Daily Site Progress Report

Project CATHODIC PROTECTION INSPECTION, 2017

Contractor Velosi (M) Sdn. Bhd


Date 06th Jan 2017

1.0 Weather Record

AM: Clear / Cloudy / Rainy PM: Clear / Cloudy / Rainy

2.0 Progress done


1. Material declaration at NCSP main gate
2. Safety induction at NCSP administration building
3. Electrical inspection for all meters and equipments at NCSP electrical workshop
4. Obtain work permit in NCSP terminal
5. On/Off cycles, GPS timer, synchronization settings for both current interrupter units in Dinh Co terminal
and Phuoc Hua station

3.0 Planned progress tomorrow


1. Installation of 1 unit of current interrupter unit at NCSP transformer unit in Dinh Co plant
2. Testing and setting of synchronization cycle within interrupter units located in Phuoc Hua and Dinh Co
terminal
3. Pipe-to-soil potential at PVG and NCSP test posts from Long Hai to Phu My

4.0 Finding / Abnormalities


1. The GMT time in our current interrupter units cannot be adjusted to synchronized with PVGs in Phuoc
Hua station. Planned to used interrupter unit belong to NCSP

Prepared By: Authorized By:


(Please include companys official stamp) (Please include companys official stamp)
Name: Mohd Arzaine Abu NCSP Representative
Position: Site Supervisor Name:
Company: Velosi (M) S/B Position: