Supplying of Geo-textile bags (empty) of different sizes and capacity (fill volume and weight when
filled dry sand) at project/ work site including fabrication and supply of geo-textile fabric (mass400
gm/m2 ) and sewing in accordance with the detailed drawing and technical specifications included in
1 the tender document and schedule of rates of BWDB, protecting the geotextile bags form UV ray or
any other damages including cost of all materials, labours, taxes, including changes etc. complete as
per direction of engineer in charge.

Geo-bag; size: 1200 X 950mm, geo-fabric thickness 3.0mm, fill volume:0.1664 m3; Weight: 250 kg Nos 700,380.17 498.87 349,398,172.63
In Words:
Dumping of sand filled geo-bags from properly positioned and anchored flat top barge/pontoon over
an area specified by the bathemetric survey for uniform area coverage along the bank line up to the
designed length towards river, making a provisional falling apron at the river end of areal coverage,
recording the position of dumping barge by a total station etc. complete including loading, unloading,
sequential piling of geo-bags on the dumping edge of pontoon/ barge, carrying geo-bags from stack-
2 yard to dumping place by head load and power driven flat top country boat etc complete including
higher charge and mobilization of all equipment, materials, labours, taxes, incidental charges but
excluding cost of sand filled geo-bags as per technical specification, approved design, and direction of
engineer-in-charge.

Geo-bag; size: 1200 X 950mm, geo-fabric thickness 3.0mm, fill volume:0.1664 m3; Weight: 250 kg Nos 700,380.17 471.86 330,481,023.14
In Words:
Supplying and placing non-woven needle punched type geotextile fabric as filter materials of
elongation at maximum force machine direction (MD) 60%, and 100%, elongation and maximum
force (CMD) 40% and 100%, horizontal and vertical permeability (under 2 KN/m2 pressure) 2 X
10-3 m/sec, for effective erosion protection in hydraulic structures/ river training works including
local handling, placing in position, prodviding machine seamed joints (with 100% polypropeline or
3 nylon thread) or 35cm lap in dry condition or minimum 100cm lap under water including protecting
the geotextile material from UV ray and from any other damages including supply of all materials,
labours, equipments etc. complete as per direction of engineer-in charge. (Geotextile delivered at site
should be certified by ISO and clearly labelled with brand name and grade printed at regular intervals
across the body the fabric.)

Page 1 of 4
LONGJIAN ROAD & BRIDGE CO., LTD.
PAIRA BRIDGE CONSTRUCTION PROJECT

PROPOSED BILL OF QUANTITY OF RIVERBANK PROTECTION WORKS

SL. Unit Rate


Item Description Unit Quantity Amount (Tk) Remarks
No. (Tk)

Mass 400gm/m2, thickness (under 2 KPa pressure) 3.00mm, EoS0.08mm, strip tensile strength Rate as per Tender
m2 28,224.36 361.82 10,212,136.13
23 KN/m, grab strenth 1500N, CBR puncture resistance3800N. BOQ
In Words:
Supplying and Dumping of Imported hard rock (Pakur, mini, unit weight of 2948 kg/m3) at work site
including all modes of carriages, handling, loading, unloading and stacking in measurable stacks as
4 per specified size ranges including all taxes etc complete (deduction for voids will be made at the rate
mentioned against each size range for arriving at actual volume) as per direction of engineer in
charge.

a 30cm to 45cm size; m3 74,022.72 22,322.17 1,652,347,344.58


In Words:
b 45cm to 60cm size; m3 74,022.72 22,322.17 1,652,347,344.58
In Words:

Manufacturing and supplying CC Blocks in leanest mix 1:3:5.5 with cement , sand (FM1.5) and
stone chips (40mm downgraded) to attain a 28 days cylinder strength of 10.5N/mm2 including
5 grading, washing stone chips, mixing, laying in forms, consolidation, curing for at least 21 days,
including preparation of platform, shuttering and stacking in measurable stacks etc complete
including supply of all materials (steel shutter to be used) as per direction of engineer in charge.

