Development Organization Of 6 October City
‘Waste Water Treatment Plant (150000m3 )
General Site
ELECTRICAL WORKS
BILL OF QUANTITIES
Description Uni Total
Price
Light Current
A__ | External Ground Duct Network
A-1_ | Two way duct network including 4" UPVC
ducts, Trenching, concrete duct bank at
road crossing, welding ,elbows
sbends,.......cte. The price include 2X2"
Tead in PVC pipes to each building
A-2_ | Concrete hand hole 60X60X60 em with
frame cover
2300
28
TOTAL OF THE PAGE
‘Addendum —1- 25% May 2016
5