Professional Documents
Culture Documents
PMP s4 2013 v51 Integration
PMP s4 2013 v51 Integration
1
Copyright Narciss Popescu PMP Exam Preparation
I Project Integration Management
2
Copyright Narciss Popescu PMP Exam Preparation
1 DEVELOP PROJECT CHARTER I
INPUTS OUTPUTS
» Project statement of work Project charter »
» Business case
» Agreements
» Enterprise Environment
Factors
» Organizational Process TOOLS & TECHNIQUES
Assets
Expert judgement
Facilitation techniques
3
Copyright Narciss Popescu
7 Questions when a project is started
Business case
Typically contains the business need and cost-benefit analysis
Can be a result of:
Market demand
Organizational need
Customer request
Technological advance
Legal requirement
Ecological impacts
Social need
Agreements
Contracts
MoU – memorandums of understanding
SLA – service level agreements
Written agreements
Letters of intent
Verbal agreements
Expert judgement
It is used to assess the inputs
Forms of expert judgement
Other units within the organization
Consultants
Stakeholders, including customers or sponsors
Professional and technical associations
Industry groups
Subject matter experts (SME)
Project management office (PMO)
Facilitation Techniques
Brainstorming
Conflict resolution
Problem solving
Meeting management
Delphi technique
Project charter
May be created by the future project manager
But it issued by the project initiator or sponsor
Should be broad enough so it does not need to change as project
progresses
It is an internal document of the performing organization
It is a „contract” between the project manager and the performing
organization
Project charter
It contains:
Project purpose or justification
Measurable project objectives and related success criteria
High-level requirements
Assumptions and constraints
High-level project description and boundaries
High-level risks
Summary milestone schedule
Summary budget
Stakeholder list
Project approval requirements (i.e., what constitutes project success, who decides the project is
successful, and who signs off on the project)
Assigned project manager, responsibility, and authority level
Name and authority of the sponsor or other person(s) authorizing the project charter
Copyright Narciss Popescu
Develop Project Charter: Output
Project charter
Business need vs Customer’s need
Business need vs Business case
Why the „develop project charter” process is an integration process?
The management of the PMA Company has decided that the support activities for
the applications of an existing customer (ACCESS company) to be taken over by
PMA Romanian site. At this moment these services are delivered by PMA Sweden.
INPUTS OUTPUTS
» Project charter Project Management Plan »
» Outputs from other
processes
» Enterprise Environment
Factors
» Organizational Process TOOLS & TECHNIQUES
Assets
Expert judgement
Facilitation techniques
20
Copyright Narciss Popescu
Develop Project Management Plan
The key benefit of this process is a central document that defines the
basis of all project work
26
Copyright Narciss Popescu PMP Exam Preparation
Develop Project Management Plan: Output
27
Copyright Narciss Popescu PMP Exam Preparation
Develop Project Management Plan: Output
28
Copyright Narciss Popescu PMP Exam Preparation
Develop Project Management Plan: Output
29
Copyright Narciss Popescu PMP Exam Preparation
Develop Project Management Plan: Flow diagram
Enterprise Environmental Factors
Organizational Process Assets
Organization
a
Develop
project Project charter
charter Develop
Project Project Management Plan
management
plan
Other
processes Communications management plan
Cost management plan
Human resource plan
Procurement management plan
Process improvement plan
Quality management plan
Requirements management plan
Risk management plan
Schedule management plan
Scope management plan
Stakeholder management plan
Cost baseline Other
Schedule baseline planning,
Scope baseline controlling
Project management plan updates
and closing
processes
Copyright Narciss Popescu
3 DIRECT AND MANAGE PROJECT WORK I
INPUTS OUTPUTS
» Project management plan Deliverables »
» Approved change requests Work performance data »
» Enterprise Environment Change requests »
Factors Project management plan
» Organizational Process updates »
Assets TOOLS & TECHNIQUES Project documents updates »
Expert judgement
Project management information
system
Meetings
31
Copyright Narciss Popescu
Direct and Manage Project Work
management plan
Generate work performance data, such as cost, schedule, technical and quality
progress, and status to facilitate forecasting
Issue change requests and implement approved changes
Manage risks and implement risk response activities
Manage sellers and suppliers
Manage stakeholders and their engagement
Collect and document lessons learned and implement approved process improvement
activities
Meetings
Information exchange
Brainstorming, option evaluation, or design
Decision making
Deliverables
A deliverable is any unique and verifiable product, result or capability
to perform a service that is required to be produced to complete a
process, phase, or project.
