Professional Documents
Culture Documents
Kang'Ombe C.N. Design Final Report 2017
Kang'Ombe C.N. Design Final Report 2017
YEAR 27/11/2017
i
DECLARATION
is involved, every effort has been made to indicate this clearly with due reference to
literature.
The work was done under the guidance of Dr. A. Ogunmokun at the University of Namibia,
Faculty of Engineering and Information Technology, Jose Eduardo dos Santos Campus,
Ongwediva.
In capacity as the supervisor of the candidate’s design project, I certify that the above
ii
ACKNOWLEDGEMENTS
Firstly, I like to thank Lord Almighty for his mercy, guidance, and for giving me the
consistent drive to persist in making this project possible. I thank my family for the support to
carry out the project and the provision of funds where it was needed the most. I would like to
express my appreciation to my friends for motivating me to go ahead with this project even at
times when it seemed impossible to complete till the end because the innovation also served
as an inspiration to them.
providing the necessary information and literature and emphasizing on the critical aspects of
the design that were looked at. I thank Mr. Ndapuka of the electrical department for the
guidance on the sizing of the electrical components of the PV system. I thank Mr. Shikomba
for the much needed access to the machining laboratory at UNAM JEDS Campus and making
provisions of tools and machines where necessary. I would like to thank the University of
Namibia for the opportunity to apply my knowledge I acquired throughout my 4-year course
in this project wherever I was required to do so. Finally, if there are any people I have left out
who was a part of my success along the way in completing this project, I thank them too.
iii
SUMMARY
There is a need of a water purification design that enhances the technology used in water
treatment in many parts of Namibia especially in the rural and remote areas. This design can
contribute greatly to the health standards of the people who are occupants of these areas with
no electricity supply making most water purification systems unsuitable for these areas. A
proposed design is a UV-C Solar Water Purification System. It is designed for the elimination
This report is articulated to demonstrate the capability of off the grid water treatment by
harnessing of Namibia’s abundant solar energy to make this system fully operate
independently from a mains supply. It shows the design alternatives that were considered and
selected and the calculation of retention time and the common length of beams to keep the
system stable.
A prototype was fabricated with improvised materials and a final CAD drawing was
delivered. Despite an incomplete fabrication of the system, tests were able to be carried out to
observe the performance of the physical components successfully put. Faults that were
iv
TABLE OF CONTENTS
DECLARATION...................................................................................................................... ii
ACKNOWLEDEMENTS.......................................................................................................iii
SUMMARY ............................................................................................................................. iv
1. INTRODUCTION.............................................................................................................. 1
3. OBJECTIVES .................................................................................................................... 3
4. REQUIREMENTS ............................................................................................................. 3
6. DESIGN APPROACH....................................................................................................... 6
v
6.6 Tests and Results................................................................................................................ 30
7. DELIVERABLES ............................................................................................................ 35
9. CONCLUSION ................................................................................................................ 37
10. RECOMMENDATIONS................................................................................................. 38
REFERENCES ....................................................................................................................... 39
APPENDICES ........................................................................................................................ 43
vi
LIST OF FIGURES
Figure 6.1: Design concepts with hand pumps(L) and without hand pumps (R)
Figure 6.13: Graph representation of UV Output vs. Exposure Time Figure 6.14: close-up of
vii
Figure 6.18: System beam structure
LIST OF TABLES
Table 6.1: Data representation of the three velocities at different water levels.
Table 6.2: A computation of the time taken for values of V0 and their correspondents
viii
ABBREVIATIONS
ix
1.0 INTRODUCTION
Water is life. It is therefore essential for water to be safe and readily available for human
consumption in achieving the benefits of human health [1]. Improvement of water supply and
Despite these facts, many in the world (an estimated 1.8 billion people [1] living mostly in
rural areas as of November 2016) have access to contaminated water which has serious health
hazard and rural area settlers living close to rivers and lakes and other water sources are the
biggest victims in this concern. Organisations such as the World Health Organisation (WHO)
and United Nations International Children’s Emergency Fund (UNICEF) are working hand in
In 2012, WHO estimated 6.3% of all deaths caused by limited access to safe drinking water
[2]. Diseases such as intestinal worms, lymphatic filariasis, trachoma, typhoid, diarrhoea and
some waterborne diseases are in relation to these deaths and children are especially
susceptible to unsafe water and poor sanitation [2]. In a country like Namibia, “diarrhoea and
other infections like worms, due to lack of safe drinking water and proper sanitation, accounts
for about half of ill-health and under-nutrition in children” as stated by De Sousa [3]. An
estimated 19.6% of people living in the rural areas of Namibia do not have access to potable
(drinkable) water with the rest living on safe water [4]. Most of these people do have access
to water from waterbodies such as rivers, lakes and streams but the water may have
contaminants which open doors to diseases [2]. As far as this is concerned, a method used to
turn dirty water to clean water is needed to contribute on improving these people’s standards
of living. Everyone, including the likes of these people, also have the right to sufficient, safe,
and affordable water for personal and domestic use hence the dissatisfaction with the current
1
It is therefore needed to work on a project that would contribute in the overcoming the
challenge of lack of water pre-treatment and purification to make it drinkable for the
objective of Namibia’s vision of 2030 [4] which is to “achieve equitable access to potable
water and freshwater resources by all. [5]” This project will enhance the vision by designing
and building a system which should therefore be easily available and affordable on a small
scale with requirements specified by the client, the Ministry of Agriculture, Water and
Forestry.
