Professional Documents
Culture Documents
عقود هندسية .. (E.I.B)
عقود هندسية .. (E.I.B)
:
/
.
: .
:
:
Lump Sum General Contracting (Design-bid-build process) .1
Cost-plus a Fee/GMP General Contracting .2
Design-Build .3
Construction Management .4
:
.1 ( :) Competitively Bid
.
.2 ( :)Negotiated
.
.3 (.)Combination of the two
Project Delivery System Contractor Selection/Contract
Type Competitively Bid Negotiated
Lump Sum General Contracting
Cost-plus a Fee/GMP General Contracting
Design-Build
Construction Management
):)Criteria For Determining The Best Project Delivery System For A Proposed Building
:
.1.
.2 .
.3 Fast-track
(.(accelerated construction
.4 .
.5 .
.6 .
.7 .
.8 .
.
. .9
. .11
. .11
. .12
. .13
( :)Donor () .
( :)Owner
( )public owner ( )private owner .
( :)Contractor
.
( :)Sub-Contractor
.
( :)Designer
- .-
( )Traditional System :
(:)Traditional System
( )Design-bid-build
( )
.
(:)Value Engineering
:
.1 (.)Cost
.
.2 ( )Revision (.)Reactive
(:)Constructability
:
.1 .
.2 (.)Proactive
( )VE/Constructability
.
(:)Contract
.
(:)Contractual Relationship
:
.1 .
.2 .
.3 .
.4 .
:
Lump sum contracting is the execution segment of the design-bid-build process.
( ) .
Design Bid Select Contractor Build
(
)
.
.
()Lump Sum
Lump Sum
.
Stipulated sum , Fixed price , Hard money
:Unit Price
. %25
%25
.
.
. .1
. .2
. .3
: .4
. .
. .
. .
. .
. .
. .
:Bid Bond . .1
:Performance Bond .2
.
:Labor and material Bond . .3
:
. .
. .
. .
:Maintenance Bond . .4
( )
.
( )Tender (:)Bid
:Tender .
:Bid
.
()Prequalification
:
.
.
()Post qualification
.
()Competitive Bidding
.
( ).
):)Subcontractors tend to give better prices to general contractors who
. .1
. .2
. .3
. .4
. .5
:The Aggressive Designer
.
:Alternates (
) ( ).
:Substitutions ( )
.
.
:Allowances :
. .
. .
:Change order :
.( .)..
.( .)..
.( ).
. ( ).
. .
:Bid shopping
.
:Shop Drawings .
:Pre-Bid Conferences
.
:Bid Day .
:Contingency .
: . .
. .
:Bid Strategy :
.1 .
.2 .
.3 .
.4 .
.5 .
.6 .
.7 .
.8 .
:Risk Allocation
.
(:)Risk Factors
.1 .
.2 .
.3 .
.4 .
.5 .
.6 .
.7 .
.8.
.
:Casualty Losses .
:Partnering
.
:
.
.
:
:Cost of the work plus a fee .1
.
:Cost-plus a fee with a Guaranteed Maximum Price .2
.
GMP
.
GMP
.
(:(Contractor Selection
(:)A private owner will rarely select a general contractor based on price alone. Other factors, such as
.
.
:DESIGN-BUILD
:
.
:In-house design
.
:Consultative design
.
):)Joint Ventures
()
.
.
(:)Advantages of Design-Build
( ). .1
. .2
. .3
. .4
.Lump Sum .5
.
:
:
):(Owners have particular responsibilities to develop clear, detailed statements of requirements, including ..
.1 (:)Project scope
Facility management cost analysis
.
.2 (:(Activities to be housed in the new building
.
.3 (.)Space needs
.4 ( )Ergonomic considerations .
.5 (.)Functional requirements
.6 (.)Budget and its level of certitude
.7 (.)Personnel to be accommodated
.8 (.)Esthetic statement
.9 (.)Expected construction schedule
.11 (.)Expected level of quality
(:(Contractor Selection
:
.1 ( ) Prequalification :
.
:
.1 .
.2 .
.3 .
.4 .
. ( )5-3
.
.
.2 :
. :
.1 .
.2 .
.3 .
.4 .
.5 .
. .
:
:Turnkey Projects ( )Design-Build -
.
:Bridging ( )Design-Build :
.1
(.)scope
.2 -
.
:Build-Own-Transfer (BOT)
.
.
:CONSTRUCTION MANAGEMENT
:
( )construction firm
( ).
.
:
( )amount of risk :
:Agency Construction Management .1
.
:At-Risk Construction Management .2
.
(:)Contingency
:
.1 ( )construction manager .
.2 .
.3 .