageing Study; Phase 1 Report, 2010 HSE.
Possible remaining life ratings
5 7 years given
Very Low in Table
Very
ModerateLow 3 also correspond to was 15 (i.e. High using Table 3). an over-commoditised industry. The Duty
Risk Assessment
Rating
Highly probable
Unlikely remaining life
Description
Allowable loss is already
a Table 2: Risk matrix
description
Table
2:7 Table
Table used 2:
10matrix
Risk Risk
years matrix
up 2: Riskused
Low used
which
matrix
for the is
used
for the assessment
identical
for
usedassessment the to that
assessment
for the assessment given Holders best course of action is to question
Very Low
The riskremaining
Probable assessment
Very unlikely
life was carriedremaining
3 - 5 years out using
life in theyears
> Rating
10 5x5 risk matrix (Table 2),Description and thus the Taking the results from the probability of the WSE they are following and ensure it
Rating Rating Rating Description Description
a semi-quantitative approach: the 5x5 risk overall
Table 2:
Highly risk Risk
probable can be
matrix used for theDescription
determined. assessment
Allowable loss is alreadyfailureused (Unlikely)
up and consequence of failure calls for a level of inspection which highlights
Possible remaining life 5 7 years ProbabilityHighly Highly probable
of Failureprobable
Highly probable Allowable Allowable
Allowable
loss is already lossisused
loss isalready
already
up used usedupup
Probable remaining life 3 - 5 years
matrix remaining
Unlikely shown inlife table 2: 7 10 years Probable
Rating remaining life 3 - 5 years
Description (High), and using Table 2 the overall risk the degradation mechanisms that are really
Consequence of Failure
Conduct thorough internal inspection once every five years in alignment with the
Consequence of Failure
filter change. Internal inspection shall be carried out in June 2014, or at the
first opportunity where the vessel is available for internal inspection if before
The consequences then.of failures were similarly
assessed using guide words given in
General Condition,
the practice
Fatigue, ... etc. and then rated numerically.
The consequences considered different
categories which included: location and
personnel, impact on production, and others
which took into account fluid pressures,
temperatures and hazards.
www.hazardexonthenet.net www.hazardexonthenet.net