Professional Documents
Culture Documents
0212 Digging Deeper PDF
0212 Digging Deeper PDF
0212 Digging Deeper PDF
D I G G I N G
DEEPER
Eden Paki is the Drill & Blast Supt at Newcrest satisfy those requirements. In the process of Eden of course points out that there are always
Mining Limited’s Cadia Valley Operations near helping the Telfer team, Eden has offered site specifics which must be taken into account
Orange in NSW where the current open pit guidelines based on his experience and these in any mining determination, but AMC suggests
mining rate is around 80 Mtpa. Eden already are summarised below. They include formulae that Eden’s guidelines provide an excellent start
had substantial mining experience before moving which have been developed by others (apologies point. AMC has also found Eden’s guidelines
to Cadia, including 7 years D&B work for Roche in advance to authors of the formulae for not to be consistent with its discussions with drill
at KCGM’s Superpit in Kalgoorlie followed by being able to acknowledge them!!!) and these manufacturers and suppliers, blast hole drilling
working with Macmahon on D&B at the Mt formulae have gained good acceptance amongst contractors and drill bit suppliers.
Todd Gold Mine in the Northern Territory. open pit mining D&B practitioners. Eden asks
We thank Eden for his cooperation in agreeing
that the reader bear in mind that the guidelines
Despite his more than full time job at Cadia, to provide his guidelines to the broader mining
were put together for practical, operations
Eden has also been acting as a sounding board community through Digging Deeper.
based in-house assistance to his colleagues and,
for Newcrest’s Telfer Project Feas Study open
as such, do not pretend to be an exhaustive or
pit mining team in the areas of assessing D&B Continued page 2
scientifically rigorous treatment of the subject.
requirements for the project and how best to
1
PRACTICAL ADVICE WHERE IT’S CRUCIALLY NEEDED, AT “THE FACE”
Continued from page 1
EDEN’S RULES OF THUMB Blast Depth Blast depth can get you into
trouble, both through productivity issues and
There are a number of combinations that can
through the cost required to minimise the effects
be used for Burden to Spacing ratios etc,
on productivity. I have trialed various blast depths
especially when blasting in unfamiliar territory.
over time, trying various techniques such as
When I encounter this, it is usually prudent to
increased powder factors in the back rows, or
go back to basics and apply a few well accepted
altered burdens and spacings, adding delays to
principles or “rules of thumb”. You will generally
give a second front etc, however have had mixed
find that most “rules of thumb”, require either
success in my efforts. Essentially, the largest
the hole diameter or burden to calculate what
impact of blast depth is muckpile looseness.
other parameters will fit into the puzzle. The
As a base, I tend to favour the material size Higher powder factors can be introduced to
following are fairly common “rules of thumb”
required to allow for productive mining by the ensure that fragmentation is maintained in the
used throughout the industry when designing
selective loading tools – given that the hole back rows of the blast, however it is very difficult
blast patterns.
diameter determines the burden and spacing. to provide a free face that allows sufficient
Burden = 25 to 35 hole diameters. Until you can substantiate the mine to mill displacement to give productive dig rates.
process at the mine, then ultimately this should Blast patterns that are greater than 8 rows,
Spacing = 1.2 to 1.5 burdens (for large
not determine the drilling and blasting practices are generally tighter to dig on the back few
diameters e.g. Greater than 140mm) or around
(don’t pour money into the process until you rows. The lack of a free face in front, means that
1.5 to 1.8 for smaller diameters.
can quantify and accurately measure it). Ground the material is choked therefore becomes tighter
Stemming = 0.7 to 1.3 burdens. Keep in mind hardness can also affect the hole diameter to dig. Additional heave is also a result which,
that if you select a larger bench height, the selection process, but this can be addressed although providing some relief, is generally
stemming column could have an impact on the through powder factors. Critical diameter for confined to the upper reaches of the muckpile,
digger’s productivity, especially if you are looking explosives can also affect the hole diameter – and not the lower and middle sections where
at digging in flitches. For instance, if you were but as long as you are looking at larger than the shovel/excavator bucket spends most of its
to dig a 12m bench in three (3) flitches, then 76mm blast holes, then this shouldn’t be an issue. time. The higher face created from the choked
the loading tool would be digging through the rows also creates a hazard due to the higher face
Blast Size I always tend to look at going for
stemming column. This is the area where you height. Larger rocks, generally encountered in the
the largest achievable blast possible. This means
are more likely to encounter oversize, therefore stemming collar are now higher in the digging
a reduction in infill drilling, reduction in initiation
productivity would be much lower than the face, meaning that cooler packs on face shovels
costs, reduction in blasting frequency, which
other two (2) flitches. become prone to accident damage.
