Fifty-eight days ago a nervous Board of Directors of Igloo Foods, owners of the Igloo
Frozen Yogurt chain, watched as the company began a program to test market its product
in London, England. The target opening date for the first store was four months (122
days) from the inception of the project. If the store proves successful, Igloo plans to open
up at least two dozen Igloo Frozen Yogurt stores across Great Britain and the European
continent. This is the first such venture for Igloo Foods outside of the United States. The
project consists of 18 work packages summarized in Table 1 below, together with budget
information and time estimates.
A timetable based on the three time estimate approach was used to generate a schedule of
work packages for the project. Now, 58 days into the project, the Board of Directors has
received the following project status report summarized in Table 2 below.
Prepare a report for the Board of Directors of Igloo Foods which analyzes the progress of
the project from both a budget and time point of view. By using PERT analysis, compare
the initial probability of finishing the project in 122 days with the probability that the
project will now be finished by the end of day 122. Assume that the expected completion
time and standard deviation for each unfinished work package are reduced by an amount
proportional to the completion percentage of the work package (for example, if 75% of
an activity is completed, then the both the expected time to complete the activity and the
standard deviation are reduced by 75%). As an alternative method, calculate the
probabilities by creating an Excel simulation model. Compare the probabilities obtained
by using the PERT method and by conducting spreadsheet simulation.
Part 2
Igloo has planned a big gala "grand opening" for the morning of day 123 with visiting
dignitaries and a popular rock band. If the project is not completed in time (by the end of
day 122), the event will have to be canceled, and Igloo will suffer a $100,000 loss. Three
suggestions have been proposed for reducing the times of certain of the remaining work
packages:
Table 2