Professional Documents
Culture Documents
RV Bentulan Construction: Item Scope of Works Qty. Unit Unit Cost
RV Bentulan Construction: Item Scope of Works Qty. Unit Unit Cost
DETAILED ESTIMATES
a. Elements :
uPVC Pipes C-100, 75 mm 696 mtrs.
Trench Details ( w x h )
0.60 m x 0.50 m
A.1 Earthworks
Earth Excavation 208.8 cum 400.00
Sub-Total
Fire Hydrant
CI Gate Valve FF with BNG, 75mm 1 pcs. 6,620.00
CI Flange Adaptor FM with BNG 75mm 2 pcs. 1,754.00
Hydrant Head Angle Type, 75mm 1 pcs. 10,108.45
CI Elbow MM with BNG, 75mm x 90deg 1 pcs. 1,700.00
GI Pipe Sch. 40, 75mm 3 ft. 428.10
CI Valve Box Cover, 150mm 1 pcs. 1,056.02
uPVC Pipes C-100, 75 mm 1 ln.m 488.31
CI Tee MM with BNG, 75 mm 1 pcs. 2,305.39
CI Sleeve type Coupling MM with BNG, 75mm 1 pc. 1,260.00
Portland Cement 1 bags 287.85
Goodmixed Aggregates 1 cu.m. 330.00
Sub-Total
SUMMARY:
DIRECT COST
C Materials Cost
A.1 Earthworks
A.3 Interconnection & Gate Valves
A.4 Hydrotesting & Disinfection
A.5 Blow Off Valve & Fire Hydrant
C.8 Equipment Rental
C.9 Labor Cost
TOTAL DIRECT COST (C)
INDIRECT COST
A. OCM ( 8% of Direct Cost)
B. Contractor's Profit ( % of Direct Cost)
C. Vat 12% (Direct Cost + Indirect Cost (A+B)
TOTAL INDIRECT COST (A+B+C)
TOTAL COST (DIRECT COST + INDIRECT COST)
UNIT COST 908.05
II. Elevated Steel Tank
C.1 Earthworks
Earth Excavation 12 cum 350.00
Washed Sand & gravel 4 cum 600.00
Washed Gravel 4 cum 650.00
Boulders 6-8" 4 cum 1,800.00
Sub-Total
C.8 Painting
Sand Blasting 1 lot 50,000.00
Epoxy Primer ( Silver ) Outside 12 gals 1,200.00
Metal Paint ( Food Grade ) Inner 12 gals 1,600.00
Paint Roller 8"; Tray; extra foam 4 set 255.00
Paint Brush 2" 8 pcs. 90.60
Sub-Total
C.9 Equipment Rental
1 Boom Truck ( include operator & fuel ) 2.00 days 120,000.00
1 Bsckhoe ( include operator & fuel ) 1.00 days 13,200.00
2 Welding Machine 30.00 days 1,200.00
1 Generator Set 30.00 days 4,500.00
1 Concrete Mixer ( include fuel ) 12.00 days 1,200.00
Sub-Total
SUMMARY:
DIRECT COST
C Materials Cost
C.1 Earthworks
C.2 Metal Reinforcement
C.3 Concrete Works
C.4 Plastering and Finishing column
C.5 Welding Works
C.6 Pipes & fittings
C.7 Formworks & Scaffoldings
C.8 Painting
C.9 Equipment Rental
C.10 Labor Cost
TOTAL DIRECT COST (C)
INDIRECT COST
A. OCM ( 8% of Direct Cost)
B. Contractor's Profit ( % of Direct Cost)
C. Vat 12% (Direct Cost + Indirect Cost (A+B)
TOTAL INDIRECT COST (A+B+C)
TOTAL COST (DIRECT COST + INDIRECT COST)
UNIT COST 1,490,000.78
III. PUMPHOUSE
E.4 Painting
Primer; Flat; Premium grade 2 gals 1,350.00
Semi-Gloss Latex Paint; Premium Grade 2 gals 1,200.00
Roofpaint 1 gals 1,600.00
Sandpaper #100 20 shts. 255.00
Paint Roller 8"; Tray; extra foam 1 set 150.00
Paint Brush 2" 2 pcs. 40.00
Sub-Total
3. Electrical Works
THW Wire; 6/7 62 m 110.00
TW Wire; 14/7 10 m 24.00
Flexible Pipe 1" dia 5m 8.00
Nipple 32 mm ^2 dia x 1" 2 pcs 40.00
Secondary Rack Assembly ; 1phase Porcelain Spool Insulato 2 sets 280.00
Electical Tape , 3M 3/4" 2 rolls 40.00
Entrance Cap 32 mm^2 dia 1 pc 85.00
REC Pipe 32 mm^2 dia 1 length 850.00
LB Pipe 32 mm^2 dia 1 pc 155.00
ACB 60 A; 2- Bolt-on; w/ enclosure 1 unit 8,000.00
Switch; Single gang ; w/plate & screw 1 sets 125.00
CFL bulb; 11 W 1 pc 130.00
Junction Box 4x4" 1 pc 27.00
Sub-Total
5. Labor Cost
