Professional Documents
Culture Documents
TMG Hold & Check Points 16.11.17
TMG Hold & Check Points 16.11.17
TMG Hold & Check Points 16.11.17
Sl no Description Doc No
Project-
Job No-
Area-
Location-
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
1.1 Cable tray layout as per G.A/ composite layout drawing no.
3 Erection
Contractor TSL
Name
Designation
Project
Job No.
Cable layout/ Cable
Schedule no.
Voltage level
Checked by Checked
Remarks/
Contractor by TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
1.1 Cable route layout as per G.A/ composite layout drawing No
2.3 Check the IR value & physical condition of cable planed for laying.
2.4 check clear access to location for cable laying along the cable route.
For Under ground cable laying- Measure the Depth & sand bed for
3.3
underground cabling as per guidelines before laying cable.
For Signaling cables- Lay the signalling cable inside the conduit.
3.5
Fix the coupler after cabling
Fixing of cable tags as per unique cable Identification no at both
3.6 ends and at intervals as per specification immediately after dressing
of cable.
Contractor TSL
Name
Designation
Project
Job No.
Equipment/Designation no.
Location
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
1.1 Location and orientation as per G.A Drawing no.
Clearance for grouting/ welding with insert plate for bus buct
3.3
supports
3.4 Placement & alignment of sections / enclosures on supports.
3.5 Alignment of busbars for the entire length.
3.6 Cleaning of all support insulators, busbars, flexible joints etc.
3.13 Installation of busduct CTs and their wiring upto JBs/ MBs.
Contractor TSL
Name
Designation
Project
Job No.
Transformer no.
Location/Voltage level
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Verification wrt Drawings
1.1 Location and orientation as per G.A Drawing no.
1.3 Name Plate details & assemby as per approved Vendor Drawing no.
Contractor TSL
Name
Designation
Project
Job No.
Transformer no.
Location/Voltage level
Checked
Checked
by Remarks/
by TSL
Contractor Observations
(Tick)
Sr. No Item Description (Tick)
1 Reference Drawings
1.1 Location and orientation as per G.A Drawing no.
Contractor TSL
Name
Designation
Contractor TSL
Name
Designation
Signature & Date
Format No-
TATA STEEL LIMITED
Hold & Check
Points
TSL-E-HCP-
Installation of Drives 07-R0
Project
Job No.
Drive no.
Location/Voltage level
Checked by Checked by
Remarks/
Sr. No Item Description Contractor TSL
Observations
(Tick) (Tick)
1.2 Name Plate details & assembly as per approved Vendor Drawing no.
3.6 Foundation bolts fixing with base frame to support structure by bolting.
Connections of internal wire to devices and terminal blocks and their
3.7
dressing.
Intersection/ interpanel wiring as per vendor drawing & tightness of
3.8 connections.and earth connections ( both body earthing & electronic
earthing).
3.9 Cleaning of internal parts of the panel.
3.10 Rack in / Rack out operation of the switchgear truck / module.
3.11 Fixing of Bus-bar shrouds / Insulating barriers.
3.12 Space heater / thermostat connection.
3.13 Check clearance of busbars (i.e from Ph to Ph & Ph to E) at terminals.
3.14 Smooth operation of truck / module including shutters.
Closing of all doors / covers to ensure dust / vermin proof condition
3.15
including provision of proper gaskets.
3.16 Door interlock checks (Mechanical).
3.17 Measurement of IR value ( Indicate value )
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Contractor TSL
Name
Designation
Project
Job No.
Location -
2.5 Availability of necessary tools and tackles for the erection work.
3 Erection
Marking the locations on floor / roof / wall / structure/ conduits with other
3.1
equipment / systems.
3.6 Excavation for cable trench for street light/ outdoor lighting cables.
Pulling of earthing wires along cable / conduits and its termination as per
3.13
specs.
3.14 Use of different color wire (code) for phase, neutral and earth wire.
3.18 Erection of lighting poles including its excavation, grouting and concreting.
Contractor TSL
Name
Designation
Project
Client / Job No.
Equipment no.
Location/Voltage level
Checked by Checked by
Remarks/
Sr. No Item Description Contractor TSL
Observations
(Tick) (Tick)
1.3 Name Plate details & assembly as per approved Vendor Drawing no.
Contractor TSL
Name
Designation
Project
Job No.
Conveyor no.
Area-
Checked by Checked by
Remarks/
Sr. No Item Description Contractor TSL
Observations
(Tick) (Tick)
Measure & mark the location of safety switches from drive end of the
conveyor as per the drawings & specification. Verify fouling of any
3.1 switch/support frame with conveyor accessories like guards, utility
pipelines, cross over bridges, other movable objects if any &
consider Maintenance prospects also.
Weld the frame on stinger post & striker plates on pulley (if not
3.13
available) at tail end of the conveyor for installation of ZSS.
