Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

MBAM SECTION

Your Contractual Question Answered

What are Preliminaries and How to Evaluate Them?


By The Entrusty Group

Entrusty Group, a multi-disciplinary group of companies, of which, one of their specialisation is in project,
commercial and contractual management, has been running a regular contractual questions and answers section
for Master Builders member in the Master Builder Journal

In this instalment of this series, Entrusty Group will provide the answer to another frequently asked question:-
What Are Preliminaries and How to Evaluate Them?

Introduction additional preliminaries to be claimed What are preliminaries ?


over the prolongation period by the The purpose of Preliminaries section
In the construction industry, Bill of Contractor under prolongation costs, in BQ is to provide information,
Quantities (BQ) is a part and which essentially is a loss and particulars, general obligations and
common feature in many tender expense claim, as provided under the liabilities, etc of the project concern to
and/or contract documents for relevant contract clause/s of he tenderers, who should then price for
construction projects. Traditionally, standard forms of construction the various items provided under this
BQ is prepared by the consulting contract in Malaysia. section.
quantity surveyors (QS), particularly
under traditional or conventional In this article, Entrusty aims to provide The Preliminaries section, which form
building procurement system, usually readers with a better understanding of part of the BQ is normally priced by
following the Standard Method of Preliminaries, by answering the the tenderers separately from trade or
Measurement published by the following:- elemental bills , which are integral
Institution of Surveyors, Malaysia parts of the BQ.
(ISM) for building projects. A BQ What are preliminaries ? ;
typically comprises of preliminaries, The relevant provisions under In the Standard Method of
preambles and measured works. the common standard forms of Measurement 2 in Malaysia, items
building/construction contract in under Preliminaries are grouped into
When there is a disruption or delay in Malaysia; 13 listed categories, as follows-
the project, which often leads to Case studies/scenarios;
prolongation period of the Methods in assessing additional
construction contract, it is usual for costs of Preliminaries .

80 MBJ Volume 1 2009 MASTER BUILDERS JOURNAL


MBAM SECTION
Q&A

1 Project, parties and consultants


- name, nature and location of the project; general description of works; names and addresses of the Employer
and Consultants to be named in the contract.
2 Description of site
- information to indicate the boundaries of the site, the means of access and the position of the works; any
drainage, water, gas and other mains or power services known to exits on or over the site; any adjancent or
abutting buildings; information to facilitate visiting the site
3 Drawings and other documents
4 Form, type and conditions of contract
5 Contractor's liability
6 Employer's liability
7 Obligations and restrictions imposed by the Employer
- access to and possession or use of the site; limitations of working space; limitations of working hours; the
use or disposal of any material found on site; hoardings, fences, screens, temporary roofs, temporary
name/sign boards and advertising rights; the maintenance of existing live drainage, water, gas and other mains
or power services on or over the site; the execution or completion of the work in any specific order or in sections
or phases; maintenance of specific temperature and humidity levels; temporary accommodation and facilities
for the use of the Employer including air-conditioning, lighting, furnishing and attendance; the installation of
telephones for the Employer and the cost of his telephone calls; any other obligation or restriction such as
restriction upon the employment of labour, restriction on the use of radios by employees, restriction on the
felling of trees, car parking arrangements for the employees, etc
8 Works by Nominated Sub-Contractors
- The name of the firm to be nominated together with a description of the sub-contract work; attendance on
nominated sub-contractor where required shall be described and given as an item in each case for special
scaffolding additional to the Contractor's standing scaffolding, the provision of temporary access roads and
hard standings in connection with structural steelwork, precast concrete components, piling, heavy items of
plant, unloading, distribution, hoisting, placing in position giving in the case of significant items the weight
and/or size, the provision of covered storage and accommodation including lighting and power thereto,
maintenance of specific temperature or humidity levels,etc
9 Goods and materials from Nominated Suppliers
- The name of the supplier to be nominated; particulars shall be given where the Contractor is required to pay
the costs of conveying goods and materials to the site and/or of any special packing or similar requirements
10 Works by government or statutory authorities
- works which are to be carried out by a government or statutory authority in accordance with statutory
obligation shall be described, stipulating the scope and timing of the work and its effect on the Contractor's
operations
11 Works or goods and materials by the Employer
- a description shall be given of works by others directly engage by the Employer; a description shall be given
of good and materials provided by or on behalf of the Employer
12 Pricing
- Plant, tools, vehicles, scaffolding, site administration and security, transport for workpeople, protection of
work in all sections, water for the works, lighting and power for the works, temporary roads, hard standings,
crossings, temporary accommodation for the use of the Contractor, temporary telephones for the use of the
Contractor, traffic regulations, safety, healthy and welfare for the workpeople, disbursements arising from the
employment of workpeople, maintenance of public and private roads, removing rubbish, protecting casings and
coverings and cleaning the works on completion, drying the works, temporary fencing, hoardings, screens, fans
In monthly progress payment
planked footways, guardrails, gantries, control of noise, pollution, all other statutory obligations, surety or
performance bond, shop drawings, co-ordination and record drawings, schedules,valuations,
chartsthe
andpriced
the likeitems in the
showing
the progress, organisation of trades, progress photographs, etc Preliminaries section are normally
13 Contingencies divided into three categories, namely
initial, recurring and final costs by the

