ALPHA DRIVES PREVENTIVE MAINTENANCE SCHEDULE CUM RECORD Revision/Date 00/01.06.2016
Machine Name Horizontal Machining Center Machine No. Month & Year July 2016

Sl.No. Activity Freq. Days


To be done on daily before start of morning shift 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Clean oil, dust, dirt on the outside of machine using dry cloth
2 Check Servo 68 oil level in Hydraulic oil tank
3 Check air pressure in FRL unit is 5 bar
4 Clean dust, oil, dirt in Front & side glass door using dry cloth

Daily
5 Check LAVISA Super 90 Coolant oil level.
6 Open AC air Filter & clean with air.
7 Check any Tools are damaged
8 Clean dirt, chips in the Fixture.
9 Check any loose or damaged parts in Fixture.
Remarks if any
Operator sign

To be done on first working day of every week Week 1 Week 2 Week 3 Week 4

10 Remove filter from Coolant tank & remove dust / dirt using air
11 Clean chips, dirt in bottom side of Chip Conveyor
12 Clean Tool pockets using dry cloth
Weekly

13 Clean ATC unit using dry cloth


14 Clean dirt, dust in outer area of Panel Box using dry cloth
15 Check Spin 12 oil level in FRL unit
16 Clean oil, dirt in Front & Side Door Slide ways using dry cloth
Remarks if any
sign & Date
Operator

- Checked and found OK X - Checked and found not OK. Details to be recorded in this sheet