Fix the ZSS controller with bolt & Place the proximity switch on the
3.14
frame near to the striker of tail pulley or other pulley as per drawing
Complete the cabling & termination & adjust the proximity switch
3.15 position for sensing the strikers. Adjust the NTD/ITD during
commissioning of the switch.
For Chute block switch install the sensor on the discharge chute.
3.16
( Marking & cutting to be done by mechanical) as per drawing.
Fix the contoller near to the discharge chute & complete the cable
3.17
termination between controller & sensor.
For Under belt switch installation weld the frame below the belt so
3.18
that the roller of the UBS will touch the belt only in loaded condition.
Fix the switch & controller as per drawing & complete the internal
3.19
wiring.
For shuttle conveyors fix the NTLS & OTLS switches at the travel
ends & fix the striker on the moving structure. The position of the
3.20
switches to be marked by moving the shuttle within extreme travel
positions.
Lay cable from switches to the panel as per the schedule &
3.22
complete the terminations.
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Project
Job No.
Instrument / P&ID No-
Location / Service line-
Checked by Checked by
Remarks/
Contractor TSL
Observations
Sr. No Item Description (Tick) (Tick)
Range of the Transmitter has been correctly selected and set points
5
have been provided as per drawing.
Contractor TSL
Name
Designation
Project
Job No.
Equipment Designation-
Loation.
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
Contractor TSL
Name
Designation
Project
Job No.
Battery Charger/DCDB no.
Location
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
1.1 Location and orientation as per G.A Drawing no.
3.6 Space heater / thermostat connections for battery charger and DCDB.
Contractor TSL
Name
Designation
Project
Job No.
Battery Charger/DCDB no.
Location
Checked by Checked by
Remarks/
Contractor TSL
Observations
Sr. No Item Description (Tick) (Tick)
1 Reference Drawings
2.7 Availability of PPEs like rubber gloves/ full body apron etc.
3 Erection
3.1 Assembly of battery support, erection and alignment
Assembly of battery cells & installation of inter cell connectors for
3.2
battery
Contractor TSL
Name
Designation
Project
Job No.
PLC Panel No-
Location-
Checked by
Contractor
(Tick)
Sr. No Item Description
3
Cable routings and connections are properly clamped, dressed &
tagged
4
Tag No has been provided on the Panel / controller and the devices
Are as per drawing
6 Loop checking has been done for each and every digital input from
the field as well as electrical room
7 Loop checking done for each & every Analog input from field
Loop checking done for each & every digital & analog Output
8 from PLC to field and the same has been correctly wired and
function of field device is ok
Remarks/Any other Obervations
Contractor
Name
Designation
TSL-E-HCP-16-
R0
Checked by
Remarks/
TSL
Observations
(Tick)
TSL
Format No-
TATA STEEL LIMITED
Hold & Check
Points
TSL-E-HCP-
ERECTION OF GENERATOR (ELECTRICAL PART) 17-R0
Project
Job No.
Equipment no.
Rating/ Location -
Checked by Checked
Remarks/
Contractor by TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
1.1 Location and orientation as per G.A Drawing no.
Contractor TSL
Name
Designation
Signature & Date
Format No-
TATA STEEL LIMITED
Hold & Check
Points
ERECTION OF DIESEL GENERATOR SET
TSL-E-HCP-
18-R0
Project
Job No.
Equipment no.
Rating/ Location -
Checked by Checked by
Remarks/
Contractor TSL
Observations
Sr. No Item Description (Tick) (Tick)
1 Reference Drawings
1.1 Location and orientation as per G.A Drawing no.
2.2 Identification of shortages and damages & reporting for insurance claim.
3.12 Space heater / thermostat connection for generator and DG control panel
Contractor TSL
Name
Designation
Signature & Date
Format No-
TATA STEEL LIMITED
Hold & Check
Points
CHECK LIST FOR “AUDIO/LOUD SPEAKER
TSL-E-HCP-
COMMUNICATION SYSTEM” 19-R0
Project
Job No.
Device No-
Location-
Checked by Checked by
Remarks/
Contractor TSL
Observations
Sr. No Item Description (Tick) (Tick)
The main unit and the sub units have been provided at the
1
locations as per the drawing
2
Fixing arrangement of base unit (amplifier) with mic, loud
speaker, JB, etc is sturdy and properly protected
4
Tag No has been provided on the device as per drawing
Contractor TSL
Name
Designation
Signature & Date
Format No-
TATA STEEL LIMITED
Hold & Check
Points
TSL-E-HCP-020-
ERECTION OF FDA System R0
Project
Job No.
Location
Checked by Checked by
Remarks/
Contractor TSL
Observations
Sr. No Item Description (Tick) (Tick)
1 Reference Drawings
3.9 Electrical Termination for Panels/ Power supplies with gland, lugs &
proper tightness.