means a reduction in blast affected production
Bench Height 4= 0 to 50 hole diameters. delays. Altogether, a reduction in cost. When Choke Firing Related to the above, choke firing
Obviously this can usually change in accordance talking blast size, I refer to the overall volume of has its positives and its negatives. Choke firing
with the bench height requirements of the the blast. Vibration and timing (scheduling) and allows for minimal disruptions to the scheduling
loading tools. physical restrictions such as the time taken to process, as a digging unit does not need to free
Subdrill = 8 hole diameters. This can be load, tie-in and fire the blast play a more limiting face a blast and walk away. Instead, the digging
increased for the face rows to around 10 to factor on the size blasts that I elect to use. unit can continue digging through the area with
12 hole diameters. the choke shot being fired prior to the material
Blast Width I find this to be more important
in front running out. The negative of choke firing
Powder Factors Governed by budget, than overall blast size. I have a tendency to look
is muckpile displacement (which is actually a
mine to mill processes and, to a lesser extent, at maximising the blast width, while minimising
positive for grade control) and looseness –
ground hardness. the blast depth. Of course this is constrained
or lack of. Higher powder factors are generally
by the bench and mine plan, but where the real
Hole Diameters Essentially governed by the used also, to ensure that fragmentation is
estate is available to do so, I would elect to go
required average material size. There are many maintained, as due to the confinement of the
with 6–8 row shots that go on for as far as
different perceptions on what determines the blast, the energy tends to vent up and outwards.
possible. When looking at minimising the blast
hole diameter, but I personally select a hole This can mean poor fragmentation, especially at
depth, I refer to minimising to around 6 rows in
diameter based on the size of the loading the toe. Maximising free faces is always the best
depth – not fewer. This provides excellent
equipment, and any other material constraints option (productivity wise) however, choke firing
displacement (if that is the desired result),
placed upon me by the milling process (finer can be a necessary evil – especially in a gold
delivering excellent muckpile looseness.
material means higher throughput). You must mining environment.
Fragmentation is also maintained which means
find the middle ground between the two –
that productivity is maximised.
at which point the higher cost of increased
powder factors, or drill & blast costs outweigh
the savings received from the milling process.
2
Explosives Density As a general rule, the become a rare event, as opposed to a hazard compressive strength of the rock being drilled.
harder the rock, the higher the explosives density. that is dealt with on a regular basis. A basic formula to determine the pulldown
You require more shock energy in harder ground. requirements of drilling with rotary is as follows:
Stemming Size If you are looking at increasing
For rock with a density of around 2.6 to 2.8, I
the blast hole diameter, I would recommend the P = (D x C) / 5
would look at using an explosive with a density of
use of crushed rock for stemming. A “rule of
1.2 to 1.3. Further, as I am going to a high density Where P = Required Pulldown, D = Hole
thumb” is that stemming size should be between
explosive, I would look to maximising the usage Diameter in inches and C = The rock uniaxial
10% and 15% of the hole diameter. Drill cuttings
of heavy ANFO based explosives as opposed compressive strength in PSI.
used in holes greater than 127mm tend to eject,
to pumped product, as the heave properties of For example, if you were drilling a 251mm hole
giving minimal confinement. The better
the augered product allows for better muckpile in rock with a UCS of 260 MPa, the following
confinement offered by the crushed rock also
looseness. would apply:
gives you the opportunity to reduce the
Number of blasts per blast day Determined stemming column, thus improving the overall 251mm = 97/8”; 260 MPa = 37,710 PSI
by labour. I would recommend blasting no more fragmentation.
