PEMERINTAH ACEH

DINAS BINA MARGA DAN DIPTA KARYA

SUMBER DANA : KEGIATAN DANA OTONOMI KHUSUS KAB. SIMEULUE DINAS BINA MARGA DAN CIPTA KARYA ACEH
NAMA PAKET : PENINGKATAN JALAN PSR INPRES - AIR DINGIN
NOMOR PAKET : BANG/SMUL/2011/01
NOMOR KONTRA : 37/KTR/BANG/SMLU/OTSUS/V/2011
KONTRAKTOR : PT. SELAMAT JAYA ABADI
KONSULTAN : PT. NUSVEY Ass. CV. ALPHA ENGINEERING CONSULTANT
LOKASI : KABUPATEN SIMUELUE

KONTRAK AWAL KONTRAK ADD-I KO


HARGA SATUAN
NO. URAIAN SAT.
(Rp.) JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT
VOLUME VOLUME VOLUME
(Rp.) (%) (Rp.) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 50,100,000.00 1.00 50,100,000.00 0.689 1.00 50,100,000.00 0.689 1.00
DIVISI 2. DRAINASE 50,100,000.00 0.689 - 50,100,000.00 0.689 -
2.1 Galian Untuk Selokan Drainase dan Saluran Air M 37,888.00 2,000.00 75,776,000.00 1.042 1,849.33 70,067,415.04 0.963 1,832.02
2.3.5 Gorong-gorong Pipa Baja Bergelombang Ton 37,703,990.35 1.50 56,555,985.53 0.778 0.15 5,655,598.55 0.078 0.23
DIVISI 3. PEKERJAAN TANAH 132,331,985.53 1.820 - 75,723,013.59 1.041 -
3.1.1 Galian Biasa M 24,003.00 1,250.94 30,026,312.82 0.413 - - - -
3.2.1 Timbunan Biasa M 71,022.00 2,000.00 142,044,000.00 1.953 511.46 36,324,772.13 0.499 477.20
3.2.2 Timbunan Pilihan M 106,227.00 1,221.83 129,791,335.41 1.785 2,900.74 308,136,907.98 4.237 2,870.08
3.3.1 Penyiapan Badan Jalan M 2,922.00 27,900.00 81,523,800.00 1.121 25,840.15 75,504,918.30 1.038 26,746.55
DIVISI 4. PELEBARAN DAN PERKERASAN BAHU JALAN 383,385,448.23 5.272 - 419,966,598.41 5.775 -
4.2.2 Lapis Pondasi Agregat Klas B M 455,605.00 1,860.00 847,425,300.00 11.652 1,289.79 587,634,772.95 8.080 1,259.31
DIVISI 5. PERKERASAN BERBUTIR 847,425,300.00 11.652 - 587,634,772.95 8.080 -
5.1.1 Lapis Pondasi Agregat Klas A M 526,671.00 2,790.00 1,469,412,090.00 20.204 2,906.64 1,530,842,995.44 21.049 3,010.14
5.1.2 Lapis Pondasi Agregat Klas B M 449,249.00 3,720.00 1,671,206,280.00 22.979 3,875.52 1,741,073,484.48 23.940 3,904.56
DIVISI 6. PERKERASAN ASPAL 3,140,618,370.00 43.184 - 3,271,916,479.92 44.989 -
6.1.(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 11,249.00 13,950.00 156,923,550.00 2.158 14,691.41 165,263,671.09 2.272 15,189.31
6.3.(6a) Laston Lapis Antara (AC-BC) (gradasi halus/kasar) Ton 521,662.00 2,027.22 1,057,523,639.64 14.541 2,134.97 1,113,732,720.14 15.314 2,203.27
6.3.8.a Aspal Ton 10,809,425.00 126.20 1,364,149,435.00 18.757 132.91 1,436,680,676.75 19.754 123.32
6.3.10 Bahan Pengisi (Filler) Tambahan Kg 1,206.85 41,371.98 49,929,774.06 0.687 43,570.79 52,583,407.91 0.723 44,964.74
DIVISI 7. STRUKTUR 2,628,526,398.70 36.142 - 2,768,260,475.89 38.064 -
7.9 Pasangan Batu M 613,517.00 80.00 49,081,360.00 0.675 161.57 99,125,941.69 1.363 174.22
7.10 (3) Bronjong M 589,406.00 70.00 41,258,420.00 0.567 - - - -
90,339,780.00 1.242 - 99,125,941.69 1.363 -
Jumlah Nilai Pekerjaan 7,272,727,282.46 100.00 7,272,727,282.46 100.00
PPN 10 % 727,272,728.25 727,272,728.25
TOTAL BIAYA PEKERJAAN 8,000,000,010.70 8,000,000,010.70
DIBULATKAN 8,000,000,000.00 8,000,000,000.00