3.10 UPS Power Provided near Panel / Power Supply. i.e as per
approved scheme.
3.11 Fix the detectors on the base as per drawings.
3,12 Install the Repeater panels & hooter as per the drawings
Install the Manual call point as per the drawings & at accessible
3.13 locations
3.14 Nomenclature of the devices/ Panels
4 Erection in Conveyors.
Weld the LHS cable supports on the stringer posts of conveyor
4.1 preferably before laying of the belts.
4.2 Fix the Panels at designated locations.
4.3 Lay the LHS cable after belting & clearance from Mechanical,
4.4 Cable should be at proper distcance from the running belts & should
not rub with the belts & overhang.
Lay the cables to the panels & interfacing systems like Deluge /
4.5 ventillation systems etc.
4.6 Nomenclature of the devices/ Panels
4.7 Earthing of panel and connections to main grid .
4.8 External cabling for auxiliary power and control supplies
Sealing of extra cable entries in gland plates of each equipment after
4.9 completion of cabling work.
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Signature & Date
Format No-
TATA STEEL LIMITED
Hold & Check
Points
CHECK LIST FOR GAS ANALYSER TSL-E-HCP-
21-R0
Project
Job No.
Device No-
Location/ Service-
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
Contractor TSL
Name
Designation
Project
Job No.
Device No-
Location/ Service-
Contractor TSL
Name
Designation
Project
Job No.
Device No-
Location/ Service-
Checked by
Contractor (Tick)
Sr. No Item Description
1 The valve has been provided at the location as per the drawing
Contractor
Name
Designation
TSL-E-HCP-23-R0
TSL
Format No-
TATA STEEL LIMITED
Hold & Check
Points
TSL-E-HCP-
Erection of Metal Detectors & Magnetic Separators 24-R0
Project
Job No.
Equipment no.
Location/Conveyor No-
Checked by Checked by
Remarks/
Sr. No Item Description Contractor TSL
Observations
(Tick) (Tick)
Contractor TSL
Name
Designation
Project
Job No.
Device No-
Location/ Service-
1 The gauge has been provided at the Location as per the drawing
2
Fixing arrangement is sturdy and properly protected
Contractor TSL
Name
Designation
Project
Job No.
Device No-
Location/ Service-
Checked by
Contractor (Tick)
Sr. No Item Description
3
Cable connection is proper with support and glanding
7
Tag No has been provided on the valve and the connecting
cables as per drawing
Contractor
Name
Designation
Signature & Date
Format No-
TSL-E-HCP-26-R0
TSL
TATA STEEL LIMITED Format No-
Hold & Check
Points
CHECK LIST FOR THERMO COUPLE / RTD
TSL-E-HCP-27-R0
Project
Job No.
Device No-
Location/ Service-
3
Cable connections (both power & communication) are properly
clamped, dressed & tagged
Contractor TSL
Name
Designation
Project
Job No.
Make/ Belt Scale no.
Location / Conveyor No-
3.9 Align at least two pre and post carrying idlers with weighing idlers.
Care should be taken to ensure that the load pin touches only the
3.10
sensing stud of the loadcell and not the loadcell casing.
Tacho fixing frame should be near to weighing frame.Weld the
3.11 supplied channel to the conveyor stringers. (Make sure that load
cells removed from structure before any kind of welding).
3.12 Fix the speed sensor assembly onto the pivot arm on the welded
channel
3.13 Mount the panel in a reasonably clean area away from severe heat and
isolated from vibration.
There should be an instrumentation earth available and that is to be
3.14
connected to the panel.
Run the signal cables through metallic conduits. The distance of the
3.15
signal cable from a power line should be at least one meter.
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Project
Job No.
Location/ Service-
Contractor TSL
Name
Designation
Project
Job No.
Cable Tag/ Schedule No-
Location-
2 Suppliers’ name & the Drum No of the Cable recorded for future reference
No physical damage occurred along the length of cable during laying-
3 Ensure that rollers are put at every 15 metres while pulling
Cable is properly Laid, clamped, dressed and tagged at regular
4 intervals
For cables buried underground, check that proper route markers, sand
cushion, brick separators, slab protection covers are provided along the
5 length.
For cables crossing roads/tracks, proper sized Hume/GI pipes are
6 provided for mechanical protection
7 IR Value of the Cable recorded before laying
HT DC Test Voltage applied and leakage current for the cable checked during
8 HIPOT Test
9 IR Value of the cable recorded Before and after HIPOT Test
Before final tightness of the cable Continuity to be checked for phase
10 And orientation of runs
11 Check provision of conduit pipes At the entry of buildings, tunnels, etc
Check if all the cable entry pipes into the substation building have been sealed
12 properly at both ends
Check if the cable entry point/gland plate inside the panel has been sealed
13
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Project
Job No.
