Professional Documents
Culture Documents
Method Statement-Ext Pipe Fittings
Method Statement-Ext Pipe Fittings
Rev No: 01
Project Name:
Page 1
Doc No:
Rev No: 01
1.0 Purpose 3
2.0 Scope 3
3.0 Abbreviation 3
4.0 Reference 3
1.0 PORPOSE.
This document explains the procedure to be followed during surface preparation and
coating of AG pipes/fittings external surface & UG fittings external surface.
Page 2
Doc No:
Rev No: 01
3.0 ABBREVIATION
PS : Production Supervisor
PO : Purchase Order
4.0 REFERENCE
5.0 RESPONSIBILITIES
The Production Engineer ,Production Supervisor (PS) & QC inspector (QCI) shall be
responsible for production activities ensuring all aspects of the work is carried out as per
the above referred documents requirements. He shall ensure the first line coordination with
management and client for managing all relevant project specific requirements. Production
engineer shall be the contact point for Clients project Manager/Engineer. Inspection
request shall be send by production engineer as per the request from QC inspector.
Production Engineer.
Page 3
Doc No:
Rev No: 01
Overall responsible for the project execution in line with project specification and as
per the reference standards.
He will be direct contact point for the clients Project Manager/Project engineer
Submitting the progressive invoices to the client as per PO requirements.
Notifying the deviations (if any) in advance and take clients approval (PO) before
proceeding with painting works.
Production Supervisor.
Overall responsible for the project execution at site in line with project specification
and as per the reference standards.
He is the direct contact point at site for the clients Project Manager/Project engineer
Responsible for executing all activities related to blasting and painting and reporting
to Project Engineer
He has to plan day to day activities and deputing the resources various activities in
the project.
Preparing the daily activity report based on resources used, job completion, etc and
reporting to Project Engineer on daily basis.
Recording the daily consumption of consumables, paint material, fuel, abrasives etc.
QC Inspector.
Responsible for managing all quality requirements at site in line with project
specific requirements and PO requirements.
He is the direct contact point for the QC representative of the client at site and
reporting to Project Engineer.
Recording and monitoring the ambient conditions.
Preparing all QC related reports, test packs on daily basis.
Conduct/performing all required inspection and testing in line with Project & PO
requirements and offering the same to client/Paint QC representative.
Maintain the copies of inspection equipments valid calibration certificates for
ready reference.
Page 4
Doc No:
Rev No: 01
The sequence of blasting and painting of pipes & fittings as per project specification
are detailed below.
M/s.XX shall sent un-coated pipe & fittings to our yard with proper packing. Our
Supervisor will check & verify the quantity. If any discrepancies noticed in quantity ,the
same shall be noted in Delivery note. Forklifts shall be used for unloading & handling of
pipes & fittings. Pipes shall be properly stacked & stored in outside. Fittings have to send in
wooden boxes & same shall be stored outside in same condition.
While receiving paint material from paint manufacturer, verify the quantity of paint
with Delivery order. Check the batch number and shelf life of paint and it should be
conform to the batch certificate of paint. Paint material shall be stored in temperature
controlled room.
Garnet (abrasive) shall be received in 2 tons bags. Quantity & batch number shall be
verified with DO & Batch certificates.
Pipes & Fittings External Blasting shall be carried out on properly dried surface free
of any moisture or contamination. Blasting standard and profile shall be achieved as
per painting systems.
Stripe coat shall be applied prior to each and every coat to achieve required DFT to
the critical areas ,corners,edges,weld joints small areas which are difficult to spray .And
paint manufacturer recommendation shall be followed in line with project requirements.
Page 5
Doc No:
Rev No: 01
6..7 Inspection
Stage wise inspection shall be conducted by our QC from raw materials to the
finished product in line with paint manufacturer, project and PO requirements.
The blasted surface shall be free from grit particles by blowing dry compressed air.
Blasting standard & surface profile requirements shall be checked in one per shift and it
should be 50-75 microns on pipes external.
The blasting and painting shall not be done while the weather conditions are
beyond the range specified in the applicable data sheet
Note: GTC QC shall monitor all painting activities. He shall inspect the job after
blasting/painting of each coat and upon satisfaction, shall offer the same to client
Page 6
Doc No:
Rev No: 01
Abrasive blast clean to Sa2.5 (ISO 8501-1:1988) or SSPC-SP 10. If oxidation has
occurred between blasting and application, the surface should be re-blasted to the
specified visual standard.
