Professional Documents
Culture Documents
Cbes Major Final
Cbes Major Final
DELHI
KATHPUTLI COLONY SLUM J.J. CLUSTER, DELHI
SUBMITTED BY:-
SAI KUMAR JASTI - A13559017234
RAHUL JANGHU A13559017113
AMARKANT SHARMA A13559017133
CHAPTER 1
Slums are defined as the residential area where dwellings are unfit for human
settlement. It is estimated that there are about 1.38 crores of household which are in
slum area, that is about 18% of the urban population, and the expected rise in
population of slums is assumed 11.6 millions from 2011 to 2017.
Delhi, the national capital of India has about 2.1 million people living in slums and it
is about 12% of its total population.
CHAPTER 2
PROJECT RATIONALE
Kathputhli Colony is a 40 year old slum which houses families of magicians, folk
singers painters acrobats, painters, dancers, acrobats, puppeteers and story tellers etc
in shadipur depot area Delhi.
It is estimated that about 2800 families live in this slum. This is the second largest
slum in india. after Dharavi slum in Mumbai.
These people living in slum areas they dont have proper housing and basic
infrastructure for the habitat of a human being. They lack in basic necessities like
water, toilets, sewer lines etc. Also a forced eviction can happen to them anytime by
anyone powerful as they dont have any legal proof of their residence.
So in order to help these people provide a better infrastructure and utilising the
unplanned land wasted on slums this redevelopment project was needed.
3. FEASIBILITY ANALYSIS
5.22 hectare of land for 6.11 crores to Raheja Developers with an expected cost of
Rs.254.27 crores. The building has a proposed height of 190 meters and 54 floors.
constructed is 2800 with a dwelling unit of minimum 30.5 sq.m. with a room of 9
sq.m. and a multipurpose room of 6.5 sq.m. and one bathroom of minimum 1.2 sq.m.
and a kitchen of 3.3 sq.m. This project is a being in-situ type of project which means
the people living over there are settled at the site only instead of moving them to other
places.
This project comes under PPP mode that is Public Private Partnership mode.
The other modes of financing this project can be taking loans from infra
The circle rates of that area is about Rs. 45000/sq.m. for flats and the flat rates
The kathputi colony has a large number of communities. Basically it was a colony of
rajasthani migrants but today it comprises of communities across all India. These lines
are not only geographical but are economical as well, where many people live in
jhuggis only some live in more developed version of it which is made of bricks and
has electrical outlets connected for TVs and overhead fans. These economic borders
relocation represent a better living standards for some and loss for others. But
negotiations were made with the leaders of these slums which were called pradhans
Impact Assessment Authority (SEIAA). And the clearance was given to them only
Percentage land use demarcation for various infrastructure and green areas in
PLANNING:
-Time taken for the completion of the project. It is split in different
stages:
-Due diligence: legal, permissions, verifications, GPA's, plans etc these
are the first stage of the planning.
Construction stage and executions:
-Foundations to completions that is below ground level and above
ground level and it includes all the finishes of the building and
Construction of basement
Construction of services
Construction of amenities.
Handing over stage:
-Snag stage: preparation and handing over the flat with completing all
the finishes to the customers to their satisfaction.
-again after the customer is handed over the flat we should complete
their requirements for what we had specified in the specs.
DESIGN:
Very important stage which is the soul of the project. This includes three
parameters:
Super structure
Brick work with Clay bricks or Fly ash bricks in cement mortar.
Plastering
Double coat sponge finish cement plastering 18mm thick for outside
walls and common areas. Plastering/ zyproc/ pop finish for internal
walls.
Main Door
Teak wood frame with aesthetically designed teak veneered flush door
shutter with melamine polished with standard hardware.
Internal Doors
Teak wood frame with laminated/ skin/ membrane flush door shutters
of standard make with standard hardware with enamel paint.
Windows
Aluminium / UPVC glazed sliding shutters with mosquito mesh shutter of
standard make with MS grill.
Toilets:
Best quality acid resistant and Anti skid designer Tiles.
Parking:
Cement based Designer Tile/ VDF Flooring.
Kitchen:
Granite platform with stainless steel sink of FRANKE MAKE or equivalent
with separate bore & municipal water connection. Provision for cabinets
and exhaust fan, chimney & water purifier
Painting
Internal:
Plastic emulsion paint over NCL ALTEK or equivalent putty for all Rooms
with smooth finish.
Waterproof paint over Birla wall / JK wall putty for toilets and Balconies.
External:
Texture with weather proof paint with ASIAN / ICI Make.
SANITARY:
PVC pipes / SW pipes / Concrete NP 2 pipes for sanitary & drainage lines.