The Ministry of Agriculture, Water and Forestry (client) wants an effective system that can
eliminate pathogens in the water to make it drinkable without any chemical additions or
There are several methods of achieving this. However, some of these methods will not be
able to achieve all of them like those with chemical addition. Henceforth, an Ultra Violet
(UV) system looks to be the ideal type of a water purification system. It includes a UV-C
bulb, with an optimum wavelength of 254nm, that can eliminate 99.9% of micro-organisms
in the water [7] and can operate on solar energy. However, UV light can only work on clear
With Namibian remote areas currently facing challenges with having sources of electricity
and considering that they are not connected to the grid, there is need for a solar water
purification system in these remote areas. UV water purification systems have not been
implemented in these rural and remote parts. However, it is preferable to use UV-C systems
over other systems because of its advantages of completing the purification process without
2
3.0 OBJECTIVE
The objective of this project was to design a water purification system for rural and remote
areas in Namibia that will utilise solar energy as a renewable energy source and operate with
UV-C light.
4.0 REQUIREMENTS
By the end of the project, the system output should definitely be drinkable clean water. The
The pre-filter of the system should be able to reduce the contents of solid particle
It should be able to deactivate harmful pathogens using the UV-C light system.
Even without the following requirements, the system is able to function. However, their
consideration is of significance:
3
5.0 LITERATURE REVIEW
Deshmukh [8] constructed a portable UV-solar water purifier which makes use of filtration
and distillation processes. Water goes through three filters namely: pre-filter, sediment filter
and activated carbon filter where solid particles are removed. It includes a UV-bulb which
carries out the process of destroying parasites and micro-organisms. Its battery is solar
charged and can also be charged from the mains supply on days with low sunlight. This
system, however, has many filters that cannot easily be maintainable in Namibian remote
areas. Also, since sunlight is available in most parts of the country all year round, a mains
supply may not be necessary for these areas but a solar PV system is sufficing to charge the
battery in daylight.
Wilson [7] designed and constructed a Solar Water Purification System with Ultraviolet
Radiation. The water is pumped from a settling tank up a pipe system into the UV-tank via a
hand pump and then into a storage tank where water for drinking can be collected. A UV-C
bulb is used to kill pathogens and other organic material in the water. It was concluded that
UV-C light systems is more effective than systems that use UV-A light (from sunlight for
example) in killing pathogens to obtain suitable drinking water. This project, however, has
challenges to the requirements of this proposal. Firstly, Wilson’s prototype had a high initial
cost due to his huge number of material requirements. Secondly, UV treatment always
requires a pre-filter in order to reduce its turbidity hence making the water appear clearer [6].
Therefore, having a settling tank cannot be an optimum way of eliminating solid impurities.
Shull [9] designed a portable low power water purification system used by workers in
underdeveloped world regions. This design consisted of an activated carbon filtration, candle
filtration of 0.2 microns for bacteria and UV-filtration. This system was powered by an
4
electric generator to power up the UV lamp and the pump which boosts the flow of water.
This system may yield an improvement in hygiene for the people in the rural communities
but unfortunately, the carbon filter is never readily available in rural areas and would have to
Martin, Oberg and Yoder [10] produced a water filtration and purification system and their
aim was to make it marketable for a SUV or RV. They improved on a previous system that
was incomplete hence not marketed. They improved on the cost, bulkiness and weight of the
system and incorporating a DC battery and a micro controller to control the UV exposure
level. The system could easily be dissembled and packed in a casing. However, when the
system was designed, no safety factor was considered in order for surety of complete
deactivation of pathogens. It also consists of a sediment filter and a carbon filter which are
not easily maintainable in the rural areas but ok for the system because it was designated for
urban standards.