The surface profile on the blasted surface shall be 50-75 microns
A cut back (No paint) of 50mm shall be given to both ends of pipes & fittings.
Apply one coat of AMERCOAT 68G at 75 micron DFT.
Prepare the prime coat surface by emery paper and stripe coats should be applied to
all welds any other areas where spray application of the overall coating system may
prove difficult resulting in low dry film thicknesses.
Apply one coat of AMERCOAT 310 at 150 micron DFT.
Prepare the second coat surface by emery paper and stripe coats should be applied
to all welds any other areas where spray application of the overall coating system
may prove difficult resulting in low dry film thicknesses.
Apply one top coat of AMERCOAT 450 H at 50 micron DFT (Color need to be
confirmed by client)
Total DFT of paint system shall be 275 microns. All paint material shall be
from M/s.PPG AMERON Paints.
Painting System UG Fittings External. (System M)
Abrasive blast clean to Sa2.5 (ISO 8501-1:1988) or SSPC-SP 10. If oxidation has
occurred between blasting and application, the surface should be re-blasted to the
specified visual standard.
The surface profile on the blasted surface shall be 50-75 microns
A cut back (No paint) of 50mm shall be given to both ends of fittings.
Apply two coats of AMERLOCK 400C at 2 x 200 microns DFT.
Prepare the prime coat surface by emery paper and stripe coats should be applied to
all welds any other areas where spray application of the overall coating system may
prove difficult resulting in low dry film thicknesses.
Apply one coat of AMERCOAT 450 H at 75 micron DFT.
Page 7
Doc No:
Rev No: 01
Page 8
Doc No:
Rev No: 01
All the coating materials will be stored in safe containers, out of sunlight, and in a
position where they do not pose a fire risk to other areas.
All paint materials shall be stored in controlled temperature room as per
manufacturers TDS.
All coating material and thinner will be in original unopened containers being with
the manufactured label, batch number and instruction. 2 x 4.5kg DCP
extinguishers should be provided in paint storage area and near to the compressor.
9.2 Mixing:
Paint shall be mixed in accordance with manufacturers instruction and shall
be mixed immediately prior to application by mechanical agitator. The mixing will
continue while pouring curing agent until the mixed material is ensured of
uniformity and continuity of flow. Mixed paint will be mildly agitated during
application to avoid bottom settling. Thinner will be added to improve spraying
properties only and within the limits recommended by manufacturer. Only paint
manufacturers recommended thinner will be used.
Page 9
Doc No:
Rev No: 01
Therefore no naked flames, cigarettes or matches should be allowed near the area
where the work/ paint is being applied or stored. Precautions should be taken avoid
sparks caused by metal to metal
Contact from electrical appliances. Appropriate ventilation should be maintained to
avoid vapor build up especially in an enclosed space.
9.5 Skin and Eye contact
If paint is spilled the following precautions should be taken:
Ventilate the area to remove the fumes.
Mop up all spilled paint with absorbent material, ensuring that all materials used to
mop up the paint are disposed of in closed metal containers.
It is recommended that the following precautions should be taken to prevent paint
coming in to contact with the skin and eyes.
Select sensible working clothes, that cover as much of the body as possible.
Always wear gloves and eye protection. Replace /clean eye shields, etc. fairly
frequently when spraying to prevent accidents due to obscured vision.
Do not touch your mouth or eyes with your gloves.
Remove rings and watch straps before starting work as they can trap paint or
solvent next to the skin.
Eyes are particularly sensitive, so if you are splashed in the eyes by paint or
thinners flood them immediately with fresh water for at least 10 minutes and seek
medical advice immediately.
If paint should splash on your skin, remove it with soap and water or any other
industrial cleaner, never use solvent.
Despite these precautions paint can still come into contact with the skin or eyes
(e.g. spray mist, excessive splashing) so a no greasy barrier cream is recommended
for all exposed skin. Temporary eyewash facility shall be arranged at work site.
Remember the objective is to avoid skin contact, if your clothes become soaked in
paint, change them immediately wash the affected garments with soap and water
Page 10
Doc No:
Rev No: 01
Page 11
Doc No:
Rev No: 01
Page 12
Doc No:
Rev No: 01
*****
Page 13