Doc. No.

:
CONST/PK/HSE/FRM-22
Rev.: 00
JOB SAFETY ANALYSIS Date: July 1st, 2016
Page: 1 of 2

Project: NRL CDU Revamping Project Project#: 1166 Area: E-64 General Comments: Proper PPE, TBT should be conducted before start the job,
Access control authority would be DEL Site Manager/Site Engineer
Date:20-02-2017 Supervisor: Ramzan/Adnan
Job Description: Work at Height
Detail of Equipment & Tools Responsible Severity
Item
Activity
Risk Involved Preventive Measure
used Person Rating

MATERIAL CAN FALL. MATERIAL WILL BE FASTENED PROPERLY BEFORE Area I/C 3
TRANSPOR VEHICLES. TRANSPORTING TO SITE. (Authorized
1 PERSONAL INJURY.
TING OF ONLY EXPERIENCED, SKILLED AND TRAINED Person).
SCAFFOLDI UNAUTHORIZED / PERSON SHOULD BE ALLOWED
2
NG UNTRAINED/ ALL HANDTOOLS SHOULD BE INSPECTED PRIOR TO
MATERIAL SCAFFOLDING INEXPERIENCED START OF JOB
3
AT SITE. MATERIALS. PERSONNEL ON THE JOB SCAFFOLDING PIPES WITH CORROSION SHOULD
(PIPES, UNEVEN GROUND NOT BE USED. 3
JOINTS, FAULTY/ POOR CONDITION
PLANKS, BASE SCAFFOLDING MATERIAL MATERIAL WILL BE UNLOADED WITH BOOM TRUCK 3
2 UNLOADING PLATE, TOE
OF BOARD & etc.)
IMPROPER SCAFFOLDING CERTIFIED BOOM TRUCK OPERATOR WILL CARRY
ERECTION OUT THE TASK. 2
SCAFFOLDI
NG TAG SYSTEM NOT MATERIAL WILL BE STORED IN A DESIGNATED AREA.
MATERIAL. FOLLOWED.
MATERIAL WILL BE STORED ON SCAFFOLD RACKS.
.LEVEL STRIP, WRONG MATERIAL HARD BARRICADE AND SIGNAGE WILL BE PROVIDED
3
HAMMER, HANDLING/ FALLING OBJECT
STORAGE
3 OF
METER TAP & PERSONNEL INJURY. GROUND SURFACE SHOULD BE LEVELED
ROPE. 3
SCAFFOLD PERSONNEL FALL. RED TAG MUST BE PLACED/ HANGED AT THE START
MATERIAL. OBJECT FALL. OF SCAFFOLDING
ENSURE VERTICAL PIPES ALLIGNMENT AND CHECK
PROPERTY LOSS IT WITH HAND LEVEL
ERECTION ENSURE ALL JOINTS ARE PROPERLY TIGHTENED 3
4 & USE BRACING PIPES AND OUTERRIGGERS PIPES
DISMANTLI WHERE NECESSARY.
NG OF ONLY CERTIFIED SCAFFOLDERS WILL PERFORM THE 3
SCAFFOLDI JOB.
NG. SCAFFOLDERS WILL BE TRAINED ON SAFE WORKING
AT HEIGHT.
ABOVE 1.8M HEIGHT SAFETY HARNESS WILL BE
WITH DOUBLE LANYARD. 100%TIE OFF WILL BE
ENSURED.
SCAFFOLD PLATFORM WILL NOT BE OVERLOADED.

This document is the intellectual property of Descon Engineering Limited. Any unauthorized use, including modification and reproduction of the content is strictly prohibited.
Copyrights Ordinance 2002, All Rights Reserved
HAND RAIL AND TOE BOARDS WILL BE INSTALLED
WITH SCAFFOLDING PLATFORM.
ALL EMPLOYEES WILL WORK WITH PROPER PPES.

LADDER SHOULD BE CONSTRUCTED AT SUITABLE.

METAL PLANKS SHOULD BE PROERLY PLACED ON


PIPES WITH HOOKS AND USE BINDING WIRE FOR
ELECTRIC SHOCK DUE TO BINDIND WHERE NECESSARY
POWER LINE NO PERSON SHOULD GO IN DROP ZONE.
SCAFFOLDING AREA.
AREA SHOULD BARRICATED WHILE ERECTION OR
DISMENTLING THE PLATFORM.

AREA MUST BE CHECKED & FREE FROM ELECTRICAL


WIRES BEFORE ASSEMBLING TO THE CRANE.

OVERHEAD SCAFFOLD PERSONAL INJURY ENSURE OVERHEAD CLEARANCE WHILE Area


ELECTRICA STRUCTURE PROPERTY LOSS OPERATING THE EQUIPMENT Representative
L POWER
LINES

5 NIGHT LIGHTS HAND INJURY/EYE ENSURE WORKERS ARE COMPLYING PPES


WORKING
ACTIVITIES
STANDS INJURY REQUIRED. Area I/C 2
ELECTRIC SHOCK / EXTINGUISHER MUST BE PRESENT AT ALL TIME (Authorized
Person).
ELECTROCUTION LIGHT SHOULD BE PROPER PRIOR TO START THE
IMPROPER ILLUMINATION WORK. 3
PERSONAL INJURY ALL POWER CABLES SHOULD BE INSPECTED AND
PROPERTY LOSS INSULATED.
LIGHTS SHOULD BE INSTALLED OVER HEAD HEIGHT 2
TO AVOID GLARING TO PERSONAL.
IF GENERATOR USE FOR ELECTRICITY SHOULD BE
PROPERLY GROUNDED 3
ALL TOWER CRANE LIGHTS SHOULD BE CHECKED
AND USE WHEREVER NECESSARY.

This document is the intellectual property of Descon Engineering Limited. Any unauthorized use, including modification and reproduction of the content is strictly prohibited.
Copyrights Ordinance 2002, All Rights Reserved
HOUSEKEEPING 3
PROPERTY LOSS AREA BARRICADING 2
HOUSEKEE MANUAL CLEANING OF
6 PING AREA
SLIP/TRIP PPE AREA IN- 3
FALL FROM HEIGHT CHARGE

Severity Rating : (1) First Aid / Minor Property Damage (2) Recordable Accident / Property Damage

(3) Lost Time Accident / Major Property Loss (4) Catastrophic Accident

Are you aware of, and do you have the correct PPE? What are the risks? How do controlled risks?

_______________________________ __________________________
AREA ENGINEER / SUPERVISOR HSE REPRESENTATIVE

This document is the intellectual property of Descon Engineering Limited. Any unauthorized use, including modification and reproduction of the content is strictly prohibited.
Copyrights Ordinance 2002, All Rights Reserved