EOT no./Capacity-
Location -
Details of the crane recorded along with the Crane Survey Report
(Span/Diagonal/Girder bottom Flange level for EOT Crane) and
1
(Span/diagonals/rail level for Gantry rail)
Deflection Test carried out with 100% Load and compared with the
2 Permitted value.
Values of current & voltage at all speeds For all motors/motions noted
3
Total Height of the Lift above and below floor are recorded.
5
Main hook approach is recorded on both DSL and Non DSL Side
6 and is complying to drawing
Contractor TSL
Name
Designation
Project
Job No.
Panel No-
Location-
3 Ratio Test of Control Transformer conducted and the values are noted
Contractor TSL
Name
Designation
Project
Job No.
UPS / ACDB no.
Location
Checked by Checked by
Remarks/
Contractor TSL
Observations
(Tick) (Tick)
Sr. No Item Description
1 Reference Drawings
1.1 Location and orientation as per G.A Drawing no.
Contractor TSL
Name
Designation
Project
Job No.
Make/ WF no.
Location-
3.1
Position the WF frame on the Civil foundations as per GA drawings
3.2 Alignment of WF frame & water level checking & Bolting with support
foundation. Mention the alignment readings.
Remove all the transit locks from WF mechanics.
3.3 Installation of WF conveyor motor on the foundation
Installation of CJBs, LCS & safety switches like Belt drift switch,
3.5 ZSS, Tachometer, chute vibration motor & limit switches as per
drawings.
3.6 Connection of electronic earthing for the panels & load cells.
3.7 Check the condtion & internal wiring of load cell to CJB.
No welding to be done on the frame if the load cell are fixed on the
3.8
structure.
Laying of interconnecting cables as per schedule & complete the
3.9
terminations
Install WF panel as per layout drawing & fix the controller &
3.10
accessories.
Provide electronic earth, UPS power supply & terminate the cables
3.11
as per schedule.
Routing of signal cables from load cells at field upto the panel is as
3.12
per OEM guidelines.
laying of cables between WF panel & PLC panels as per schedule &
3.13
complete termination.
3.14 Check the belt tightening, gap between feed chute bottom & belt,
installation of vibration pad as per OEM instructions
3.15 Adjust tail pulley scraper-cum-plough-scraper as per OEM
guidelines.
3.16 Shifting & placement of calibrated load at defined location.
3.17 Adjustment of the load cell button height as per guidelines.
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Project
Client / Job No.
MCC/PMCC/PDB/MLDB no.
Voltage level
Check & adjust the zero error of ammeters & volt meters of the switch board.
34
35 Check the room ventilation and ensure that there is no water ingress.
Measure the IR value of the bus section along with power circuit of all the motor
starters and outgoing feeders before boxing-up after removing earthing (Take corrective
36 actions, if IR value is low).
Remove the barriers provided and remove all the other shortings / earthings
37 made for carrying out the commissioning job.
Box-up the bus chamber and other compartments, etc. properly after ensuring
38 no tools / tackles / foreign materials are left inside.
39 Normalize other panels with proper co-ordination.
40 Motor Starter & Feeders
Test the motor overload relay elements by injecting primary current through the
overload circuit and monitoring trip time of the overload element.
41
42 Perform operational tests by initiating control devices.
43 Operate circuit breaker to ensure smooth operation.
44 Inspect case for cracks or other defects.
45 Perform a contact-resistance test.
Verify correct operation of any auxiliary features such as trip and pickup
indicators, zone interlocking, electrical close and trip operation, trip-free, and
46 antipump function.
Verify the calibration of all functions of the trip unit by means of secondary
47 injection
48 Check the operation of electrically-operated breakers in their cubicles.
Remarks/Any other Obervations
Contractor TSL
Name
Designation
Protected from
Storage and protection As specified Each week Visual
2 weather
Hazard
Assess- Specification, as
Preliminary activities Task completion Each work area
ment attached
3 procedure
5a
5b
5c
Wiring
All matters finalised, clean and Specification, as
Pre-handover activities Each work area diagrams/
tidy attached
checklist
6
A ‘witness point provides a party (such as the customer, service provider and regulatory authority) with the oppo
W = Witness Point
at their discretion.
A ‘hold’ point defines a point beyond which work may not proceed without the authorisation of a designated serv
authority’ might be an agency or other customer’s representative/ authorised person, or a regulatory authority (
H = Hold Point WorkCover etc.) representative, or it may be the service provider inspecting its service provider or worker.
Service
Worker Customer
Provider
Check
Specification and
Orders as placed against H S
codes
orders
Specification, as
All tasks completed Visual H W S
attached
To authority
Checked H W S
requirements
Checklist
SWMS012 Checked X W S
Checklist
SWMS013 Checked X W S
HV test report
gulatory authority) with the opportunity to witness the inspection or test or aspect of the work,