PENYEDIA
Ir. MUDJI HALIM

JOHNNICO APRIANO
DIREKTUR UTAMA
INTAH ACEH
RGA DAN DIPTA KARYA

KONTRAK ADD FINAL


Keterangan
JUMLAH HARGA BOBOT
(Rp.) (%)

50,100,000.00 0.689
50,100,000.00 0.689
69,411,504.95 0.954
8,671,917.78 0.119
78,083,422.73 1.074
- -
33,891,698.40 0.466
304,879,988.16 4.192
78,153,419.10 1.075
416,925,105.66 5.733
573,747,932.55 7.889
573,747,932.55 7.889
1,585,353,443.94 21.799
1,754,119,675.44 24.119
3,339,473,119.38 45.918
170,864,548.19 2.349
1,149,362,234.74 15.804
1,333,018,291.00 18.329
54,265,696.47 0.746
2,707,510,770.40 37.228
106,886,931.74 1.470
- -
106,886,931.74 1.470
7,272,727,282.46 100.00
727,272,728.25
8,000,000,010.70
8,000,000,000.00

PENYEDIA
Ir. MUDJI HALIM

JOHNNICO APRIANO
DIREKTUR UTAMA
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN
MONTHLY CERTIFICATE (MC)
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 1 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

NILAI KONTRAK JUMLAH PEMBAYARAN


NOMOR MATA
URAIAN PEKERJAAN S/D S/D BOBOT (%) BOBOT (%)
PEMBAYARAN KONTRAK AWAL (Rp.) KONTRAK ADD-I (Rp.) KONTRAK ADD FINAL (Rp.) BULAN INI
BULAN LALU BULAN INI S/D BULAN INI ITEM PEKERJAAN
1 2 3 4 5 6 7 8 9 10
1 UMUM 50,100,000.00 50,100,000.00 50,100,000.00 35,070,000.00 15,030,000.00 50,100,000.00 0.69% 0.69%
2 DRAINASE 132,331,985.53 75,723,013.59 78,083,422.73 70,067,415.04 8,016,007.69 78,083,422.73 1.07% 1.07%
3 PEKERJAAN TANAH 383,385,448.23 419,966,598.41 416,925,105.66 415,993,619.55 931,486.11 416,925,105.66 5.73% 5.73%
4 PELEBARAN DAN PERKERASAN BAHU JALAN 847,425,300.00 587,634,772.95 573,747,932.55 - 573,747,932.55 573,747,932.55 7.89% 7.89%
5 PERKERASAN BERBUTIR 3,140,618,370.00 3,271,916,479.92 3,339,473,119.38 3,207,077,907.12 132,395,212.26 3,339,473,119.38 45.92% 45.92%
6 PERKERASAN ASPAL 2,628,526,398.70 2,768,260,475.89 2,707,510,770.40 2,527,370,130.26 180,140,640.14 2,707,510,770.40 37.23% 37.23%
7 STRUKTUR 90,339,780.00 99,125,941.69 106,886,931.74 99,125,941.69 7,760,990.05 106,886,931.74 1.47% 1.47%

A SUB TOTAL 7,272,727,282.46 7,272,727,282.46 7,272,727,282.46 6,354,705,013.66 918,022,268.80 7,272,727,282.46 S/D BULAN INI
B PPN (10%) X A 727,272,728.25 727,272,728.25 727,272,728.25 635,470,501.37 91,802,226.88 727,272,728.25 100.00%
100.00%
C JUMLAH TOTAL A + B 8,000,000,010.70 8,000,000,010.70 8,000,000,010.70 6,990,175,515.02 1,009,824,495.68 8,000,000,010.70
D DIBULATKAN C 8,000,000,000.00 8,000,000,000.00 8,000,000,000.00 6,990,175,000.00 1,009,824,000.00 8,000,000,000.00 BULAN INI
E MATERIAL ON SITE (MOS)
12.62%
F JUMLAH KOTOR SERTIFIKAT BULAN INI
G POTONGAN - POTONGAN S/D BULAN LALU
1 SERTIFIKAT S/D BULAN LALU (KOMULATIF) 5,242,631,250.00
87.38%
2 5 % JAMINAN PEMELIHARAAN ( 5% X D ) 400,000,000.00
3 20 % PENGEMBALIAN UANG MUKA 1,600,000,000.00
H JUMLAH POTONGAN ( 1 + 2 + 3 ) 7,242,631,250.00
I JUMLAH BERSIH SERTIFIKAT BULAN INI TERMASUK PPN 10% (F-H) 757,368,750.00
J DIBULATKAN 757,368,750.00
Terbilang : #VALUE!