than once per day, with no more that two (2) to P = (97/8 x 37,710) / 5
The table below is an example of the above rules
three (3) shots at a time. Any more and you start P = 74,530 lbs
of thumb applied to an example set of project
to have problems relating to preparing the blast
parameters. Using this number to assist you in drill selection
on the day (tie-ing in the shot), clearing the pit
You will note that my Burden to Spacing ratio is should go a long way to ensure that you have the
for blasting, firing the shots and clearing the blasts
on the low side – I have actually found that right drill combination to suit the application.
after firing. These can be very time consuming
equilateral patterns give a great result (Burden = Imperative in this is selecting a drill that will
and could result in a delay for blasting taking up
0.867 of Spacing) however, they do cost a little achieve your desired targets comfortably, unlike
to an hour. I would not recommend planning to
more in the long run. Please also note that I have the mistake made at one project where the drill
tie in the blast the day before, purely for safety
elected some fairly simple pattern sizes. Where selection was aimed around maximising the
reasons (also increases the risk of misfire through
possible, I would suggest that you err away from output of the drill through minimising the cost of
human interaction or natural events such as wind
using dimensions such as 4.1 or 5.9. What tends the initial purchase. Drill manufacturers will state
and storm).
to happen is that operations will look for a that their units are capable of drill hole diameters
Number of blasts per week Once again ranging from 165mm to 270mm however, they
simpler dimension working in half metre
I would look to minimise this. I try to schedule are not recommended to be run under load for
increments rather than 0.1 decimals.
blasting to a maximum of 3 times per week. extended periods of time. In order to achieve the
Any more and you start feeling the effects of Pulldown is another factor that you must 270mm, the engine, pumps and rotary head will
delays to production caused by blasting, plus the consider when selecting a hole diameter. This is be under maximum load. The unit is capable of
strain starts to tell on the blast crew through especially important when drilling rotary (note achieving this, however you will find that over
the frequency of tasks such as tie-ing in a shot. that an 8” hammer is the largest commercial time, in order to sustain this diameter, you are in
This means that mistakes tend to creep in, plus hammer on the market today – other larger fact drastically reducing the life of the drill and its
complacency becomes apparent. It is preferable hammers are generally made for specialist components. Further, you may find that a drill’s
to dedicate whole days to purely charging and purposes other than production blasthole performance is reduced when operating for long
stemming operations, which also gives the blast drilling). The pulldown requirement is usually periods at the upper ranges of the drill’s
crew adequate relief between each shot. Misfires governed by the hole diameter, and the capabilities. I cannot provide operating data to
evidence this view, however it is a qualitative
observation made from experience.
Parameter 187 mm Diameter 251 mm Diameter
The last thing to consider when looking at hole
Pattern Burden x Spacing 5.5 x 6.5 6 x 7.5 7.5 x 9 9 x 10.5
diameters, is the size of the drill pipe associated
Explosive Density (g/cc) 1.2 1.1 1.2 1.2 with that hole diameter. Drill pipe affects your
Hole Diameter (mm) 187 187 251 251 uphole velocity (also bailing or annular velocity)
Burden (m) 5.4 6.0 7.5 9.0 which, in turn affects the performance of the
drilling consumables and the wear characteristics
Spacing (m) 6.5 7.5 9.0 10.5
of your drill string. A higher uphole velocity,
Burden/Spacing Ratio 1.20 1.25 1.20 1.17
created by a smaller annulus will drastically
Bench Height (m) 12.0 12.0 12.0 12.0 increase the wear on your hammers, subs and
Subdrill Length (m) 1.5 1.5 2.0 2.0 drill rods, however a lower uphole velocity
Stemming Length (m) 4.5 4.5 4.5 4.5 may mean that you’re not sufficiently lifting
the drill cuttings out of the blast hole.
Stemming/Diameter Ratio 24.1 24.1 17.9 17.9
Powder Factor (kg/bcm) 0.70 0.50 0.70 0.50
Explosive Mass (kg per hole) 297 272 564 564
3
short. The cause is claimed to be outside
I have worked on 7000 to 8000 feet per minute management’s control, because there is a general
for fresh rock, going for the upper limits if that shortage of experienced professionals and they
material is also wet and down around 5000 feet are highly mobile. New vacancies arise as quickly
per minute for softer materials. A formula for as positions are filled.
calculating uphole is as follows:
This phenomenon, in my opinion, compromises
V = (Q x 183.33) / (D2 - d2)
MESSAGE FROM the safe and effective working of the mine.
