Professional Documents
Culture Documents
Construction of A High Voltage Test Facility: W. Mcdermid, J.G. Lambert
Construction of A High Voltage Test Facility: W. Mcdermid, J.G. Lambert
Abstract Manitoba Hydro has constructed a facility for 60 Hz Series Resonant Test Supply
dielectric testing of equipment rated up to 500 kVac and
500 kVdc. A test system for induced, no-load and full load tests The 60 Hz series resonant test supply is rated 800 kV. When
on large power transformers is being added. tuned for the maximum capacitance the current rating is 5 A.
Fig. 2 shows the 60 Hz series resonant test supply under test at
I. INTRODUCTION the manufacturers facility.
The high voltage test facility was constructed to enable
dielectric testing of instrument transformers, bushings and
aerial devices rated up to 500 kVac and 500 kVdc. The facility
also provides for the full electrical testing of power
transformers rated up to 500 kV 310 MVA 3-phase and 400
MVA 1-phase. The applications are new equipment following
transport and service aged equipment that is being evaluated
for re-use. The objective is to minimize forced outages
associated with in-service failures involving lost revenue and
consequential damage as well as to improve safety. Further
details on rationale for the construction will be found in [1].
Impulse Generator
The impulse generator is rated 2400 kV 360 kJ. It is suitable Figure 2. 800 kV series resonant supply under test
for 2200 kV lightning impulse and for +1300 kV and
-1500 kV switching impulse. Fig. 1 shows the impulse
generator under test at the manufacturers facility. Direct-voltage Test Supply
2009-09-17
Core Tower
The core tower contains the stairway to the roof of the Test
Hall as well as the elevator shaft to the elevation of the cat
walk immediately above the bridge crane in the Test Hall. Re-
usable forms were employed for the core tower which was
Figure 4. Completion of driving piles for Test Hall
poured in seven stages. Fig. 7 shows the pouring of the final
stage on 20 May 2010.
Figure 9. Bonding of wire ropes in pile
Erection of the columns and roof trusses for the Test Hall
began in October 2010 and was completed in March 2011.
Fig. 8 shows the structure as of 5 November 2010. Note the
12 m x 12 m doorway into the Test Hall for rail access.
Figure 10 Bonding of re-bar laps in lower course of reinforcing steel
2010-11-05
Following the completion of the structural floor the copper
ground mat was put in place. This consists of AWG #6 solid
copper wire spaced 100 mm as is shown in Fig. 11. All piles
are bonded to the ground mat as are 72 equally spaced
grounding points in the super flat topping slab one of which is
shown in Fig. 11. The super flat floor facilitates the use of air
cushions for moving equipment within the Test Hall.
Electrical Bonding
IV. CONCLUSIONS
The Test Hall will be in use early in 2012 for the dielectric
testing of instrument transformers, bushings and aerial devices
Figure 12. Bonding of interior liner panels from outside every 600 mm followed later in the year by full electrical testing of power
transformers.
Heating of Test Hall