DIAJUKAN OLEH : DIPERIKSA/DISETUJUI OLEH : MENYETUJUI OLEH :


PENYEDIA BARANG/JASA KONSULTAN SUPERVISI PPTK
PT. FLAMBOYANT HUMA ARTA PT. CIPTA JAYA UTAMA KONSULTAN PEMBANGUNAN JALAN DAN JEMBATAN
WILAYAH XI (SIMEULUE)

ALWIN ABDULLAH LINDUNG NAINGGOLAN Ir. ZULKARNEN, MT.


DIREKTUR UTAMA SITE ENGINEER Nip. 19640516 199703 1 001

MENGETAHUI OLEH :
KUASA PENGGUNA ANGGARAN / KUASA PENGGUNA BARANG
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN
DINAS BINA MARGA DAN CIPTA KARYA ACEH

Ir. FAJRI, MT
PEMBINA
NIP. 19640831 199203 1 005
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 2 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 1. UMUM JUMLAH KONTRAK ADD FINAL Rp 50,100,000.00

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

1.2 Mobilisasi Ls 1.00 1.00 1.00 50,100,000.00 50,100,000.00 0.70 35,070,000.00 0.30 15,030,000.00 1.00 50,100,000.00

TOTAL HARGA 50,100,000.00 - - -

DIVISI 1. UMUM TOTAL PEMBAYARAN - 35,070,000.00 15,030,000.00 50,100,000.00

PERSENTASE 100.00% 70.00% 30.00% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 3 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 2. DRAINASE JUMLAH KONTRAK ADD FINAL Rp 78,083,422.73

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

2.1 Galian Untuk Selokan Drainase dan Saluran Air M 2,000.00 1,849.33 1,832.02 37,888.00 69,411,504.95 1,849.33 70,067,415.04 (17.31) (655,910.09) 1,832.02 69,411,504.95

2.3.5 Gorong-Gorong Pipa Baja Bergelombang Ton 1.50 0.15 0.23 37,703,990.35 8,671,917.78 - - 0.23 8,671,917.78 0.23 8,671,917.78

TOTAL HARGA 78,083,422.73 - - -

DIVISI 2. DRAINASE TOTAL PEMBAYARAN - 70,067,415.04 8,016,007.69 78,083,422.73

PERSENTASE 100.00% 89.73% 10.27% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 4 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 3. PEKERJAAN TANAH JUMLAH KONTRAK ADD FINAL Rp 416,925,105.66

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

3.1.1 Galian Biasa M 1,250.94 - - 24,003.00 - - - - - - -

3.2.1 Timbunan Biasa M 2,000.00 511.46 477.20 71,022.00 33,891,698.40 505.13 35,875,342.86 (27.93) (1,983,644.46) 477.20 33,891,698.40

3.2.2 Timbunan Pilihan M 1,221.83 2,900.74 2,870.08 106,227.00 304,879,988.16 2,867.57 304,613,358.39 2.51 266,629.77 2,870.08 304,879,988.16

3.3 Penyiapan Badan jalan M 27,900.00 25,840.15 26,746.55 2,922.00 78,153,419.10 25,840.15 75,504,918.30 906.40 2,648,500.80 26,746.55 78,153,419.10

TOTAL HARGA 416,925,105.66 - - -

DIVISI 3. PEKERJAAN TANAH TOTAL PEMBAYARAN - 415,993,619.55 931,486.11 416,925,105.66

PERSENTASE 100.00% 99.78% 0.22% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 5 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 4. PELEBARAN DAN PERKERASAN BAHU JALAN JUMLAH KONTRAK ADD FINAL Rp 573,747,932.55

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

4.2.2 Lapis Pondasi Aggregat Klas B M 1,860.00 1,289.79 1,259.31 455,605.00 573,747,932.55 - - 1,259.31 573,747,932.55 1,259.31 573,747,932.55