MASTER BUILDERS JOURNAL MBJ Volume 1 2009 81


MBAM SECTION
Q&A

Notwithstanding, the Preliminaries section in most BQs, comprises typically of claim for loss and/or expense suffered
the following headed items:- resulting from the Employers own
breach of contract i.e. delay and/or
1 Preliminaries particulars - project and 12 Safety, health and welfare
contract details, works, goods &materials non-payment, wrongfully termination
by others, contractual obligations and of the contract, etc.
liabilities, etc
2 Plant, tools and vehicles 13 Maintenance of publ and private
roads The Contractor may choose to claim
3 Scaffolding 14 Removal of rubbish, debris, etc
4 Site administration and security 15 Control of noise, pollution, etc under the relevant provisions in the
5 Transport for work people 16 Statutory compliance and contract or bring legal action in
obligations
6 Protection of work 17 Surety or performance bond
arbitration/litigation for damages
7 Water, lighting and power 18 Insurances resulting from the breach of contract.
8 Temporary telephone 19 Shop drawings, co-ordination
and record drawings
9 Temporary roads, hardstandings, 20 Progress photographs In simple terms, loss and expense
crossings, etc and reports items may include the following ;
10 Temporary accommodation 21 Schedules, charts, etc showing
progress of trades, works,
activities. i. Prolongation costs
11 Traffic regulations 22 Clearing, cleaning and handover
ii. Disruption costs
iii. Additional Preliminaries
In monthly progress payment but which he did not receive, because iv. Overheads
valuations, the priced items in the of one or more of those events listed v. Profit
Preliminaries section are normally in the conditions of the relevant vi. Finance charges
divided into three categories, namely contract, which entitle him to vii. Other additional costs/expenses
initial, recurring and final costs by the reimbursement of direct loss and /or not reimbursable under the
usually by the project consulting QS, expense and Expense as Any cost contract.
in consultation with the Contractor. to the contractor which is more than it
The proportion of initial and final costs would otherwise have been, because Under the standard forms
are usually fixed and payable upon of the events referred to above of building / construction contract
commencement and at completion, commonly used in Malaysia, the
while the recurring costs are then The word direct loss and expense, relevant loss and expense clauses
spread evenly over the project means the direct consequence of the are briefly described and discussed
completion period. act giving rise to the claim (A & B below.
Taxis Ltd v The Secretary of State for
The Relevant Provisions Under The Air 1922) or that which flows PAM Forms (1998 & 2006)
Common Standard Forms Of naturally from the breach, without
Building/Construction Contract In other intervening cause and Under PAM Form of Building Contract,
Malaysia ? independently of special there are two provisions that enable
circumstances (Saintline Ltd v the Contractor to claim for additional
Many standard forms of construction Richardsons, Westgarth & Co Ltd preliminaries. However, such claim
contract allow loss and expense to be 25 BLR140, 1940). In essence, for must fall under the specific
claimed by the Contractor and loss and expense to be admissible, it circumstances provided under Clause
ascertained by the Superintending cannot be costs arising from indirect, 24 Loss and Expense for both PAM
Officer (or the Architect / Engineer remote, consequential or contributory 98 and 06 and Clause 11.6 Variation
/PD/QS, depending on the form causes. for PAM 98 and Clause 11.7
applicable) for payment by the Variation for PAM 06.
Employer. The Contractor is usually entitled to
claim for loss and/or expense suffered In order to succeed in the claim for
In the Royal Institution of Chartered if the work is disrupted/ affected loss and expense (in this
Surveyors (RICS), UK (1987) had /delayed due to certain specific case, additional preliminaries), the
defined Loss as Any monies that the causes or events, which are of no fault Contractor must notify the Architect in
contractor should have received, of their own. In addition, he can also writing if the regular progress of