Production variability rises due to a lack of
Where V = bailing velocity, Q = compressor
output in CFM, D = Hole Diameter in inches and THE MANAGING planning and process control, leading to a loss
d in drill pipe diameter in inches. DIRECTOR of profitability and to accidents. Both of these
outcomes should be unacceptable to
For example, if you are selecting a drill with a
Redundancy management and to boards of directors.
compressor output of 1150cfm, drilling a 251mm
hole with 8 1/2” drill pipe, the bailing velocity Redundancy is essential in engineering and The solution is simple. Build some redundancy
would be: systems design. It is why a jumbo jet can lose an into the management chart. If the “bare bones”
entire electrical circuit and continue flying. It is management chart requires 15 technical people,
251mm = 97/8”
why your car brakes are still effective after losing make it your aim to employ 20. With the chronic
V = (1150 x 183.33) / (97/82 - 81/22) a brake circuit. shortage still applying, you may sustain 15. The
same principle applies for operators. And guess
V = 8,345 ft/min When we prepare a feasibility study for a
what? Safety and profitability will improve, despite
You can go to a smaller hole diameter to achieve new mine we specify a range of management,
the higher employee cost.
the same result, however you must ensure that technical and operating positions in an
organisation chart. Traditionally, the redundancy I have been an expert witness in more than
you have sufficient air capacity on the drill to
allowance (sickness, leave and absenteeism) thirty underground mine accident cases and
achieve an optimal bailing velocity, e.g. 1,450cfm.
was around 12% of the complement. This didn’t I believe that the cultural causes of accidents are
Last but not least, when considering varying hole really allow for replacement of specialists, who hard to quantify. However, it is easy to prove,
diameters, consideration must be taken as to the were required to arrange their work so that they using employee records, that a mine was under-
difference between the hole diameter and drill could take annual leave. We assumed that if staffed. I think that the causal link between
pipe combinations available. The 81/2” drill pipe unusual circumstances led to higher absences, under-staffing and safety could be demonstrated.
used in the example above for the 251mm hole, additional appointments would be made to Some operations are adequately staffed and
is too large to drill a 187mm hole. Therefore, in provide the necessary redundancy. can demonstrate this. If your operation is not,
order to use this configuration you would need
Most mines today operate on an organisation then I think that you are exposed. As a director
to change your drill string every time you wish to
chart that is pared to the bone. It shows just or manager you might turn your thoughts to
change hole diameters. This requires labour,
enough people, if they were all available, to run redundancy.
cranes and, most important of all, time. The
optimal drill pipe size required to drill a 187mm the mine safely and efficiently. But most mines Merry Christmas.
hole, will be too small to effectively run the don’t have those people available.
251mm rotary bits at the end of the day – this is It has become common for a mine having a
due to bailing velocity plus flex on the rods. technical and management complement of,
say, 15 to run chronically three or four positions Peter McCarthy
Figure 1: Production Relative to Peak Monthly Production – 25 Underground Figure 2: Ratio of Actual to Planned Tonnage – 25 Underground Mines 2000–2002
Mines 2000–2002
Australian Mining Consultants Pty Ltd ABN 58 008 129 164 Website: http://www.ausmin.com.au
MELBOURNE PERTH BRISBANE UNITED KINGDOM
Level 19 Ground level Level 8 Hampton Business Centre
114 William Street 9 Havelock Street 135 Wickham Terrace 7 Mount Mews, Hampton-on-Thames
Melbourne 3000 West Perth 6005 Brisbane 4000 Middlesex, TW12 2SH, UK
Telephone +61 3 9670 8455 Telephone +61 8 9481 6611 Telephone +61 7 3839 0099 Telephone +44 20 8213 5881
Facsimile +61 3 9670 8311 Facsimile +61 8 9481 6622 Facsimile +61 7 3839 0077 Facsimile +44 20 8979 2187
amcmelb@ausmin.com.au amcperth@ausmin.com.au amcbris@ausmin.com.au amclondon@dial.pipex.com