Rate as per Tender


Block size 45 X 45 X 30 cm m3 6,795.78 20,125.00 136,765,102.69 BOQ
In Words:

Page 2 of 4
LONGJIAN ROAD & BRIDGE CO., LTD.
PAIRA BRIDGE CONSTRUCTION PROJECT

PROPOSED BILL OF QUANTITY OF RIVERBANK PROTECTION WORKS

SL. Unit Rate


Item Description Unit Quantity Amount (Tk) Remarks
No. (Tk)

Earthwork by carried (by truck/boat or any other means) supplied at contractor's own cost (including
royaltry) in constructing/ resectioning of the embankment/ canal bank/ road etc. by mechanical
excavator (long boom) compacted to 85%/ 90% maximum dry density at optimum moisture content
with reference to laboratory density test AASHTO modified hammer, with clayey soil (minimum 30%
clay, 0-40% silt and 0-30% sand) beyond initial lead of 300m including throwing the spoils to profiles
in layer not exceeding 230mm in thickness with clod breaking to maximum size of 100mm, benching
6 the side slopes, removing roots and stumps of trees of girth upto 200m, stripping/ploughing the base
of embankment and borrow pit area, dug bailing, clearing jungles, rough dressing including (150mm
cambering at the center of crest with all leads and lifts complete(compaction will be done by the
contractor with approved equipment including all ancillary charges for compaction and testing) as per
direction of engineer in charge

300m to 1km and embankment Height: 4 to 6m and above with 85% compaction m3 96,172.26 739.04 71,075,072.05
In Words:
Supplying and Laying of 100mm dry 1st class or pick jhama chips as per specific size, range and
7 gradation, including breaking chips, grading, preparation of surface, compacting each layer etc.
complete with supply of all materials and as per direction of engineer in charge
a Well graded between 40mm to 20mm size m3 1,104.37 6,407.57 7,076,318.76
In Words:
b Well graded between 20mm to 5mm size m3 1,104.37 6,407.57 7,076,318.76
In Words:
Supply and laying sand as filter layers as per specific size ranges and gradation including preparation
8 of surface, compacting in layer etc. complete with supply of all materials and as per direction of
engineer in charge

Page 3 of 4
LONGJIAN ROAD & BRIDGE CO., LTD.
PAIRA BRIDGE CONSTRUCTION PROJECT

PROPOSED BILL OF QUANTITY OF RIVERBANK PROTECTION WORKS

SL. Unit Rate


Item Description Unit Quantity Amount (Tk) Remarks
No. (Tk)

FM: 1.00 to 1.50 m3 2,208.74 1,905.74 4,209,285.05


In Words:
Rate as per Tender
9 Fine dressing and Turfing m3 14,279.39 241.21 3,444,330.46 BOQ
In Words:
Rate as per Tender
10 Surface soil removal (Clearing and Grubbing) as per specification and drawings etc. complete. m2 7,106.00 36.18 257,095.08 BOQ
In Words:
Rate as per Tender
11 Cutting (soil) as per specification and drawings etc. complete m3 37,340.94 241.21 9,007,006.93 BOQ
In Words:
Rate as per Tender
12 Side-slope forming (soil) as per specification and drawings etc. complete m2 34,186.49 168.85 5,772,388.84 BOQ
In Words:
Removing of old concrete blocks used for embankment protection along with upstream and /
downstreamand reuse the blocks as score protection for sheet pile along with river etc. complete. Rate as per Tender
13 m3 2,065.00 482.43 996,217.95
(Removed old cc blocks to be collected, stocked, measured, and carried dump behind sheet pile wall BOQ
on river side) all cast included labor & equipment etc.
In Words:
Pipe Dredging for as per Design and drawings etc. complete as drawing and specifications and as Rate as per Tender
14 m3 504,329.11 361.82 182,476,357.81
directed by the Engineer BOQ
In Words:
Pipe Banking for as per Design and drawings etc. complete as drawing and specifications and as Rate as per Tender
15 m3 504,329.11 141.48 71,352,482.18
directed by the Engineer BOQ
In Words:
Total= Tk. 4,494,293,997.60