Development Organization Of 6 October City
Waste Water Treatment Plant ( 150000m3 )
General Site
ELECTRICAL WORKS
BILL OF QUANTITIES
Description
LIGHTING POLES :-
Supply, install, test and put into operation
lighting poles galvanized steel(10m height)
with one arc frame , led lighting fixtures
(93 watt), wiring by using wires 3 x 4 mm2
connections , completed with concrete base
awinch motor and all other fittings and
accessories required to complete the work.
MATERIALS.
Supply, install, test and put into operation
the load break switches inside galvanized
box IP 65, weather proof mounted on
galvanized pedestal ,complete with all
accessories and as specified and shown on
the drawings.
3-phases load break switch ,4 terminals,
with rating 380V , 40A (Fused)
3ephases load break switch ,4 terminals,
with rating 380V , 63 ( Fused)
3-phases load break switch ,4 terminals,
with rating 380V , 80A (Fused)
3ephases load break switch ,4 terminals,
with rating 380V , 100A (Fused)
3-phases load break switch ,4 terminals,
with rating 380V , 200A ( Fused)
TOTAL OF THE PAGE
3
‘Addendum —1- 25% May 2016