Professional Documents
Culture Documents
Planning For Desalination in The Context of The Western Cape Water Supply System
Planning For Desalination in The Context of The Western Cape Water Supply System
11
Blersch CL, Du Plessis JA. Planning for desalination in the context of the Western Cape water supply. J. S. Afr. Inst. Civ. Eng. 2017:59(1),
Art. #1200, 11 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n1a2
seawater desalination differs from the demands at the required assurance of sup- that the results of such an analysis should
surface and groundwater resources of the ply, or whether water restrictions should be be used when calculating the Unit Reference
WCWSS, firstly in its higher capital and implemented (Shand & Sparks 2004:6). Value (URV) of any newly proposed scheme
operating costs, and secondly in its resilience Seawater desalination as possible future (Van Niekerk & Du Plessis 2013b:552).
to climate variability, having an assurance supply source for the WCWSS was first
of supply of essentially 100 percent. Factors assessed at a pre-feasibility level in 2003 Estimating desalination costs
such as integration into the WCWSS, supply as part of the Bulk Water Supply Study. A
risks and cost implications may therefore be feasibility study was commissioned in 2011, South African approach to
more relevant in evaluating desalination than and was set for completion at the end of desalination costing
a 98 percent assurance of supply from tradi- 2013, although the findings have not yet been Du Plessis et al (2006) present a step-by-step
tional water supply options, as is currently released. The anticipated capacity based on guide to determining first-order capital and
the case. The higher costs and assurance of the feasibility study would be 150 Mℓ/day, operating costs for desalination plants of
supply of desalination will also impact on the upgradeable to 450 Mℓ/day (Department of different sizes in South Africa. The process
overall operational philosophy. Water Affairs 2013a:12). centres on selecting a plant capacity, deter-
The aim of this research was to deter- mining the required membrane area and
mine what operating rules and modified Local research into desalination feed water pressures, and calculating capital
planning criteria are required to optimise the and integrated system modelling and operating costs with these parameters as
implementation of large-scale desalination as Despite the various feasibility studies which a base. In terms of capital costs, the desalina-
part of the WCWSS, in order to ensure cost- are currently under way, and the ambitious tion cost component can be estimated as
effective provision of water at an appropriate outlook for seawater desalination develop- a function of the membrane area, the pre-
assurance of supply. ment in South Africa, there has been little treatment costs can be calculated as a func-
research into the conjunctive use of seawater tion of the feed flow rate, and the combined
desalination with surface water supply cost of the intake, outlet and post-treatment
BACKGROUND AND sources, and how to integrate seawater systems can be estimated as a percentage of
LITERATURE REVIEW desalination plants into existing water supply the capital cost of the desalination plant and
systems. The only South African authors pre-treatment system (15 to 30 percent).
Existing Western Cape Water who have presented any material on the topic Du Plessis et al (2006) suggest that the
Supply System are Mallory et al (2013) who undertook a operating costs comprise energy costs, which
The Western Cape area is characterised by a study into the optimal operation of the sea- can be estimated based on the total energy
Mediterranean climate, with rainfall occur- water desalination plant in Mossel Bay using requirement of the plant (which is primarily
ring in the winter months (May to October) the Water Resources Modelling Platform. a function of feed-water pressure), chemical
when demands are low, and minimal rainfall The work of Mallory et al (2013) began to costs of approximately R0.50/m3, membrane
occurring in the summer months when tackle some of the key questions associated replacement costs based on a unit cost of
demands are high. Approximately 50 per- with the value of water to different users, and R165/m2 of membrane area and a membrane
cent of the total system storage is available setting of operating rules for a desalination lifespan of six years, and annual labour
for storing winter flows to meet summer plant. and maintenance costs of about 5 percent
demand, with the remaining 50 percent Although not specifically related to sea- of the total capital cost. All costs and rates
required for long-term drought storage water desalination, the work of Van Niekerk provided by Du Plessis et al (2006) are for a
(Shand & Sparks 2004:3). The main dams and Du Plessis (2013a:543) into the conjunc- base date of 2006 and were escalated to 2014
of the WCWSS are operated as an integral tive evaluation of the costs and benefits of at 6 percent per annum.
system in order to reduce the probability of inter-basin water transfer schemes illustrates This methodology was applied to the pro-
spillage, hence increasing the overall system a number of useful principles which could be posed Cape Town desalination plant, situ-
yield (Department of Water Affairs 2007:31). easily applied to integrate system modelling ated on the west coast, based on a capacity of
The WCWSS supplies water to various for seawater desalination. Van Niekerk and 100 Mℓ/day and a two-pass system, giving a
towns and irrigators in the Western Cape, Du Plessis (2013a:543) found that the so- first-order (2014) estimate of the capital cost
including the City of Cape Town. The latest called incremental approach has historically of R1 054 million and the total specific cost
WCWSS planning documents give the total been followed in evaluating the viability of of R16.44/m3.