1 Project Engineer 3.00 days 500.00
1 Foreman 3.00 days 450.00
1 Electrician 3.00 days 250.00
1 Laborer 3.00 days 250.00
Sub-Total
SUMMARY:
DIRECT COST
E Materials Cost
E.1 Concrete Works Materials Cost
E.2 Roofing Works
E.3 Forms and Scaffoldings
E.5 Labor Cost
E.6 Service Drop Concrete Post
1. Concrete Works Materials Cost
2. Forms and Scaffoldings
3. Electrical Works
4. Load Deposit & Transformer
5. Labor Cost
INDIRECT COST
A. OCM ( 8% of Direct Cost)
B. Contractor's Profit ( % of Direct Cost)
C. Vat 12% (Direct Cost + Indirect Cost (A+B)
TOTAL INDIRECT COST (A+B+C)
TOTAL COST (DIRECT COST + INDIRECT COST)
UNIT COST 365,001.01
Amount
83,520.00
83,520.00
6,000.00
3,400.00
1,995.00
1,356.00
2,520.00
99,992.00
3,900.00
460.00
450.00
1,050.00
425.00
121,548.00
1,009.80
6,620.00
3,508.00
176.00
853.00
850.00
2,700.00
350.00
16,066.80
2,400.00
3,250.00
4,000.00
9,650.00
253.64
853.00
2,806.00
421.32
1,190.90
308.78
90.00
86.49
165.00
287.85
330.00
6,792.98
6,620.00
3,508.00
10,108.45
1,700.00
1,284.30
1,056.02
488.31
2,305.39
1,260.00
287.85
330.00
28,948.32
223,550.00
3,600.00
227,150.00
17,680.00
27,200.00
27,200.00
34,000.00
106,080.00
83,520.00
16,066.80
9,650.00
35,741.30
227,150.00
106,080.00
478,208.10
38,256.65
47,820.81
67,714.27
153,791.72
631,999.82
/mtr.
Amount
4,200.00
2,400.00
2,600.00
7,200.00
16,400.00
16,250.00
13,524.00
2,850.00
1,750.00
34,374.00
1,800.00
3,900.00
1,200.00
400.00
17,500.00
2,100.00
26,900.00
180.00
450.00
2,500.00
3,130.00
21,000.00
12,250.00
7,200.00
4,800.00
23,100.00
120,288.00
22,000.00
20,520.00
3,930.00
9,300.00
3,840.00
20,000.00
6,000.00
3,325.00
277,553.00
6,400.00
4,800.00
170.00
170.00
400.00
550.00
450.00
650.00
850.00
650.00
17,000.00
32,090.00
20,000.10
7,500.00
1,500.00
4,140.00
450.00
90.00
900.00
34,580.10
50,000.00
14,400.00
19,200.00
1,020.00
724.80
85,344.80
240,000.00
13,200.00
72,000.00
135,000.00
14,400.00
474,600.00
18,200.00
15,750.00
28,000.00
28,000.00
8,750.00
43,750.00
142,450.00
16,400.00
34,374.00
26,900.00
3,130.00
277,553.00
32,090.00
34,580.10
85,344.80
474,600.00
142,450.00
1,127,421.90
90,193.75
112,742.19
159,642.94
362,578.88
1,490,000.78
/lot
Amount
2,707.50
240.00
10,500.00
9,250.00
3,500.00
340.00
1,575.00
475.00
28,587.50
768.00
1,920.00
5,400.00
960.00
425.00
240.00
360.00
60.00
170.00
288.00
360.00
2,800.00
800.00
85.00
14,636.00
85.00
170.00
959.40
1,001.25
2,215.65
2,700.00
2,400.00
1,600.00
5,100.00
150.00
80.00
12,030.00
4,000.00
3,600.00
900.00
3,600.00
3,200.00
4,000.00
19,300.00
1,500.00
1,750.00
170.00
4,625.00
500.00
105.00
8,650.00
85.00
85.00
480.00
600.00
1,250.00
6,820.00
240.00
40.00
80.00
560.00
80.00
85.00
850.00
155.00
8,000.00
125.00
130.00
27.00
17,192.00
180,000.00
180,000.00
1,500.00
1,350.00
750.00
750.00
4,350.00
28,587.50
14,636.00
2,215.65
19,300.00
8,650.00
1,250.00
17,192.00
180,000.00
4,350.00
276,181.15
22,094.49
27,618.12
39,107.25
88,819.86
365,001.01
/lot
Contractor :
Project Name : Water System Level II
Project Location : Brgy. Magsaysay, Carmen, Davao del Norte
SUMMARY
517,303.02
791,411.22
84,369.82
39,766.94
1,432,851.00
SUMMARY
Item Description Estimated Cost
I Pipelaying 631,999.82
II Elevated Steel Tank 1,490,000.78
III Pumphouse 365,001.01
IV Painting Err:509