Progress of Earth Works of SS V as at 22nd December 2017

Section cut/fill Sub sections Progress/(%) Remarks


18010-18120 cut 100
18120-18320 85
18120-18430 fill
18320-18430 0
18430-18790 cut 60
18790-19030 100
18790-19110 fill
19030-19110 0
19110-19300 cut 90
19300-19460 fill 100
19460-19600 100
19460-20360 cut
19600-20360 30
20360-20430 100
20430-20560 80
20560-20700 10
20700-20840 5
20840-20930 80
20930-21020 100
21020-21120 0
20360-21950 fill
21120-21200 40
21200-21250 0
21250-21370 40
21370-21780 0
21780-21810 10
21810-21870 0
21870-21950 10
21950-22000 cut 100
22000-22300 2
22300-22410 100
22410-22470 0
22000-22950 fill
22470-22580 100
22580-22680 70
22680-22950 25
22950-23090 cut 60
23090-23290 fill 0
23290-23520 cut 0
23520-23610 0 Clearing only
23520-23660 fill
23610-23660 50
23660-23840 100
23840-23890 fill 100
23890-24110 cut 100
24110-24220 100
24110-24700 fill
24110-24700 fill
24220-24700 0 Clearing In Progress
24700-24820 cut 95
24820-25030 fill 0
25030-25310 cut 0
25310-25360 fill 0
25360-25550 0
25360-25760 cut
25550-25760 75
25790-25950 fill 0 Clearing only
25950-26230 cut 0
26230-26500 fill 0
cl