specifications of the NSF 55 standard [11]. The system is designed to give a dosage of 80
𝑚𝑊 · 𝑠/𝑐𝑚2 following a safety factor of 2 under the NSF 55 standard [11]. As for the pre-
filter, it has to filter the particles to the required turbidity for UV-filtration which is 5 NTU
[11]. In addition, the initial idea was to design a system that can supply a family of four in a
remote area on a daily basis. The average water consumption in Africa is 5litres per person
5
6.0 DESIGN APPROACH
Different design concepts were considered to suit the client’s needs. These concepts were
The first concepts considered were to do with hand pumps. One that would function with
hand pumps such as that of Wilson [7] where hand pumps were involved in the design and
the other without hand pumps where the waterflow occurs via gravity. However, despite
having a cost-benefit and being able to compete with the functionality of the mechanical
pump, implementing it in this project would be costly considering purchasing different pipe
fitting to suit the size of the piping. The figures below show the initial idea on how the system
Filtration
tank
Solar Panel
Solar Panel
Filtrate
tank
Waterflow pipeline
Filtration UV
tank tank
UV
P-10 P-11 tank
Waterflow pipeline
Figure 6.1: Design concepts with hand pumps(L) and without hand pumps (R)
With these alternatives considered, it was then decided that a system without hand pumps is
going to be designed due to lack of local availability and expense. Having a system without
hand pumps will make the system less complicated hence also take advantage of gravity
The figure below shows the way the final concept appears considering compactness and less
complex. The ball valves are meant to restrict flow within the system.
6
Filter
Tank
Filtrate
Inverter Tank
Ball valve 1 UV
Tank
Ball valve 2
Storage
Battery Tank
Controller
This system concept was initially designated to sufficiently supply an African family of four
daily with potable water. It was meant to be on four wheels for easy movement. However, the
cost to build this system was higher than expected. People who are financially well to do can
afford this type of system and make use of it when travelling to a place where there is no
surety of the water being clean there. As for the people living in rural areas it does not favour
the economics of scale for the people living in these rural and remote areas and therefore,
they cannot afford to buy this kind of system. The client then suggested that it is therefore
economical to have one system designed in this way for the whole community (say a
An addition to this design is a storage tank for the contaminated water and another one for
potable water already treated. The whole purification system would consist of three pumps.
One to take the contaminated water up to fill a storage tank from its source, another one to
pump potable water to the other storage tank and a third to boost the water up the potable
water tank. The figure below shows a general concept of the way the whole purification
system would look like for a community. The size of the two tanks are determined by how
many people live in the commmunity. Instead of tanks used for the filtration and UV-phase,
three 25 litre buckets were improvised for the prototype. Contaminated water tank would be
7
linked with the pre-filtration phase and the UV-filtration bucket linked to the potable water
NB: This project only dealt with the purification section which was necessary to fulfil the
There were three different types of pre-filters considered in designing the system. Pre-
i) Sand Filtration
Slow sand filters (Figure 6.4), which are popular in developing and developed countries [13]
will be a part of this system. However, sand filtering is not independently a safe method of
water treatment because pathogens are not deactivated [14] hence can work well with UV
treatment.
8
Figure 6.4: Sand filtration [15]
This is a famous water filtration process which is practiced in countries like Bangladesh and
is currently used for treating contaminated water from lakes and rivers [16]. Studies have
shown that it is also well known for its turbidity reduction and capability of eliminating 99%
of cholera parasites found in the water. Sari Cloths would only require washing to be kept
clean although it is not effective in removing organisms [16] that can be removed using UV-
C filtration.
9
iii) Sieve Filtration
This type of water treatment method involves the use of sieves which consist of a porous
medium that remove small flocs or precipitant particles [18]. This filtration methods can as
well be used in some wastewater applications and serves as a primary turbidity reduction
process.
Ceramic water filters are known as a “point of use” treatment system used globally [19].
These filters work by using porous materials allowing water to flow through while restricting
the passage of potentially harmful microbes. 20 Modern filters are made by mixing clay with
sawdust, rice husks, or other flammable organic materials [20]. The pores are large enough to
allow the passage of water but not the microbes that cause water-borne disease. However,
10
Figure 6.7: Ceramic Filter [21]
All these methods of filtration cannot work independently to filter the water to a point where
availability (how easily accessible they are) and maintainability. Sand filtration requires a
special type of sand for its process which is not available in abundance. Sieve filtration is
very effective hence make a very good option but because of its expense on the market, it was
eliminated from being chosen and same goes for ceramic filters which were not found
locally. It was therefore the choice to go with a sari-cloth filter because it was readily
available and also the time constraint to complete the project was another reason for its
selection.
6.3 Constraints
The constraints to consider when selecting the type of system were cost effectiveness,
In this project, there are major engineering criteria that were applied from the designing to the
drawing and then to the building of the system. Fluid Mechanics was used to determine the
11
discharge time of the water from the filtration phase. Computer Aided and Engineering
Manufacturing will be applied in drawing the system and the fabrication of the framework
and other Machine Tools applications such as welding, bolt fastening, drilling and material
cutting were considered when fabricating the prototype. From the knowledge of Project
Management, time and cost estimates for the project were formulated. Application of statics
6.5 Procedure
6.5.1 Acquisitions
Quotations were taken from Benz, Build-it and Namibian solar solutions in order for the
prices of certain parts of the system to be taken note. Some items were found in more than
one shop hence the prices were compared. Quotations under the name of UNAM were
submitted to Mr. Shikomba who then processed the orders. All items received are shown in
The UV-C Lamp (25W Ultraviolet disinfection lamp) was looked up online [22] and was
ordered. The following are its specifications: Quartz Glass material, 20-30 square meters
suitable space, output power of 20W, Voltage of 220V, 50 Hz, E27 Lamp Holder type and
The framework of the prototype was made using the workshop materials at UNAM JEDS
6.5.2 Calculations
This part of the project determines critical aspect parameters that gives an expectation on how
the system is going to function. It is essential to find the retention time [23] in the whole
purification process.