American standard or equivalent makes wash basins & water closets.
RAK / JAQUAR / GROHE or equivalent make CP fittings
Electrical
Concealed copper wiring with ISI marked cables and standard make
modular switches.
Provision for A/C in master bedroom
Power outlets for geysers in all bathrooms.
Power plug for cooking range chimneys, refrigerator, micro oven, mixer
grinders in kitchen.
Telephone and TV provision in master bedroom and hall.
3-phase supply for each unit and individual meter boards, Miniature
Circuit Breakers (MCB) for each distribution board of standard make.
Lifts
Lifts of JOHNSON / OTIS / KONE / SCHINDLER make.
EXECUTION:
-This has been distributed in 2 parameters:
3. Time:
As per the planning schedule the project speed and quality is
continuously monitored and any delays have been encountered
with catch up plans.
As per the quality schedule.
HANDOVER PARAMETERS:
-Initially the project after the completion every unit is handed
over to the CRM team (customer relationship management).
-Then CRM team visits each and every unit and prepare snag
list for which construction team will complete the snag list and
handover to the customers.
-Then the customers further may give some more snags and a
final handing over document is prepared and customer sign is
taken.
APPROVALS
(B) Sanction Stage - Lay Out Plan/ Local Area Plan/ Urban Design Plan
(B3.1)Approval from the Forest Department, GNCTD when there is a proposal for
tree cutting/ felling and transplantation at the site.
(B5.1)NOC from the Road Owning Agency (MCD, Delhi PWD, NDMC, DDA) when
cutting of footpath or road or service lane or Right of way (ROW) is involved.
(B6.1)NOC from the Delhi Traffic Police when the proposal involves disruption of
general traffic movement/ circulation pattern temporarily or permanently during and
after the construction of the project.
(B.7) APPROVAL FROM CHIEF FIRE OFFICER
(B7.1) Approval /Fire Safety Certificate from Chief Fire Officer (CFO) / Director,
Delhi Fire Service for the proposals at layout plan stage as stipulated in the Delhi
building byelaws and National Building Code (NBC).
(B.8) APPROVAL FROM DELHI URBAN ART COMMISSION (DUAC) for the
proposals at layout plan stage as stipulated in the DUAC Act.
(C1.1)Approval from the local body /authority (DDA / MCD/ NDMC) for sanction of
building plans/ building permit under the provisions of Delhi Building Byelaws,
Master plan of Delhi and Local Body Acts. The local body forwards the proposals to
the various other concerned authorities (as mentioned above at S.No. 8 - 21) in the
city as required for issue of case specific approvals/ NOC before granting building
permit.
(C2.1)Approval/ NOC from DCP (Licensing) for the proposals when the proposal
includes construction of auditorium/ theatre/ large hall of seating capacity of more
than 50 persons to be used for public amusement.
(C.3) APPROVAL FROM THE POWER DISTRIBUTING / SUPPLY AGENCY
(NDMC/BSES/NDPL)
(C3.1) Approval from the Power distributing / supply agency (NDMC/ BSES/ NDPL)
for sanction of electrical load and requirement for the electrical substation and
provision of transformers. The temporary connection for power supply needs to be
obtained from the concerned authority before start of construction.
(C4.1) Approval / NOC /assurance from the water supply agency (NDMC for NDMC
area/ DJB for rest of Delhi) for uninterrupted water supply, drainage and sewerage
connections. The temporary connection for water supply needs to be obtained from
the concerned authority before start of construction.
(D2.1) The owner/applicant who has been granted building permit shall intimate the
local Authority (DDA/ NDMC/ MCD) in writing before 7 days of starting of
construction work at site in the prescribed form (Form III, Appendix 'B', Bye Law
No.7.2.1). An acknowledgement needs to be obtained from the Authority of this
notice.
(E2.1) NOC from the Lift Inspector, GNCTD before granting Completion-cum-
Occupancy Certificate when lifts are installed in a building.
PROJECT PROFESSIONALS
Lead contractor
Project manager
Architects
Consultants
o Structural
o Electrical
o Plumbing
o HVAC
o Landscape
o Interior design
o Special design
SCOPE IDENTIFICATION
School
Community center.
The selection of construction contractors are very often conducted during tendering.
Tendering definitely gives a client a choice in awarding contract a company which
purposes the lowest price and short construction cycles, but usually they dont allow
to precisely evaluate the tender.
This in-situ slum rehabilitation project comes under PPP mode and the selection of
contractor was done on two basis, that is technical bid and financial bids.
Eight developers qualified for the bid. Which was awarded to a Delhi based
developer, Raheja Developers.