PT. WASKITA BETON PRECAST Tbk.

MONITORING PCI-GIRDER

Periode: 13 Februari 2017

VOLUME PRODUKSI VOLUME PENGIRIMAN


NO. URAIAN SATUAN KETERANGAN
PMO S/D SAAT INI S/D SAAT INI SISA
I PROYEK JALAN TOL BECAKAYU
1 Square pile (Bottom) 45 x 45 L = 12 m Batang 1854 1854 1701 153
2 Square pile (Upper) 45 x 45 L = 11 m Batang 30 30 30 0
3 Square pile (Midlle) 45 x 45 L = 10 m Batang 56 56 52 4
4 Square pile (Bottom) 45 x 45 L = 10 m Batang 1600 1600 1569 31
5 Square pile (Upper) 45 x 45 L = 9 m Batang 76 76 76 0
6 Square pile (Upper) 45 x 45 L = 8 m Batang 155 155 154 1
7 Square pile (Upper) 45 x 45 L = 7 m Batang 210 210 210 0
8 Square pile (Upper) 45 x 45 L = 6 m Batang 738 738 721 17
9 Square pile (Upper) 45 x 45 L = 5 m Batang 388 388 357 31
10 Square pile (Upper) 45 x 45 L = 4 m Batang 93 93 93 0
11 Square pile (Bottom) 30 x 30 L = 3 m Batang 372 372 229 143
12 Square pile (Middle) 30 x 30 L = 4 m Batang 658 607 433 174
13 Square pile (Upper) 30 x 30 L = 4 m Batang 204 204 156 48