12
i) For Water Discharge Time from the filtration phase
The figure below shows the filtration tank which is designated for filtered
water.
0.305 m
0.36 m
}
Datum
0.36 m
Figure 6.8: Filtration Bucket
The aim of this section was to determine the discharge time of the water in the filtration
bucket (the time it would take for the water to completely discharge). This is, as part of the
retention time significant. The system was designed in a way that gravity is the force that
takes down the water through the whole purification process. The first step always considered
in such an analysis is to derive everything from the Bernoulli equation (1) [24] between the
𝑃0 𝑉2 𝑃 𝑉2
0
+ 2𝑔 + 𝑍0 = 𝜌𝑔1 + 2𝑔
1
+ 𝑍1 (1)
𝜌𝑔
In Equation 1, 𝑃0 , 𝑉0, 𝑍0 are respectively the pressure, velocity and water level height of the
surface above the datum line. The correspondents on the other side of the equation are that of
the velocity of the water at the exit of the tank. 𝜌 is the density of the water and 𝑔 is
equation 2.
13
𝑉02 1 𝑉2
+ 𝑍0 = 2𝑔 (2)
2𝑔
The amount of water exiting is equal to the amount of water entering the pipeline. This is
𝑄0 = 𝑄1
Therefore,
𝐴0 𝑉0 = 𝐴1 𝑉1
𝐴
𝑉1 = 𝐴0 𝑉0 (3)
1
where 𝐴0 and 𝐴1 are the surface areas of the water in the tank and at the exit respectively.
The ratio of the two areas was converted to a square diameter ratio as shown:
𝜋𝑑02⁄
𝐴0 4 𝑑2
= 𝜋𝑑12⁄
= 𝑑02
𝐴1 1
4
𝑑2
Let 𝑑02 = 𝑘. Therefore,
1
𝑉1 = 𝑘𝑉0 (4)
𝑉02 (𝑘𝑉0 )2
+ 𝑍0 = (5)
2𝑔 2𝑔
2𝑔𝑍
𝑉02 = (𝑘−1)
0
14
Hence
0 2𝑔𝑍
𝑉0 = √(𝑘−1) (6)
The Bernoulli equation was then used between the bucket exit and the pipe exit as shown
2 𝐿 𝑉2
below. A hydraulic loss due to friction in the pipe (ƒ 𝐷 2𝑔 ) was considered because as water
flows inside the pipeline, the velocity decreases due to a pressure drop and friction.
Where 𝑉2 is the velocity of the flow at the pipe exit ƒ is the friction factor for the PPR pipe
(which is 0.009 [25]) used in the design, D is the pipe diameter, L is the length of the PPR
linkage (assuming the whole length is just piping) shown in figure 6.7. Assuming the pipe not
𝑉12 1
𝑉2 = √ 𝐿 = 𝑉1 (7)
(1+ƒ ) 𝐿
𝐷 √(1+ƒ )
𝐷
𝑘
𝑉2 = 𝑉0 (8)
𝐿
√(1+ƒ )
𝐷
The following shows iterations that where computed in Microsoft Excel using the above
velocity equations with different heights of the water level. The values of the different
15
Friction factor 0.009
Diameter of pipe (m) 0.015
Diameter of bucket (m) 0.305
Pipe Length (m) 0.36
Gravity Accel. (𝒎/𝒔𝟐 ) 9.81
16
k 413.44
A graph was plotted as shown below to see how the three velocities are changing with respect
to the water level as it goes to zero. As observed, the plots of 𝑉1 and 𝑉2, which are the two
velocities at the ends of the pipeline, have the same shape hence their rates of change are very
much comparable whereas 𝑉0 at any time, t is always close to zero. Comparing any two of the
three velocities, it would be found that their decelerations occur at a constant ratio at any
17
Discharge velocities vs. Water level
velocity in tank (v0) velocity at tank exit (v1) velocity at pipe exit (v2)
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35
To find the time of complete discharge, equation (6) had to be differentiated w.r.t. time as
shown below:
𝑑 𝑑 2𝑔𝑍
(𝑉02 ) = 𝑑𝑡 ( 𝑘−10 )
𝑑𝑡
𝑑𝑉0 2𝑔 𝑑𝑍0
2𝑉0 = 𝑘 2 −1
𝑑𝑡 𝑑𝑡
𝑑𝑍0
Taking note that = 𝑉0,
𝑑𝑡
𝑑𝑉0 𝑔
2𝑉0 = 2𝑉0 𝑘 2 −1
𝑑𝑡
The equation was then simplified as shown below and written w.r.t. 𝑉0.
