Professional Documents
Culture Documents
MOECC Municipality of Kincardine 2017
MOECC Municipality of Kincardine 2017
MOECC Municipality of Kincardine 2017
2
What Requires a Renewable Energy
Approval
In general, all large wind, solar and bio-energy Wind Projects
projects require a REA including:
Wind >50kW (small wind 3kw-50kW have
streamlined requirements)
Ground mounted solar >500kW (Solar projects
between 10kW 500kW can go through EASR)
Solar Projects
Bio-energy facilities (anaerobic digestion or thermal
treatment facilities using biomass, biogas or
biofuel)
REA does not apply to: Waterpower projects;
Rooftop solar; Bio-energy projects on farms that opt Bioenergy Projects
to follow the Nutrient Management Act process
instead, and very small projects (e.g. wind <3kW,
solar <10kW)
3
Wind Facility Approvals
ECA* REA
Pre-September 2009 Post-September 2009
5
Ministry Compliance Approach
6
Compliance Approach
7
Proactive Compliance Initiatives
Pre-Construction Post-Construction
Inspection Inspection
(Completed by SCB prior to April 1, 2017)
8
Complaints
Noise
85% of complaints
Shadow Health Safety
Related to loss of
enjoyment and health
Flicker Lights
Various symptoms
including
effects Temporary condition
Usually broadband Fatigue Transport Canada
Shadows flick on and Loss of
Tonal noise requirement
off as blades rotate concentration
Infrasound Not required for every
Construction Head-ache turbine
Ear-ache
9
Reactive Compliance Activities
10
Quantitative Noise Assessment
Two types of noise monitoring can be conducted at a sensitive
receptor and/or complainants residence:
11
Quantitative Noise Assessment
continued
Results of noise monitoring is used to inform whether a more
comprehensive assessment is warranted and/or if a Noise
Abatement Action Plan is required.
12
Enbridge Wind Facility
13
Enbridge Wind Facility
Second report (draft) submitted in March with updated sound level reports
submitted in August 2013. Enbridge indicated that they were unable to
collect enough data at the 7 m/s wind speed to make any conclusion.
In December 2013 the ministry confirmed that the report was incomplete as
the acoustic audit was unable to attain sufficient ambient measurement data
points at the 7 m/s wind speed interval.
In April 2015 the ministry requested additional monitoring which took place
from July to September, 2015. Insufficient data was collected at higher wind
speeds as confirmed by the ministry in December 2015.
In 2016 the ministry began work on a updated Compliance Protocol with
revisions to the assessment methodology. This was posted to the EBR on
May 02, 2016. Comments received were incorporated into the revisions.
14
Enbridge Wind Facility
15
Armow Wind Facility
16
Armow Wind Facility
17
Contact
18