TFBM Agency SCSG Intervention Report 090617
TFBM Agency SCSG Intervention Report 090617
TFBM Agency SCSG Intervention Report 090617
Date Rendered Activity/Program Description Beneficiaries & Area Estimated Amount / Issues Proposed Status Remarks
Funding Source Encountered/I Solution (Completed,
dentified Gaps Ongoing)
Emergency Response
Activities
July 3, 2017 Construction of 10 units Buruun Fisheries PHP 205,874.91 Latrine septage additional Completed
Latrines Evacuation Center comes full latrines to be July 5, 2017
easily constructed
on September
1, 2017
July 3, 2017 Construction of 9 units Ma. Cristina Gym PHP 179,597.44 Door locks Educate Completed Repair of door locks
Latrines Evacuation Center broken easily evacuees on completed on august
due to sense of 15, 2017
frequency of ownership
usage and
installation of
heavy duty
door locks.
July 1, 2017 Construction of 10 units Sta. Elena Evacuation PHP 233,658.52 Door locks Educate Completed Repair of door locks
Latrines Center broken easily evacuees on on July 3, 2017 completed on august
due to sense of 15, 2017
frequency of ownership
usage (August and
10, 2017) installation of
heavy duty
door locks.
August 11, 2017 Improvement/Installation of Sta. Elena Evacuation PHP 104,841.06 Completed
water system Center
Improvement of Evacuation Sta. Elena Evacuation PHP 233,213.58 Ongoing
Access Road and Premises Center
September 4, 2017 Expansion of Wash Area Sta. Elena Evacuation PHP 104,841.06 Completed
Center
August 17, 2017 Improvement of Evacuation Sta. Elena Evacuation PHP 233,213.58 Ongoing
Access Road and Premises Center
August 11, 2017 Improvement/Installation of Sta. Elena Evacuation PHP 104,841.06 Completed
water system Center
Improvement of Evacuation Sta. Elena Evacuation PHP 233,213.58 Ongoing
Access Road and Premises Center
September 4, 2017 Expansion of Wash Area Sta. Elena Evacuation PHP 104,841.06 Completed
Center
August 17, 2017 Construction of 5 units Pantar Evacuation Center PHP 124,116.01 Completed
Latrines
August 11, 2017 Insulation materials to Pantar Evacuation Center Delivered 1 roll of
minimize temperature insulator (August 17,
2017)
August 15, 2017 Installation of Shallow well Pantar Evacuation Center Completed on
water supply with 5000 liter August 17,
Tank. 2017
Improvement of all Evacuation All ECs PHP 5,156,430.60 Ongoing
Centers Access Roads and
Premises
September 4, 2017 Site development for Pantao-Ragat Temporary not yet started Delivery after site
transitional shelter Shelter development of
transitional shelter in
Sagunsungan, Marawi
is completed
August 11, 2017 Construction of 5 units Sarip-Alawi Evacuation PHP 118,259.79 Completed
Latrines Center
August 18, 2017 Improvement of Evacuation Al-Beroni Evacuation Completed
Access Road and Premises Center
August 11, 2017 Delivered 100 pcs. 1/4 Landa Gadungan Completed
ordinary plywood (August 17, Evacuation Center
2017) for elevating sleep area
of IDPs.
Expansion of area from Mahad Landa Gadungan Ongoing
Abdul Asis Madrasa to Landa, Evacuation Center /
Balo-i Mahad Abdul Asis
Madrasa Evacuation
Center
July 3, 2017 Transitional shelter Site Sagunsungan Transitional RROW LGU - Ongoing
Development Shelter Problems MARAWI to
Arised coordinate
with land
owners
Security Coordinate Resolved
Problem when with AFP for
Equipments security
(dumptrucks) measures and
were hit by plans
bullets from
unknown
assailants.
Reported by:
MARIA B. DAVID
Engineer III, DPWH - X
+639162329642 /
Notes:
a. This report will be the basis of the periodic report to the President
b. This is due every Friday morning.
c. Enumerate agencies with their respective accomplishments.