𝑔
𝑉0 = 𝑘 2 −1 ∫ 𝑑𝑡
−𝑔
𝑉0 = 𝑘 2 −1 𝑡 + 𝐶
18
−𝑔
𝑉0 = 𝑘 2 −1 𝑡 + 0.00643 (9)
−𝑔
𝑉1 = 𝑘(𝑘 2 −1 𝑡 + 0.00643) (10)
𝑘 −𝑔
𝑉2 = 𝐿
(𝑘 2 −1 𝑡 + 0.00643) (11)
√(1+ƒ )
𝐷
Equation (9) was used to determine the times at the velocity values shown in table 6.2.
𝑉0 −0.00643
𝑡= (𝑘 2 − 1) (12)
−𝑔
Table 6.3 shows an addition of the time column to Table 6.2. Using equation (12), the times
The following graph was plotted to show how the three velocities are changing with time
19
Discharge velocities vs. Time
v0 vs. time v1 vs. time v2 vs. time
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
in a real circumstance since conditions such as the pressure inside the pipe was neglected.
The calculations for the exposure time was dependant on the furthest distance, r the UV was
emitted in the UV bucket. The required volume of the UV tank technically was supposed to
be 20 litres. However, a UV bucket having a volume of 25 litres (0.25𝑚3 ) was what was
available and actually more than suffice to purify water for an African family of four daily.
The figure below shows the UV Lamp that was ordered from Aliexpress.com with its
dimensions. This type of lamp is what is known as a medium pressure lamp which has an
20
Figure 6.11: UV Lamp [22]
The figure below shows the lamp inside the bucket. The buckets are slightly tapered but for
calculation purposes, they are assumed uniformly cylindrical. The furthest distance (denoted
lamp is required to deactivate the furthest particle at the required dosage of 80 𝑚𝑊 · 𝑠/𝑐𝑚2 .
19 cm
41 cm
25.94 cm 22 cm
13.75 cm
Figure 6.12: UV Bucket with
lamp
The amount of time (in seconds) taken to achieve the required dosage is determined from the
following equation.
𝑃𝐿
Where the irradiation, 𝐼 (𝑟) = 2𝜋𝑟 𝑒 −𝑎𝑒𝑟 and t = time. Hence (3) can be written as follows
21
𝑃𝐿
𝐷𝑜𝑠𝑒 = 𝑒 −𝑎𝑒𝑟 · 𝑡 (3)
2𝜋𝑟
Where PL = UV power emission per arc length of the lamp in 𝑚𝑊/𝑐𝑚, r = irradiation radius
and ae = base absorption coefficient of water (0.001/cm). The equation was then rearranged
as follows
2𝜋𝑟 𝐷𝑜𝑠𝑒
𝑃𝐿 = · (4)
𝑒 −𝑎𝑒𝑟 𝑡
The type of UV lamp has an input of 20 W (20 000mW). With an efficiency of 40% [26], the
output of the lamp is actually 8 W. The following shows iterations that where computed in
Microsoft Excel. Equation (4) was used to calculate PL values and the UV output was found
by multiplying the PL values with the arc length of the lamp as shown below.
2𝜋𝑟 𝐷𝑜𝑠𝑒
𝑃𝐿 = · · 𝐿 (5)
𝑒 −𝑎𝑒𝑟 𝑡
The power output at the time that should be used in one treatment process time must have the
highest value that is below 8W in order for the system to deliver a dosage close to 80
𝑚𝑊 · 𝑠/𝑐𝑚2 which is the first highlighted row in the table below. After the iterations were
computed, a computation in the second highlighted row was done to iterate precisely the
r (cm) = 25.94
ae(1/cm) = 0.01
𝟐
Dose (𝒎𝑾 · 𝒔/𝒄𝒎 ) = 80.00
Length of UV Lamp (cm) = 19.00
22
Table 6.3: Representation of different UV outputs and PL at
different time intervals
UV output = 8W = 8000 mW
Minimum time = 41s
Therefore, the actual dosage that is going to be supplied to the water was found using
equation (3):
8 000/19 −0.01𝑥25.94
𝐷𝑜𝑠𝑒 = 𝑒 · 41 = 81.72 𝑚𝑊 · 𝑠/𝑐𝑚2
2𝜋(19)
The data from the iterations above were plotted as shown on the graph below. For lamps with
a smaller power output, the duration of water UV treatment in which the dosage above is
supplied is longer.
