Task Name Start End Duration

(days)

Discussion about title and detail 10/9/2017 14/9/2017 4


Fill up the proposal on online and discuss with 15/9/2017 21/9/2017 6
supervisor
Do research and reading through journal, books, and 22/9/2017 28/9/2017 6
article
Drafting for the chapter 1,2 and 3 29/9/2017 5/10/2017 6
Finish and prepare the chapter 1,2 and 3 6/10/2017 12/10/2017 6
Fix and discuss the writing and methodology 13/10/2017 19/10/2017 6
Testing and analysis through laboratory testing 20/10/2017 26/10/2017 6
Analysing data and collect tine information 27/10/2017 2/11/2017 6
Drafting finalize for the chapter 1,2 and 3 3/11/2017 9/11/2017 6
Preparation for final stage of FYP 1 10/11/2017 16/11/2017 6
Submit the proposal for FYP 1 17/11/2017 23/11/2017 6
Preparation for presentation 24/11/2017 30/11/2017 6