There are typically tangible components completed to meet the project
objectives and can include elements of the project management plan.
Change Requests
A change request is a formal proposal to modify any document,
deliverable, or baseline
Change requests categories:
Direct/Indirect
Externally/Internally initiated
Optional/contractually mandated
Change requests types:
Corrective action
Preventive action
Defect repair
Updates
INPUTS OUTPUTS
» Project management plan Change requests »
» Schedule forecasts Work performance
» Cost forecasts reports »
» Validated changes Project management plan
» Work performance updates »
information TOOLS & TECHNIQUES Project documents updates »
» Enterprise Environmental
Factors Expert judgment
» Organizational Process Analytical techniques
Assets Project management information
system
Meetings
43
Copyright Narciss Popescu
Monitor and Control Project Work
Validated changes
A validated change provides the necessary data to confirm that the
change was appropriately executed
Analytical Techniques
Used to forecast potential outcomes
Examples:
Regression analysis
Grouping methods
Causal analysis
Root cause analysis
Forecasting methods (e.g., time series, scenario building, simulation, etc.)
Reserve analysis
Trend analysis
Earned value management
Variance analysis
Analytical Techniques
Examples:
Failure mode and effect analysis (FMEA)
INPUTS OUTPUTS
» Project management plan Approved change requests »
» Work performance Change log »
Reports Project management plan
» Change requests updates »
» Enterprise Environmental Project documents updates »
Factors TOOLS & TECHNIQUES
» Organizational Process
Assets Expert judgment
Meetings
Change control tools
51
Copyright Narciss Popescu
Perform Integrated Change Control
It concerns with:
Reviewing all change requests
Evaluating the change requests
Approving/rejecting changes
Managing changes to deliverables, organizational process assets,
project documents and the project management plan
Communicating the decisions and the change requests updates
Meetings
There are referring to the change control meetings
CCB (Change Control Board)
The roles and responsibilities of CCB are defined in the change management plan
Some of the responsibilities:
Reviewing the change requests
Evaluating the change requests
Approving, rejecting, delaying or other disposition of those changes
Reviewing configuration management activities
Executing
process
INPUTS OUTPUTS
» Project management plan Final product, service, or
» Accepted deliverables result transition »
» Organizational Process Organizational Process
Assets Assets updates »
58
Copyright Narciss Popescu
Close Project or Phase
It covers:
Actions and activities necessary to satisfy completion or exit criteria for
the phase or project
Actions and activities necessary to transfer the project’s products,
services, or results to the next phase or to production and/or
operations
Activities needed to collect project or phase records, audit project
success or failure, gather lessons learned and archive project
information for future use by the organization
Release the ressources
Verified
Direct and Accepted
Deliverables Control Deliverables Validate Close Project
Manage Project Deliverables
Quality Scope or Phase
Work
Change
requests
Perform
Change requests Integrated
Change requests Change
Control
62
Copyright Narciss Popescu PMP Exam Preparation
I Project Integration Management
63
Copyright Narciss Popescu PMP Exam Preparation
I Project Integration Management
If not...
64
Copyright Narciss Popescu PMP Exam Preparation
I Project Integration Management
I have...
25 Questions
And You have 30 minutes
65
Copyright Narciss Popescu PMP Exam Preparation