23
UV Output vs. Exposure Time
UV Output (W)
16.00
14.00
12.00
6.00
4.00
2.00
0.00
0 20 40 60 80 100 120 140 160 180 200
Time (s)
The UV exposure time and Discharge time added together gives the system retention time at
which the water is purified. In the filtration phase, the water would take about 112 seconds to
completely discharge while in the UV phase, it would take 41 seconds to deactivate 99.9% of
all the water pathogens. The aggregate value therefore gives the retention time of 153
requirement of compactness of the client. This linkage consists of plumbing components such
as couplers, bushings, stop tap and an elbow which are all made from PPR material. The
figure below shows a close-up view of the system concept as well as just part of its
framework.
24
Constraint beams
Main beams
UV Bucket
Axis P
The structure on the right was analysed for acting moments. The figure below shows the
point of possible tipping assuming the bucket has 25litres of water (25kg of water hence
245.45 N of water) as well as the forces acting on the system causing moment about an axis
P.
0.17 m
𝑊𝑐
𝑊𝑏
𝑥/2 P
2𝑊𝐿𝑏
2𝑊ℎ𝑏
5𝑊ℎ𝑏 Point of possible tipping
The aim of this calculation was to determine the length of the main beams that form up the
general structure of the framework in order to assure no tipping at axis P when the bucket is
full. Other components of significant weight were added later on to form up the complete
25
system which gives the assurance that no tipping would occur. The following assumptions
The weight of the UV bucket and of the UV lamp is negligible therefore not part of the
analysis.
The bucket was assumed full of water with a weight of 245.45 N acting at the distance
The pre-filter platform definitely has a bigger moment value than that of the UV-filter
(due to the longer distance from the tipping axis) hence were both neglected.
With the application of statics, the sum of moments about a point or axis should equate to
zero for system stability (∑ 𝑀𝑃 = 0) [27]. As illustrated in the figure above, 𝑊𝑏 is the weight
of the water acting at the centre of the bucket, 𝑊𝑐 is the weight of the constraint beams, 𝑊𝐿𝑏 is the
force acting on each of the L-shaped cross-sectional beams of the main structure and 𝑊ℎ𝑏 is
the force acting on each of the hollow cross-sectional beams. Distance, x is the length of the
beams to be determined. Equation (1) below defined the mass of the beams in terms of x.
𝑚 = 𝜌𝑉 = 𝜌𝐴𝑥 (1)
Where m=mass, 𝜌=density and A=cross-sectional area. Mass was expressed in equation (2)
as in equation (1) modifying the equation of weight in terms of mass, W=mg [27],
𝑊 = 𝜌𝑔𝐴𝑥 (2)
The vertical beams have an L-shaped cross-sectional area of 0.225x10−3 𝑚2 whereas the
horizontal beams have a square hollow cross-sectional area of 0.116x10−3 𝑚2. Density, 𝜌 of
mild steel is 7850 kg/𝑚3 [28]. Equation (3) shows the equilibrium equation of the moments
∑ 𝑀𝑃 = 0
26
𝑥
(2𝑊𝐿𝑏 𝑥 + 2𝑊ℎ𝑏 )𝑥 + (5𝑊ℎ𝑏 + 𝑊𝑐 ) 2 − 𝑊𝑏 (0.17) = 0 (3)
From equation (2), the values of the above weights were as follows:
Solving for x, the value gotten was 0.6849 m = 684.9 mm. The length of the beams to counter
Because the width of the hollow beams cross-section was 30 mm, the horizontal platforms
formed by these beams have an outside dimension of 715 mm x 715 mm considering the
beams being welded side by side at 90°. With more components added onto the structure,
The fabrication of the mock-up started out with modifying the dimensions of the concept’s
purification section shown in figure 6.3. Some frames were modified in the drawing due to
the availability of them used to make the framework of the prototype. The material used for
The biggest diameter each bucket has is about 340mm and therefore, the constraint beams as
shown in the figure below have dimension of 350mm x 350mm on the inside with the
shortest clearance of 5mm between the bucket and the constraint framework. Due to this, the
beam dimensions on the outside are 410mm x 410mm considering the beam thickness to be
30 mm.
27
350 mm
410 mm
410 mm
Figure 6.16: Constraint beams
These beams were welded together and then welded at the top part of the framework shown
below to form the constraining frames of the filtration section. The welded components were
The main beams were cut and welded together as shown below in the figure. The structure
28
Figure 6.18: System beam structure
The constraining frame of the pre-filter was then mounted onto the frame and the result came
out as shown in the figure below. The constraint beams were put half way the framework to
balance the stress occurring on the welds. platform of the UV bucket was also made just
slightly smaller than the pre-filter platform due to scarceness of metal material.
Chipboard was then cut to the appropriate dimensions to hold the system components. The
solar panel was then welded on supports on the end opposite to the pre-filtration section. The
29
three buckets were then placed as illustrated in the concept. 2 drainage holes were made in
between bucket 1 and 2 for inflow of water onto the sari-cloth filter.
