1-AFS-FF-NCR-0001-R00
Package: P02.1 - EXTERNAL FIRE-FIGHTING SYSTEMS
Project Name: NFPC Mega Plant- MILCO / LACNOR / OASIS Factory
FROM: NEB- National Engineering Bureau TO: CES General Contracting co.
Activity: Painting and Flashing for Pipes Initiated by: Eng. Nabeel Qutub
ENGINEER'S USE
Description of Non Conformance : During site visit, Mechical team have observed that the G.I Pipes is not painted by
redoxide (primer) before executing the final paint, also the flashing process should
be carried out before fixing the sprinker system, Al Rashidya is requested to do the
above and rectifing non conformance work.
ENGINEERS INITIATORS :
NAME : Nabeel Qutub - Eng. Esmail Salam DESIGNATION SIGNATURE DATE TIME
P.M. 5/Sep/2017 10 AM
Distribution: Contractor Engineer PMC Cost Consultant Employer File
CONTRACTORS RECEIVER
NAME : DESIGNATION SIGNATURE DATE TIME
CONTRACTORS INITIATOR
NAME : DESIGNATION SIGNATURE DATE TIME
SUPERVISED BY ENGINEER
NAME
DESIGNATION
TIME
Cheked by the Initiator:
Corrective action implimented Yes No
Completed and documented Yes No
Engineer comments :