(Continued On Page 84)


82 MBJ Volume 1 2009 MASTER BUILDERS JOURNAL
MBAM SECTION
Q&A

(Continued from Page 82)

Works has been or is likely to be materially affected, which Clause 32.6 Failure to Comply
he had incurred or is likely to incur direct loss and/or
expense. Under the CIDB Form, it is a condition precedent that the
Contractor should notify the Superintending Officer within
Thereafter, the Contractor needs to submit together with thirty (30) days, if he intends to claim for Loss and
the loss and expense claim, the relevant information and Expense.
details to substantiate his claim to the Architect for his
ascertainment, accordingly. JKR/PWD Form 203A (Rev. 10/83 & Rev. 2007)

CIDB Form (2000) Under JKR/PWD Form, the Contractor is entitled to claim
Under the CIDB Form of Contract, the contract provisions for additional preliminaries under Clause 44 Loss and
concerning loss and expense claim are Clause 1.1 Expense caused by delays, and/or under Clause 5 (d)
Definition, Clause 31 Claims for Loss and Expense and Claims for compliance with the Superintending Officers
Clause 32 Procedure for Claims. (SO) instructions a provided in JKR 203 (Rev. 10/83) and
for Loss and Expense claims under Clause 44 of JKR 203
In Clause 1.1 Definitions, Loss and Expense comprise of (Rev. 2007).
actual costs and percentage of the said costs.
Similar to other aforesaid forms, the Contractor is required
Loss and expense may comprise of:- to notify the SO in writing of his intention to claim if the
regular progress of Works has been materially affected
i. the direct relevant costs of labour, Equipment, which he has incurred direct loss and/or expense due to
materials, or goods actually incurred on the Site by the following specific reasons:-
the Contractor; and

ii. costs of an overhead nature actually and necessarily


JKR 203 (Rev. 10/83)
incurred on the Site by the Contractor; and
Clause

i. the amount equivalent to the percentage named in the


44 (c) by reason of directions given by the SO
Appendix of such cost referred to in (a) and (b) above,
consequential upon disputes with neighbouring
such amount shall be deemed to be inclusive of any
owners provided the same is not due to any
profits, head office or other administrative overheads,
act, negligence or default of the Contractor or
financing charges (including foreign exchange
any sub-contractor, nominated or otherwise, or
losses) and any other costs, loss or expense of
whatsoever nature and howsoever arising. The
percentage shall exclude interest payable pursuant to
44 (f) by reason of the Contract not having received in
sub-clause 42.9(b).
due tme necessary instructions, drawings, levels
or instructions in regard to the nomination of sub-
The events which entitle the Contractor to claim for Loss
contractors and/or suppliers provided in this
and Expense are stipul;ated under Sub-Clause 31.1
Contract, from the SO due to any negligence or
Reasons for Loss and Expense Claim.
default of the SO and for which he shall have
specifically applied n writing on a date which
Clause 32 of CIDB Form of Contract set out the procedures
having regard to the Date for Completion stated
to claim for Loss and Expense, as follows;
in the Appendix to theseConditions or to any
extension of time then fixed under this
Clause 32.1 Notice of Claim
Conditions, was neither unreasonably distant
Clause 32.2 Contemporary Records
from nor unreasonably close to the date on which
Clause 32.3 Substantiation of Claims
it was necessary for him to receive the same,
Clause 32.4 Access to Contractors Books
and Documents
Clause 32.5 Payment of Claims
44 (i) by delay on the part of artists, tradesman or
other engaged b the Government in executing
work not forming part of this Contract.