As for the electric components, sizing was done to suit the capacity of the solar panel with the
help of Mr. Ndapuka. The rated power of the UV lamp is 20 Watts and, of course, a solar
panel of a higher voltage was recommended. A 30% tolerance of power input should be
considered when connecting loads onto the PV system. With that known, the maximum
possible input power of the PV system was 26 Watts given that tolerance. Other components
such as the regulator, battery and inverter were considered to have power losses. It was hence
necessary to use a solar panel of considerable amount of power (40 W) to accommodate these
factors. The specifications of the inverter, battery and regulator are shown in table 8.1.
As the fabrication was all happening, the drawing was also modified and finalised. The figure
30
6.6 Tests and results
The testing of the system was carried out after its fabrication. The system’s plumbing work
was designed and tested for any faults or leakages. In its current status, the system’s pre-
Before carrying out this test, it was ensured that the stop tap and check tap were closed to
avoid any spills on the structure. Water was poured inside bucket 1 and was drained into the
bucket 2 and leaks were observed from the pipe work as shown below.
Insufficient seal
Spills observed
indicating the
presence of leaks
in the plumbing
Pipe was too loose
A leak was observed on the coupler which links bucket 2 and the line leading to the UV
bucket. This was due to insufficient tape sealing of its threads. Another leakage was observed
31
on the check tap linkage on the connection of the pipe to the bushings. This was due to a
loose connection of the pipes on the bushings. The filtration section had to be removed as
The quantity of tape seal was limited but the effort was made to ensure minimal leakage from
the 2 couplers fastened to the bucket. The pipes were then disconnected from the system and
reconnected tightly.
With that done, the filtration phase was reconnected and tested the second time. It was then
observed that there were no more leakages from the pipe whilst there was minimized leaking
of water from the coupler on the check tap linkage with the other coupler. This was then the
moment to test the taps for any faults and it was observed that the taps were functioning well.
The sari-cloth filter was tested for its effectiveness. This test was carried out to determine
how many layers of the sari material required for reducing the cloudiness of the water for
there was no instrument to measure turbidity. Sari-cloths averagely perform well on 2 passes
[16]. For the sake of surety, 4 passes of sari were initially put and gripped inside bucket 2
32
with the bucket 2 lid. The figures below show a 2litre beaker containing contaminated water,
made in the machining laboratory, that flowed through these passes and what was contained
in the water which were wood shavings, mild steel shavings and dirt from the workshop
With both taps closed, the contaminated water was then poured into the filtration column 5
times with its contaminants. The filtration took place and this was the result of the 4 passes of
sari-cloth:
33
Figure 6.25: The result of the
sari-cloth with 4 passes
This result was not satisfactory because the water was still cloudy and hence, on the second
trial, the number of layers of sari-cloth was doubled to 8 passes and the test was repeated.
Although the turbidity may still have appeared to have been above 5 NTU, the resulted water
after 8 passes of sari-cloth was more satisfactory than the result obtained from the first test.
34
However, for particles that were able to flow with the water through the passes, it was
observed after some time that they had settled at the bottom of the bucket hence making the
water less cloudy. The following image shows the water withdrawn from the check tap after
In rural areas, women and children might have to go long distances to fetch clean water. A
system like this saves them from walking long distances to get clean water since it can purify
the water near them. There are certain factors considered that may be relevant to this project.
Environmentally, since the UV-C system planned will not be dependent on any type of fuel,
there will be no greenhouse gases emissions. Sustainably, the system concept is open to
future improvements for researchers. If this design is successful, it can serve as an economic
benefit in terms of not spending a lot of money on other systems that are more expensive.
Also, its fabrication can incorporate different design concepts such as different materials that
can be used, different structural appearances and so forth. It can as well yield a huge health
benefit if the ministry advances its exposure and thus far, meet the living standards of World
Health Organisation (WHO) such as the importance of safe drinking water to public health
[29].
35
7.0 DELIVERABLES
1. Prototype
3. Project Report
TOTAL N$ 5744.85
36
Table 8.2: Project budget to make a completely functionable system
Supposing in the community, there are 30 families of four on average. The lifetime of the
bulb is 8000 hours. Therefore, the number of years the UV-Lamp would last assuming it is
used per family once per day is evaluated by the equation below:
𝐿𝑖𝑓𝑒𝑡𝑖𝑚𝑒
Durability = 𝐻𝑜𝑢𝑟𝑠 𝑓𝑎𝑚𝑖𝑙𝑖𝑒𝑠 𝑑𝑎𝑦𝑠
𝑥 𝑥
𝑓𝑎𝑚𝑖𝑙𝑦 𝑑𝑎𝑦 𝑦𝑒𝑎𝑟
8000
Durability = 41 = 64.15 years
𝑥 30 𝑥 365
3600
Taking the assumption above, the amount of kWh used by the lamp annually is given by the
equation:
41
AKWH = 0.02 𝑥 𝑥 30 𝑥 365 = 2.49 kWh/year
3600
The following is a table showing an estimate of how long each item would last. The solar PV
system can last up to 25 years but other components may fail earlier than that time.
