SBU ENGINEERING AND TRANSPORTATION

METODOLOGI
PEMERIKSAAN
SERTIFIKASI LAIK
OPERASI PLTMH
DALAM RANGKA
RE/SERTIFIKASI

Document1
SBU ENGINEERING AND TRANSPORTATION

I. METODE PEMERIKSAAN I. METHOD OF INSPECTION


 Menelaah dokumen teknis PLTMH  Review Technical documents of
dimaksud al : PLTMH :
- Buku Manual Mesin Turbin - Manual Book Turbine and
- Buku Manual Generator Engine
- Buku Manual Peralatan Proteksi - Manual Book Generator
- Laporan Tes Sistem Pembumian - Manual Book Protection Tools
- Laporan Tes Mesin Turbin - Test Report of Grounding
- Laporan Tes Generator - Test Report of Turbine and
- Laporan Tes Fungsi Peralatan Engine
Proteksi - Test Report of Generator
- Laporan Standart Operasi Prosedur - Test Report Function of
- Laporan Garis Diagram. Protection Tools
 Menelaah dokumen non-teknis PLTMH - Test Report of Operation
dimaksud al : Standart Procedure
- Dokumen Analisa Dampak - Single Line Diagram Report.
Lingkungan  Review Non-Technical documents
- Dokumen Keamanaan Bendungan of PLTMH :
PLTMH - The Environmental Impact
- Sertifikat Laik Operasi Pembangkit Analysis Document
- Sertifikat Tenaga Ahli - Dam Secure PLTMH Document
Pengoprasian PLTMH - Certificate Operation of
 Menelaah dokumen desain PLTMH Generation
dimaksud al : - Certificate of Expert on
- Sistem Pembumian Operation PLTMH
- Short Circuit level Sistem
- Sistem Pengaman Elektrikal
- Sistem Pengaman Mekanikal
- Sistem Pengukuran
- Koordinasi proteksi dengan grid
sistem tenaga listrik
- Pembersihan

 Melaksanakan pemeriksaan secara  Carry out examination visually


visual terhadap beberapa komponen against some of the supporting
pendukung dalam pengoprasian component in operation PLTMH
PLTMH dan memastikan kondisi pada and ensure that conditions on
PLTMH dalam kondisi baik atau PLTMH in good condition or the
kemungkinan adanya cacat-catat possibility of crack in general on:
secara umum pada : - Main structure (Turbine,
- Struktur utama Turbin, Generator, Belt, Gear Box)
Generator, Sabuk, Roda Gigi. - Support structure (Reservoir,
- Struktur pendukung Waduk, Dam, Sand Trap, Intake,
Bendungan, Saringan, Pintu Penstok, Main Valve)
Pengambilan Air, Pipa Pesat, - Bolt and nut
Katup Utama. - Insulation of House Power
- Mur & Baut pengikat
- Pelindung Rumah Tenaga Mesin

II. EVALUASI HASIL UJI II. EVALUATION OF TEST RESULT


 Pengukuran Tahanan Sistem  Grounding measurement

Document1
SBU ENGINEERING AND TRANSPORTATION

pembumian.  Testing main equipment


 Pengujian Induvidual Peralatan Utama: Individual:
- Elektrikal - Electrical
- Mekanikal - Mechanical
 Pengujian peralatan proteksi dan  Testing of equipment protection
kontrol : and control :
- Elektrikal - Electrical
- Mekanilak - Mechanical
 Pengujian fungsi catu daya peralatan  Testing resource ration function
proteksi dan kontrol. equipment protection and control.

III. PEMERIKSAAN DAN PENGUJIAN III. TESTING AND MEASUREMENT


a. Pemeriksaan Secara Visual a. Visual Inspection
 Melakukan Tes dan Pengukuran.  Testing and Measurement.
Pengujian ini bertujuan untuk Testing was intended to examine
memeriksa apakah pada semua whether on all the equipment that is
peralatan yang ada pada PLTMH available on PLTMH in accordance
sesuai dengan standart yang telah with standard that has been set by
ditetapkan oleh pemerintah. the government. Testing performed
Pengujian dilakukan dengan Metode with a method of testing the
pengujian Pengukuran Resistansi measurement resistance of
Pembumian, Pengukuran Tingkat grounding, the measurement of noise
Kebisingan, Pengukuran Getaran, level, measurement of vibrations,
Pengukuran Instalasi Listrik, measurement of electrical installation,
Pengukuran Suhu terhadap komponen the measurement of temperature
: against components:
- Turbin - Turbine
- Generator - Generator
 Data name plate peralatan utama  Name Plate of main equipment
 Perlengkapan/peralatan pengamanan  Protection of fire equipment
kebakaran  Protection of voltage
 Perlengkapan/pelindung terhadap  Protection of rotating equipment
bahaya benda bertegangan  Equipment of safety electrical
 Perlengkapan/pelindung terhadap  Grounding of equipment
bahaya benda berputar b. Testing of Performance
 Perlengkapan/peralatan sistem  Syncronizing Test
Keselamatan Ketenagalistrikan (K2)  Load of perform test power plant
 Instalasi  Loses of load
 Pembumian Peralatan  Voltage measurement test
b. Pengujian Unjuk Kerja Meliputi  Frequency measurement test
 Uji sinkronisasi  Power plant reliability.
 Uji Kapasitas pembangkit c. Examination Environmental Impact
 Uji lepas beban  Noise Measurement
 Uji pengaturan tegangan  Gas Emissions Measurement
 Uji pengaturan frekuensi  Examination of Waste
 Uji keandalan pembangkit
c. Pemeriksaan Dampak Lingkungan
 Pengukuran Tingkat Kebisingan
 Pengukuran emisi gas buang
 Pemeriksaan Limbah (Padat/Cair)

Document1
SBU ENGINEERING AND TRANSPORTATION

IV. PERALATAN INSPEKSI IV. INSPECTION EQUIPMENT


 Peralatan inspeksi dan pengujian  Inspection and test Equipment
 Peralatan (Grounding, Sound Level,  Equipment (Grounding, Sound
Vribasiometer, Thermograph) Level, Vibrometer, Thermograph)
 Peralatan Safety  Safety equipment
 Komputer sets  Set of Computer
 Mobil operasi.  Operation Car

V. PELAPORAN DAN PERIJINAN V. PERMISSION AND REPORTING


Menerbitkan buku laporan dan Issuing the Inspection Report and
pengurusan akte Ijin / Ijin Perpanjangan submit to the Disnaker for
ke Disnaker. legalizations.

Document1