84 MBJ Volume 1 2009 MASTER BUILDERS JOURNAL


MBAM SECTION
Q&A

JKR 203 (Rev. 2007) JKR 203 (Rev. 2007)


Clause Clause

44 (c) suspension of works under Clause 50; 44 (f) the Contractor not having received in due time
instructions in regard to the nomination of sub-contractors
44 (d) directions given by the SO, and/or suppliers provided in this Contract, necessary
consequential upon d i s p u t e s instructions, drawings or levels for the execution of the
with neighbouring owners provided the Works from the SO due to any negligence or default of
same is not due to any act, negligence the SO PROVIDED THAT the Contractor shall have
or default of the Contractor or any specifically applied in writing on a date which having
sub-contractor,nominated or otherwise; regard to the Date for Completion stated in Appendix or
to any extension of time then fixed under this clause, was
44 (e) SO's instruction issued under Clause 5 neither unreasonably distant from nor unreasonably close
hereof, PROVIDED THAT such to the date on which it was necessary for him to receive
instructions are not issued due to any the same;
act, negligence, default or breach of
this Contract by the Contractor or any 44 (h) delay on the part of artists, tradesmen or others engaged
sub-contractor, nominated or by the Government in execting work not forming part of
otherwise; this Contract

IEM Form (1989)

Additional preliminaries claim will fall under Clause 43 and 5 (d), which is similar to JKR Clause 44, except in IEM Form,
which provides an additional clause, Clause 43 (g) to cover for reason of delay in giving possession of the Site as provided
under Clause 38 (b) (i).

The following are the grounds for claims under loss and/or expense as provided in the aforesaid PAM 1998/2006, CIDB
2000, JKR 203A and IEM 89.
Contract Clasue
Grounds for Loss and/or Expense PAM PAM JKR IEM CIDB
2006 1998 203A 1989 2000
1 Late drawings, information, confirmations and/or instructions 24.3(a) 24.2(i) 43(f) 43(f) 31.1(b)
2 Ditto, in regard to P.C. Sums & Provisional Sums 24.3(a)
3 Failure or delay in giving possession of site 24.3(b) 43(g) 31.1(e)
4 Compliance with the contract administrators instructions, eg. to resolve
discrepancies 24.2(iii) 5(d) 5(d) 31.1(c)
5 Variation 5(d) 5(d) 31.1(h)
6 Postponement of any work by Contract Administrator 24.3(c) 24.2(v)
7 Suspension of works by the Contract Administrator 24.3(c) 31.1(g)
8 Delays by artist, tradesmen or others employed by the Employer 24.3(d) 24.2 (iv) 43(i) 43(i) 31.1 (f)
9 Delay or failure supply of goods and materials by the Employer 24.3(e) 24.2 (vi)
10 Test and Inspection 24.3(f) 24.2(ii) 5(d) 5(d) 31.1(d)
11 Any acts of prevention or breach of contract by the Employer 24.3(g) 24.2
12 Contract Administrator's instruction on antiquities and fossils 24.3(h) 31.1(i)
13 Appointment of a replacement Architect/Engineer/QS/Specialist Consultant 24.3(i)
14 Dispute with neighbouring owners 24.3(j) 43(c) 43(c)
15 Reason of the execution of work for Provisional Quantity which the Architect is
not a reasonably accurate forecast of the quantity of work required 24.3(k)
16 Failure of the Employer to give access to site in time or any passage to the site
which is in possession or control of the Employer 24.3 (l) 24.2 (vii)
17 Suspension of works by the Contractor due to late payment and the withdrawal
of the Architect and/or Consultant 24.3 (m)
18 Suspension of works by the Authority but not due to the Contractor's/Nominated
Sub-Contractor's negligence, omission, default and/or breach of contract 24.3 (n)
19 Any other ground for Loss and Expense mentioned in the Contract 31.1 (j)
20 One or more of the Excepted Risk 31.1 (a)
Grounds for Loss and/or Expense provided under the various Standard Forms of Constructions Contracts in Malaysia

