Professional Documents
Culture Documents
Ass. Measurement
Ass. Measurement
1 Soil Description
a. Ground water level and the date when it was established, is the pre-contract
water level and the ground water level which shall be re-established throughout the
time the various excavation works are carried out, is the post contract water level.
Ground water levels should be described in details and the average of the mean high
and low levels should be given due to the water level being the subject to periodic
changes due to tidal or similar effects.
2. If the above information is not available a description of the ground and strata which is to
be assumed shall be stated.
Site preparation
Cutting down hedges and grubbing up their roots, including their disposal. State the nature
and height of each hedge in metres or its location.
D3 Clearing Undergrowth, m2
Clearing Site of undergrowth, bushes, scrub and grubbing up their roots, including their
disposal, shall be given in square meters.
Explanations:
2. Because the top layer of ground contains material which is decomposing such as grasses,
roots, scrub, bushes which easily compressible and unsuitable for foundation.
4. In clearing undergrowth, we must measure and calculate the area of the clearing site and
the unit is in meters square.
6. Disposal of plants which already cut no need stated as the works, assume include in the
measurement of items.
D.4 Removing trees
Cutting down trees and grubbing up their roots, including their disposal, shall be enumerated
and classified in stages of 300mm girth ( measured at height of 1.00m above ground). Filling
in voids, after removal of tree roots shall be given in description.
Removing existing tree stump and grubbing up their roots, including their disposal, shall be
enumerated and classified in stages of 300mm girth (measured at height of above ground or
at their tops if lower in height). Filling in voids if required, after removal of tree roots shall be
given in the description.
Turfs are lifted to be preserved shall be given in square metres and state the method of preservation
and disposal.
D7. Topsoil,m2
Topsoil are excavated to be preserved shall be given in square meters and state the average depth.
Handling and disposal of topsoil shall be given.
Cutting down trees and removing tree stumps (irrespective of girth) and grubbing up their
roots, which shall be deemed to include their disposal, may be given as an item stating the
area. Clearing of undergrowth within such areas and grubbing up their roots shall be given in
the description.
Explanations:
2. All sites clearing works can be given in one item by state out the area of the site.
4. The different is all the works of site clearing that measured separately in alternative
1 can be change into one item only in alternative 2 and the area of site should be
given at last of description.
Excavation:
The quantities given for excavating and subsequent disposal shall be the bulk before excavating and
no allowance shall be made for any subsequent variations to bulk or for any extra space required to
accommodate earthwork support, formwork for concrete and working space.
Explanations:
1. This is use in classify the depth of excavation which can be used in different
excavation such as excavation to reduce level, excavation pit for pad foundation,
excavation trench for ground beam.
2. We cannot straight away mention the real values of depth of excavation in
description however we must classify them into group given above in the description
of excavation.
Starting level shall be ‘ground level’, ‘reduced level’, ‘ formation level’ from which excavation shall
commence and appropriate level shall be stated and described.
We do the excavation works below lowest floor finish after piling is done.
Excavation around piles is only cover the area of the piles and not cover for whole area.
The description is same as the pits excavation for pad foundation but we need to mention
the ‘excavation around piles’ at last of description.
Excavation for rock shall be given as ‘Extra Over” . Calculate by using 5% or 10% of the excavation pit.
Excavating trenches to receive foundation given in cubic metres,m3 and state its level.
An item shall be given for keeping the surface of the site and the excavations free of surface water.
Where excavation is measured below the water level, an item shall give for keeping excavations free
of ground water.
When doing excavation, there will certainly have water on the surface of the ground and also
water in the ground.
To keep the site free from water on the surface of the ground such as rain water.
Removal soil should be specified either stored or dispersed and stated the condition of deposites
location or average distance from excavation (m or km)
Thick ≤250mm – m2
Thick ≥ 250mm – m3
Top soil which dispersed on site is measured separately for soil from preserved and imported
Topsoil stored on site for reuse should describe the site store or the average distance from the
ecavation (m or km)
Thick ≤250mm – m2
Thick ≥ 250mm – m3
D.24 Measurement
-measurement of filling is same with size of the void to be filled and no extra volume of filling before
compaction.Thickness of filling shall be deemed after compaction
-forming slopes and finishing to falls and cambers for the various items of filling the description but
for hand packing hardcore shall be follow with clauses
-all the filling to excavation shall be measured in cubic metres except to services trenches ( D.12.9 )
which filling shall be given in description of such trenches
-filling to make up levels shall be measured in cubic metres for the thickness over 250 mm
-thickness not exceeding 250 mm thick shall be measured in square metre and stated average
thickness
-filling required to be deposited and compacted in layer shall be explained of the maximum thickness
if the layers in descriptions