1. Concrete K225
No.
1 3.954 x 64 = 253.056
2. Form Work
1 5 x 64 x 2 = 640
2 3.954 x 2 = 7.908
= 647.908
3. Lean Concrete
1 5.00 x 64.5 x 0.05 = 16.125
4. Gravel Bedding
1 5.00 x 64.5 x 0.15 = 48.375
6. Concrete Pile
1. Concrete K225
No.
1 3.954 x 29 = 114.666
2. Form Work
1 4.7 x 29 x 2 = 272.6
2 3.954 x 2 = 7.908
= 280.508
3. Lean Concrete
1 4.50 x 29 x 0.05 = 6.525
4. Gravel Bedding
1 4.50 x 29 x 0.15 = 19.575
6. Concrete Pile
A GENERAL
a.1 Mobilisation and demobilisation unit 5 2,500,000
a.2 Topographycal survey by Trisutrisno LS 1 25,000,000
a.3 Soil investigation (Sondir) 3 point LS 1 6,000,000
a.4 Safety protection for excavation Jam 48 340,000
sub total
B EARTH WORKS
B.1 Excavation of soil and disposal m3 12735 22,000
B.2 Back fill and compacted layer by layer each 40cm m3 12735 30,000
B.3 Back fill selected material and compacted layer by layer each 40cm m3 5850 35,000
sub total
E DRAINAGE WORK
e.1 Geotextile Tipr 325 (produk Geosinindo) Roll 1 17,500,000
e.2 Sand stone m3 38.4 350,000
e.3 Stone for gabion 3-7 cm m3 31.61 425,000
e.4 Pvc pipe dia 4" m' 205 95,000
e.5 Tee 4" Rucica nos 38 55,000
sub total
Total
12,500,000
25,000,000
6,000,000
16,320,000
59,820,000
280,170,000
382,050,000
204,750,000
866,970,000
25,000,000 252 84
208,656,000 1056
25,200,000
48,384,000
307,240,000
10,080,000 176
14,997,800
15,323,500
291,019,000
92,250,000
220,158,720
643,829,020
17,500,000
13,440,000
13,434,250
19,475,000
2,090,000
65,939,250
1,943,798,270
BILL OF QUANTITIES
Total
25,000,000 252 136
144,072,000 1056
17,400,000
33,408,000
219,880,000
6,960,000 176
6,068,250
6,198,750
131,865,900
42,076,200
81,922,970
275,092,070
494,972,070
BILL OF QUANTITY
SLOPE PROTECTION AE3
A General
A.1 Mobilisation and demobilisation unit 5.00 9,500,000
A.2 Topographycal survey by Trisutrisno LS 1.00
A.3 Soil investigation (Sondir) 3 point LS 1.00
A.4 Safety protection for excavation Jam 48.00 110,516,000
SUB TOTAL A
B Earth Works
B.1 Excavation of soil and disposal m3 12,735.00 21,000
B.2 Back fill and compacted layer by layer each 40cm m3 12,735.00
Back fill selected material and compacted layer by layer
B.3 m3 5,850.00 26,000
each 40cm
SUB TOTAL B
C Construction Works
C.1 Mobilisation and demobilisation ls 1.00
C.2 Concrete pile # 300x300x6000 m' 1,536.00
C.3 Loading and unloading of concrete pile m' 1,536.00
C.4 Pilling m' 1,536.00
SUB TOTAL C
SUB TOTAL D
E Drainage Works
E.1 Geotextile Tipr 325 (produk Geosinindo) Roll 1.00
E.2 Sand stone m3 38.40
E.3 Stone for gabion 3-7 cm m3 31.61
E.4 Pvc pipe dia 4" m' 205.00
E.5 Tee 4" Rucica nos 38.00
SUB TOTAL E
TOTAL ( A + B + C + D + E )
GRAND TOTAL
F QUANTITY
ROTECTION AE3
May 2017
Amount
47,500,000
5,304,768,000
BILL OF QUANTITY
SLOPE PROTECTION AE6
A Construction Works
A.1 Mobilisation and demobilisation ls 1.00 25,000,000
A.2 Concrete pile # 300x300x6000 m' 696.00 207,000
A.3 Loading and unloading of concrete pile m' 696.00 25,000
A.4 Pilling m' 696.00 48,000
SUB TOTAL A
SUB TOTAL B
TOTAL ( A + B )
GRAND TOTAL
F QUANTITY
ROTECTION AE6
June 2017
Amount
25,000,000
144,072,000
17,400,000
33,408,000
219,880,000
6,960,000
6,068,250
6,198,750
131,865,900
42,076,200
81,922,970
275,092,070
494,972,070
494,972,070
BILL OF QUANTITIES OF
SLOPE PROTECTION AE3
CONSTRUCTION PROJECT
MAY 2017
BILL OF QUANTITIES AND SPESIFIKASI
SLOPE PROTECTION AE3
CONSTRUCTION PROJECT
MAY 2017
SPESIFIKASI OF
SLOPE PROTECTION AE3
MAY 2017