MASTER BUILDERS JOURNAL MBJ Volume 1 2009 85


MBAM SECTION
Q&A

thereupon also be determined and the


Contractor shall be entitled to be paid
(in so far as such amounts or items
have not already been covered by
payments on account made to the
Contractor) as follows:-

(i) The value of the Contract Works


completed at the date of the
determination, such value to be
calculated according to Clause
17 hereof; or

(ii) The value of work begun and


being executed but not
completed at the date of such
determination, such value to be
calculated according to Clause
17 hereof; or

(N.B. The Clause 17 referred above is


Case Studies / Scenarios assessed/evaluated based on
for Valuation of Variation which
different methods from the usual
is similar to JKR Clause 25)
Additional preliminaries is actually a actual cost method.
part of loss and expense claim. The
From the above provision, the
Contractor is entitled to loss and In a case where the contract is
Contractor is entitled to be paid by the
expense claim under Hadley v terminated by the Employer due to the
Employer based on the following
Baxendale (1854) 9 Ex341 first limb, Contractors default or breach, the
valuation procedure:-
i.e. may fairly and reasonably be Employer had contended that all the
(i) The value of the Contract Works
considered to have arisen naturally, preliminaries items incurred should be
completed at the date of the
that is according to the usual course evaluated as loss and expense and
determination. Such completed
of things.. Usually, the Contractors therefore be based upon actual costs
work to be valued based on the
claim for additional preliminaries incurred instead of valuing them as
stipulated contract price or rate
should be evaluated based on actual work done.
and is accordingly to be valued
cost incurred, in the absence of any
under the rules for valuation of
expressed method of evaluation. Was the Employer correct in
variation works.
evaluating all the additional costs of
Notwithstanding, there are cases or Preliminaries incurred based on
(ii) The value of work begun and
scenarios whereby the evaluation of actual costs ?
being executed but not
the additional preliminaries does not
completed at the date of
necessary have to be based on the To answer this question, lets
the determination. Such
actual cost incurred, as it depends on investigate the provision of this
uncompleted work is considered
the provisions of the contract or contract for termination/determination.
to fall under the rules for
project circumstances or conduct of The provision states that, inter alia:
valuation of variation works.
the contracting parties. In such cases,
the knowledge and skills of a QS to If for any reason the Employer's
As mentioned earlier, Preliminaries is
value the preliminaries is called for. employment under the Main Contract
a part of the Bills of Quantities relating
is determined (whether due to any
to the contract work. So, it should be
The following are a few typical default of the Employer or otherwise),
valued as work done for the works
cases/scenarios, whereby additional then the employment of the
executed up to the date of the
preliminaries have been Contractor under this Contract shall

86 MBJ Volume 1 2009 MASTER BUILDERS JOURNAL


MBAM SECTION
Q&A

termination/determination instead of It is often very difficult to value to what Contractors preliminaries claim, a
based on actual costs. The QS for this extent of the preliminaries items or good knowledge and understanding
project should undertake this works that had been executed. In of the cost structure and pricing of
valuation task, accordingly. valuing preliminaries, one would contract is essential to enable a fair
wonder whether the Contractor had and reasonable valuation to be made,
Quoting from Hudsons Building and priced the cost for example a tower accordingly.
Engineering Contracts, 11th Edition, p crane spread across the trade rates or
1602 explains the person who is in the preliminaries items. A distinction Methods In Assessing Additional
appointed to undertake this valuation has to be made as to the Contractors Costs Of Preliminaries
task; fixed costs (e.g. mobilisation and
demobilisation); time related costs In practice, it is common to use
It has been held that if a man is, (e.g. site management, plant and recurring costs based upon estimation
on account of his skill in such equipment, etc.) or quantity related or prorated time basis or formula
matters, appointed to make a costs (utilities, protection, etc.). method or negotiated basis from the
valuation, in such manner that in priced preliminaries in BQ.
making it he may, in accordance In the Singapore Institute of Architect
with the appointment, decide (SIA) form of contract, for example, Can this practice apply in evaluating
solely by the use of his eyes, his the Contractor is required to indicate the additional preliminaries? The
knowledge and his skill, he is not in his tender price for preliminaries following are a few methods
acting judicially: he is using the items in the form of quantity related, employed in evaluating additional
skill of a valuer, not of a judge. In time related or fixed cost so that any preliminaries.
the same way, if two persons are additional expenses for the
appointed for a similar purpose, preliminaries items, the indicated On Amended Contract Basis
they are not arbitrators but only tender price of the preliminaries items
valuers. They have to determine shall be used as the basis for In the Malaysian construction industry,
the matter by using solely their valuation and adjustment. the standard form of contract used
own eyes and with knowledge and are often subject to addendum/
skill. Consequently, when evaluating the supplementary /modification/