37
Solar Panel 25
Regulator 25
Inverter 25
Battery 25
Wood 5-7
UV Lamp 64
Buckets 15 +
PPR components 30
Framework Welding 40
Sari-cloth 2
9.0 CONCLUSION
The project was carried out based on the requirements of the Ministry of Agriculture, Water
and Forestry who were the clients. A number of design concepts were looked at and the final
concept was selected based on reduction of costs and requirements of the client. Materials
used to build the system were selected based on their availability and cost reduction.
Calculations were made to determine the time for the system and its physical stability. The
test for linkage leaks were carried out and leaks were observed and dealt with as well as the
sari-cloth effectiveness was also done and the conclusion was to use 8 passes of the cloth.
However, this project was faced with many challenges. Among others, materials took some
time to arrive at the campus but while that was still in the process, the drawing was being
done. Another challenge was that the UV lamp unfortunately did not arrive within the
timeframe needed to complete this project. While its arrival was still awaited, activities of the
project continued either way. A turbidity meter was unavailable hence unable to test exactly
This current system is not affordable to a rural family of four people due to their economics
of scale. People who are well to do can actually afford this system and can use it for outdoor
use where they want to be sure of the water they want to drink.
38
The prototype, if complete, would purify water in 153 seconds of purification time with a UV
10.0 RECOMMENDATIONS
In a large community, a storage tank for both contaminated and potable water is
recommended for it with the current prototype being on the platform once able to
function.
The type of wood used on the project may not be the best option for the platforms of
the buckets due to the fact that spills of water can reduce its lifespan. It is therefore
recommended to research on the type of material that can be used for these platforms.
A switch is needed in the electric circuit to switch the lamp on for 41 seconds and the
It is a huge must to prevent the inverter and regulator from damage or shorting. To
prevent this, a cover on the structure on top and at the side can be essential. In order to
minimize on cost, the chipboard to cover these parts could not be sourced.
39
REFERENCES
[2] T. Salaam, “Global Access to Clean Drinking Water and Sanitation: U.S. and International
2017].
[3] T. Tjihenuna, “More than 1 million Namibians defecate in open,” The Namibian, Windhoek,
http://www.namibian.com.na/index.php?id=121736&page=archive-read.
[4] K. Matengu, “Towards improving rural water supply and sanitation coverage in Caprivi,
North-east Namibia,” Journal for Studies in Humanities and Social Sciences, p. 13, 2013.
[5] Ministry of Agriculture, Water and Forestry: Water Supply and Sanitation Sector Policy,
[6] Unknown, “Understanding UV water Purification,” How UV Works and What It Does, 2017.
2017]
[7] B. Wilson, “Design and Construction of a Solar Water Purification system using Ultraviolet
[8] ] S. Deshmukh, “Portable Solar Water Purifier,” TERI PRESS, New Delhi, 2014.
[9] A. Shull, “The Design and Creation of a Portable Water,” Andrews University, 2012.
[10] N. Martin, S. Oberg and A. Yoder, “Water Purification System,” Messiah College Department
of Engineering, 2007.
40
2017].
[12] Unknown, "Water for Africa," Institute Water for Africa, 2015. [Online]. Available:
[13] T. B. Bagundol, A. L. Awa and M. R. C. Enguito, “Efficiency of Slow Sand Filter in Purifying
[14] H. Williams, “Slow sand filtration as a water treatment method,” An inventorying study of
slow sand filters purification rates in rural areas in Colombia, p. 75, June 2015.
[16] M. Stevenson, “Monitoring Effective Use of Household Water Treatment and Safe Storage
mit.edu/watsan/Docs/Student%20Reports/MonitoringEvaluation/Final%20Paper%20_Group
https://www.thebetterindia.com/23049/an-old-saree-glass-tubes-and-sun-all-you-need-for-a-
http://mimoza.marmara.edu.tr/~bilge.alpaslan/enve301/Lectures/Chp_12.pdf. [Accessed 16
May 2017].
[20] M. Henry, S. Maley and K. Mehta, "Designing a Low-Cost Ceramic Water Filter Press,"
International Journal for Service Learning in Engineering, vol. 8, no. 1, pp. 62-77, 2013.
2017].
41
[22] Unknown, "Aliexpress," Smuxi, 2017. [Online]. Available:
https://www.aliexpress.com/item/Smuxi-20W-E27-UVC-Germicidal-Lamp-CFL-Ultraviolet-
UV-Light-Tube-Bulb-Disinfection-Lamp-Ozone-Sterilization/32812235491.html. [Accessed
24 September 2017].
news/understanding-the-difference-between-retention-time-and-relative-retention-time/31166.
[26] V. Adam, E. Arnold and K. Brieden, "UV-Lamps for Disinfection and Advanced Oxidation -
42
APPENDICES
43
44
45
46
47