TOTAL HARGA 573,747,932.55 - - -

DIVISI 4. PELEBARAN DAN PERKERASAN BAHU JALAN TOTAL PEMBAYARAN - - 573,747,932.55 573,747,932.55

PERSENTASE 100.00% 0.00% 100.00% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 6 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 5. PERKERASAN BERBUTIR JUMLAH KONTRAK ADD FINAL Rp 3,339,473,119.38

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

5.1.1 Lapis Pondasi Agregat Klas A M 2,790.00 2,906.64 3,010.14 526,671.00 1,585,353,443.94 2,849.04 1,500,506,745.84 161.10 84,846,698.10 3,010.14 1,585,353,443.94

5.1.2 Lapis Pondasi Agregat Klas B M 3,720.00 3,875.52 3,904.56 449,249.00 1,754,119,675.44 3,798.72 1,706,571,161.28 105.84 47,548,514.16 3,904.56 1,754,119,675.44

TOTAL HARGA 3,339,473,119.38 - - -

DIVISI 5. PERKERASAN BERBUTIR TOTAL PEMBAYARAN - 3,207,077,907.12 132,395,212.26 3,339,473,119.38

PERSENTASE 100.00% 96.04% 3.96% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 7 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 6. PERKERASAN ASPAL JUMLAH KONTRAK ADD FINAL Rp 2,707,510,770.40

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

6.1.(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 13,950.00 14,691.41 15,189.31 11,249.00 170,864,548.19 14,178.41 159,492,934.09 1,010.90 11,371,614.10 15,189.31 170,864,548.19

6.3.(6a) Laston Lapis Antara (AC-BC) (gradasi halus/kasar) Ton 2,027.22 2,134.97 2,203.27 521,662.00 1,149,362,234.74 2,056.64 1,072,871,053.78 146.63 76,491,180.96 2,203.27 1,149,362,234.74

6.3.8.a Aspal Ton 126.20 132.91 123.32 10,809,425.00 1,333,018,291.00 115.12 1,244,352,036.74 8.20 88,666,254.26 123.32 1,333,018,291.00

6.3.10 Bahan Pengisi (Filler) Tambahan Kg 41,371.98 43,570.79 44,964.74 1,206.85 54,265,696.47 41,972.16 50,654,105.64 2,992.58 3,611,590.83 44,964.74 54,265,696.47

TOTAL HARGA 2,707,510,770.40 - - -

DIVISI 6. PERKERASAN ASPAL TOTAL PEMBAYARAN - 2,527,370,130.26 180,140,640.14 2,707,510,770.40

PERSENTASE 100.00% 93.35% 6.65% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT
PEMERINTAH ACEH
DINAS BINA MARGA DAN CIPTA KARYA
PEMBANGUNAN JALAN DAN JEMBATAN WILAYAH XI SIMEULUE

SERTIFIKAT BULANAN

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 8 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA

DIVISI 7. STRUKTUR JUMLAH KONTRAK ADD FINAL Rp 106,886,931.74

KUANTITAS S/D BULAN LALU BULAN INI S/D BULAN INI


NOMOR HARGA SATUAN JUMLAH HARGA
MATA URAIAN PEKERJAAN SAT. ADD FINAL JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
KONTRAK KONTRAK KONTRAK
PEMB. (Rp.) (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12

7.9 Pasangan Batu M 80.00 161.57 174.22 613,517.00 106,886,931.74 161.57 99,125,941.69 12.65 7,760,990.05 174.22 106,886,931.74

7.10 (3) Bronjong M 70.00 - - 589,406.00 - - - - - - -

TOTAL HARGA 106,886,931.74 - - -

DIVISI 7. STRUKTUR TOTAL PEMBAYARAN - 99,125,941.69 7,760,990.05 106,886,931.74

PERSENTASE 100.00% 92.74% 7.26% 100.00%

DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT OLEH :


PEMBANTU PPTK KONSULTAN SUPERVISI PENYEDIA BARANG/JASA
PEMBANGUNAN JALAN DAN JEMBATAN PT. CIPTA JAYA UTAMA KONSULTAN PT. FLAMBOYANT HUMA ARTA
WILAYAH XI (SIMEULUE)

RUSVAN VERIZAL, ST EDWARD NOUR, ST SYAHRIZAL, ST.


Nip. 19830706 201001 1029 CHIEF INSPECTOR GENERAL SUPERINTENDENT