MASTER BUILDERS JOURNAL MBJ Volume 1 2009 87


MBAM SECTION
Q&A

amplification/special provisions or PWD DB/T Clause 45.2 & 46 under Bond/Performance Sum
conditions to suit the circumstances Special Provisions, which is based on Guarantee, of the Contract Value
prevailing on the project concern. the Special Formula for calculation of OC = Original Contract Value
compensation for Loss and Expense CEP = Total Claimable Extended
An example of an Addendum to claim under Preliminaries and Period
PAM98 Clause 24, is as follows: General Requirement, as follow: BLR = Base Lending Rate per
annum as on Date of Original
The Contractors claim for loss and/or a) Cost of Extension of Insurance Completion of Work
expense (if any) under this Clause Policies
shall be confined only to those c) Other Items
recurring cost of Preliminaries items A x CEP/TDP (i) For Building Works:
which have been priced for this 14% x PL x CEP/OP
Contract and only for those A = Amount of premium paid for (ii) For Civil Engineering Works:
Preliminaries items which are deemed the whole duration of the 20% x PL x CEP/OP
applicable. The Contractor shall not extended insurance period as
be entitled to claim on any other basis provided under the Contract PL = Amount of Preliminaries
other than the aforesaid basis as he CEP = Total Claimable Extended Work and General Requirement
shall be deemed to have allowed for Period in the Contract not inclusive of
all other loss and/or expense TDP = Total Delayed Period Provisional Sum and specific
(excluding the recurring Preliminaries items for the Contract (e.g.
expenses) directly or indirectly b) Cost of Extension of Design and supervision fees,
incurred by him caused by Performance Bond/Performance Traffic management plan,
disturbance of regular progress of Sum Guarantee Environmental management
Works under this Clause. plan, I-Supervision, Aerial
5% x OC x CEP x BLR/365 survey, Digital slope mapping,
On Formula Basis Permanent diversion of
Another example is the JKR 203A 5% = Maximum percentage services, KTMBs flagging and
Clause 5(d), 44 & 48(d) and JKR amount of Performance inconvenience charges, Road

88 MBJ Volume 1 2009 MASTER BUILDERS JOURNAL


MBAM SECTION
Q&A

maintenance during construction the valuation, certification and


and other similar items) approval process for this
subjected to a maximum amount compensation claim, a decision
not exceeding 6% of the value of had been to allow the Special
Builders Work for the Contract Formula to be adopted for
(less the value of Preliminaries valuation and certification of the
Work & General Requirement) claim concern.
CEP = Total Claimable Extended
Period The above formula method was
OP = Original Contract Period (in adopted and practised until February
days) .. 2006, when JKR had decided to move
away from the above formula method
JKR had adopted the aforesaid to revert to documentary evidence
formula method for the following based on actual costs for such claims.
reasons;

i) In accordance with JKRs On Negotiation/Agreement Basis


contract, the Final Account In some cases, the contracting parties
ii) In the previous procedure, all
needs to be prepared not more settle their claim for additional
claims submitted by the
than six (6) months after preliminaries by negotiation. They
Contractor required to be
practical completion of the would agree to base on recurring cost
examined and verified of its
Works. However, the preparation or formula method as the basis to
validity and reasonableness. As
of Final Account is often delayed assess the value preliminaries items
such, a longer time may be
for the Contractor who has made in lieu of actual costs. Such method
required in the valuation and
a claim particularly on additional would avoid the tedious and time
verification stage prior to JKRs
preliminaries upon issuance of consuming process, i.e. to collate and
Claim Committee certification
Certificate of Delay and provide the necessary documentary
and approval.
Extension of Time for the project evidence for evaluation and verifying
concern. the actual costs, which can lead to
iii) Therefore, in order to expedite

