Professional Documents
Culture Documents
RVG CARD Steel Plant
RVG CARD Steel Plant
Prepared by
A. UDAYKUMAR
M.S.V. SANTOSHKUMAR
S.V. SUSHIL PRABHAKAR
T. HAREESH
SRI A.S.V.GOPALARAO
Dy. Chief Manager(E)
SMS/CCD/E
I take this movement to convey our sincere thanks to my project guide SHRI
A.S.V. GOPALA RAO, Chief Manager (E), SMS/CCD, for his valuable suggestions
A.Udaykumar
M.S.V.SantoshKumar
S.V.SushilPrabhakar
T.Hareesh
DECLARATION
training. It is the project done by us with the support of the members in your
organization.
A.Udaykumar
M.S.V.SantoshKumar
S.V.SushilPrabhakar
T.Hareesh
CERTIFICATE
This is to certify that the project report entitled “REFERENCE VOLTAGE
record of bonafide work carried out by them under my guidance and supervision.
A.S.V.GOPALA RAO
Dy. Chief Manager(E)
SMS/CCD/E
INDEX
1. Introduction
5. Advantages of project
8. Conclusion
INTRODUCTION
Steel melting shop is the heart of any steel plant where steel making
process is being done. In VSP steel melt shop is equipped with three LD
converters and six number of bloom casters with 100% continuous casting
facility.
mould with a false bottom through which partially solidified ingot\ bar
withdrawn at the same rate at which the liquid steel is teamed in the
mould.
roles is very much important in our plant 11kw DC Motors are used for the
thyristor panels for speed control of withdraw role motors one is working
panel is designated as 51AS1. If there is any failure in this panel for more
Of late both the electrics and electronics of the said 51AS1 is giving
circuit. This will lead to maximum troubleshoot time and down time.
The most influencing factor to taking of this project is to generate
such that total reference circuit can be replaced by single RVG card. And
existing relays are sealed type, in this physical contacts cannot be seen with
been prepared such that two individual reference circuit will be provided
for individual thyristor drives. Circuit also made simple for easy trouble
shooting. Existing sealed relays are rep-laced with normal relays with
single RVG card, the circuit is connected to M\c 2 Std 4, 52AU1, thyristor
smooth and linear. It is better than the earlier system. We observed it for
Now we made a total circuit with the RVG card in a single board for a
reference for both 51AU1 and 52AU1, thyristor converters. After that in
M\c 4 Std 3 whole 51AS1 circuit as been replaced with new modified
conditions. This casting speed will vary through the reference given to
thyristor drive. In earlier Russian system one separate panel (51AS1) was
there and in that a lot of cards were there. This was common reference
panel for both 51AU1 and 52AU1 drives. Hence the separate power supply
cards also provided for both 51AU1 and 52AU1. Ultimately total 10 number
With this reference generation can be done and all adjustment pots were
supply can be tapped from thyristor drive reference can be given to the
same drive. Hence this isolation cards are not required. In this system we
can put two cards for two drives so that change over facililty will be
Original Russian system occupies more space. New system occupies almost
In original system terminal blocks were given in front and back side of the
panel and it is different for point to point checking as one terminal is in front
Whereas in our new system all terminal are provided in front side only and in a
same row.
In existing system trouble shooting is very difficult and circuit also very
Whereas in our system we used one simple RVG card for reference generation
In sealed relays we cannot find contact or coil problem and it is not possible to
see the relay condition with the naked eye whether the relay is in picked or in
dropped.
Whereas in modified system we used the glass relays , by seeing with the eye
we can easily find out the position of the relay and relay contact also.
Spares are also not available for Old Russian system. For new system spares
In earlier system reference generation is common for both the thyristor drives
of the strand.
each drive and any problem in one circuit we cwn change the reference
It is difficult to adjust joint mode oscillations during the casting as all individual
Whereas in this new system we can adjust the joint mode oscillations in
In the course of doing this project, I have found that it was very interesting,
informative and result oriented. With these type if projects it has lot of
benefits to reduce brake down time, easy for maintenance and above all the
innovation.
WORKING OF THE THYRISTOR DRIVES
(51AU1 &52AU1)
The thyristor power circuit panel has two independent circuits and the four
motors are connected to this circuit with the help of two knife switches, based
card S402A and voltage feedback is connected to S402. Two thyristor bridges
(3-Φ bridges) one in the forward direction and the other in the backward
direction are connected as shown between the supply mains and the feedback
circuit whose firing angles are decided from the block diagram as shown.
Initially signals from 51AS1 are given to the card N404 which is considered
N222 (dummy card mode) generates the other reference signal which is a fixed
one. Now both these reference signals are given to a ramp generator which
has two test points u1 and u2 . The ramp generator generates the ramp signal
and this is fed to a speed regulator, the second input required comes from emf
generator to which the voltage and current feedback circuits (S404 and
S402A) are given as inputs to this card N205. The speed regulator provides a
smooth regulation of the speed whose output is again fed to a ramp generator
and a logic card N125. The output from the thyristor panel is given to the
thyristor sensor card S118 is fed to the logic card N125. The logic card
generates the desired logic that to what extent the firing of the thyristor
bridges TM1 and TM2 has to be done and is given to the firing card N123A.
ramp generator N205 generates a ramp output and gives to the current
regulator where a maximum value of current is regulated and the other input
comes from the current feedback circuit gives the other input to this card
N210. The output from the current regulator is given to a phase angle control
card in which min and max values of α are fixed to maintain the desired
voltage in the thyristor bridges. The supply to this card comes from the
given to the filter card N102, supply is given to the phase angle control card
the output of this is given to the firing card N123A. Now the output of this is
given to the amplifier cards (TM1 and TM2). Based on whether the thyristor
and gives to the thyristor panel through isolators from the thyristor panel to