MASTER BUILDERS JOURNAL MBJ Volume 1 2009 89


MBAM SECTION
Q&A

dispute, and may end up in


arbitration/litigation subsequently, References/Bibliography
thereby incurring more costs to the 1. Wallace, I.N. Duncan, Hudsons Building & Engineering Contracts,11th Edition,
parties, eventually. Sweet & Maxwell, 1995.

2. Ong, H.T., Should additional Preliminaries be evaluated on recurring costs basis


Conclusion/Solution
or actual costs incurred One Day Joint Contract Seminar: Extension of Time,
Variations, Loss & Expense and Prolongation Claims jointly organised by BK
Whether the additional preliminaries Asia Pacific and Master Builders Association of Malaysia, 27 September 2007
are evaluated based upon actual cost
3. References are also made to several Malaysia standard forms of contract,
incurred or recurring cost or namely:-
negotiation/agreed basis, the i) PAM Forms of Building Contract (1998 & 2006)
contracting parties should come to an ii) JKR/PWD Forms of Contract (203A Rev 10/83 & Rev. 2007)
iii) JKR PWD/Standard Form of Design & Build / Turnkey Contract (PWD Form
agreement at the formation of the DB/T) (2002 Edition)
contract or at the outset of the project iv) IEM Conditions of Contract for Works Mainly of Civil Engineering
on the method of evaluating the Construction (1st Edition 1989)
v) CIDB Form of Contract for Building Works (2000 Edition)
additional preliminaries to be adopted,
when a prolongation/disruption
situation arises.
In the next issue of the MBAM journal the article will answer the question on
It is often a tedious, costly and time What is Force Majeure and its implications?
consuming process in compiling and
assessing the documentary evidence
The Entrusty Group includes
(usually voluminous) in order to prove
Entrusty Consultancy Sdn Bhd
the actual costs incurred, which often
(formerly known as J.D. Kingsfield (M)
leads to dispute and possibly
Sdn Bhd), BK Burns & Ong Sdn Bhd
arbitration/litigation rather than
(a member of the Asia wide group BK Asia Pacific), Pro-Value Management Sdn
amicable settlement.
Bhd, Agensi Perkerjaan Proforce Sdn Bhd and International Master Trainers
Sdn Bhd providing project, commercial and contractual management services,
It must be noted that, actual costs for
risk, quantity, quality and value management, recruitment services and
additional preliminaries need not
corporate training programmes to various industries, particularly in construction
necessarily always mean a lower cost
and petrochemical, both locally and internationally.
than recurring cost or formula method
as determined or valued by the
For further details, please visit website: www.entrusty.com or contact HT Ong
Architect / Engineer / SO / PD or QS,
at 22-1 & 2 Jalan 2/109E, Desa Business Park, Taman Desa, 58100 Kuala
depending on the form of contract
Lumpur, Malaysia.
used. In some cases, actual costs are
Tel: 6(03)-7982 2123
actually higher than recurring costs or
Fax: 6(03)-7982 3122
formula method.
Email: enquiry@entrusty.com.my

Nevertheless, unless the above


Entrusty Group provides 30 minutes of free consultancy (with prior
circumstances or conditions as
appointment) to MBAM members on their contractual questions. The Group also
described apply then the evaluation of
provides both in house and public seminars/workshops in its various areas of
additional preliminaries should be
expertise.
based on actual reasonable costs
which flow from the claim event.
Upcoming Public Seminars in 2009
Certifications and Payments.
Common Contractual Issues/Problems in Malaysia.
Determination/Termination of Construction Contracts in Malaysia.
Pertinent Contractual Provisions in Construction Contracts

90 MBJ Volume 1 2009 MASTER BUILDERS JOURNAL

You might also like