water usage from the system as 503 mil- inter-basin transfer schemes, which assumes
lion m3/a in 2013 (Department of Water that volume transferred per annum is equal International seawater desalination
Affairs 2013a:21) and the total integrated to the difference between the projected literature
system yield at a 98 percent assurance of future water demands and the current sys- In terms of international literature on seawa-
supply as 596 million m3/a (Department of tem yield. The authors found that the origi- ter desalination cost estimation, Karagiannis
Water Affairs 2011:7). To manage demands, nal projections vastly exceeded the actual and Soldatos (2008) studied almost 100 dif-
yield and planning models of the WCWSS transfers, mainly because the incremental ferent seawater desalination plants and pre-
have been set up in the Water Resources approach ignores the stochastic nature of sented a summary of first-order desalination
Yield Model (WRYM) and Water Resources the conditions of the receiving system. To costs derived from literature. Based on their
Planning Model (WRPM) respectively in address these concerns, Van Niekerk and Du costs, a 100 Mℓ/day seawater desalination
order to simulate the inflows and demands Plessis (2013a:543) propose a comprehensive plant would cost approximately R9.84/m3.
on the system and plot storage trajectories approach in which the receiving water Similarly, Wittholz et al (2008) collated a
of the coming year. These models (WRYM basin and the transfer scheme are modelled database of over 300 seawater desalination
and WRPM) are run annually in November stochastically as an integrated system in the plants and derived an equation for estimat-
in order to determine whether the dams are WRPM. Taking this concept further, Van ing capital costs for seawater reverse osmosis
full enough to meet the projected summer Niekerk and Du Plessis (2013b:551) postulate desalination plants based on the plant
12 Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017
regardless of the conditions in the rest of
Capital costs for existing large seawater RO desalination plants
100 000 the supply system.
■■ Scenario C: Desalination plant used as
90 000
a base load supply, but only if the major
80 000
dams are not spilling.
Capital cost (R/m3/day)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017 13
Short-term stochastic analyses were
Growth in water demands in the WRPM
also performed in the WRYM in order to 1 000
create short-term yield curves for use in the
WRPM. For short-term analyses, Basson et 900
al (1994:34) suggest that at least five times
800
14 Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017
consumption, chemical costs, maintenance
Increase in historic firm yield for different storage trigger levels
180 costs and membrane lifespan.
Increase in historic firm yield (million m3/annum)
100
PRESENTATION AND
y = 47.038ln(x) + 106.17
80 R 2 = 0.9981
DISCUSSION OF RESULTS
60
System yield
40 y = 25.023ln(x) + 52.378
R 2 = 0.9789 Base scenario
20 For Scenario A (the base scenario with
0
no desalination plant) the historic firm
0 10 20 30 40 50 60 70 80 90 100 yield of the system was calculated as
Desalination trigger level (percentage of total system storage) 530 million m3/a. Based on the stochastic
450 Mℓ/day capacity 300 Mℓ/day capacity 150 Mℓ/day capacity analyses, this corresponds to an assurance
of supply of approximately 70 percent, or
Figure 4 I ncrease in historic firm yield versus reservoir trigger level 1 in 215 years. The 1 in 50, 1 in 100 and 1 in
200 year yields of the system were calculated
as 580 million m3/a, 553 million m3/a and
Increase in historic firm yield for different storage trigger levels
180 532 million m3/a respectively. The results for
Increase in 1 in 50 year yield (million m3/annum)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017 15
firm yield in million m3/a (∆HFY) of the
Annual supply from a 150 Mℓ/day desalination plant as a percentage of capacity
WCWSS for any desalination plant capac- 100
16 Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017
median, decreasing to zero by the end of the
Annual supply from desalination plant as a percentage of capacity based on traditional approach
100 analysis period (2028), when even the wetter
Annual supply from desalination plant as a percentage of capacity
400
Planning for future interventions
2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034
Year Traditional approach
1 in 50 year yield with 450 Mℓ/day desalination plant Projected demands The typical approach that would be followed
1 in 50 year yield with 300 Mℓ/day desalination plant 1 in 50 year current base yield in determining when a future intervention is
1 in 50 year yield with 150 Mℓ/day desalination plant required in a water supply system would be a
water balance of system demands and supply.
Figure 9 P
rojected demand and supply of WCWSS with and without a seawater desalination plant The water demands that were projected as
part of this study, based on the recent work
to 100 percent by 2015. Lowering the trig- Stochastic variability in supply by Aurecon (presented in Figure 2), were
ger level (Scenario D), lowers the output The results presented in Figure 6 are based on plotted along with the calculated 1 in 50 year
from the seawater desalination plant as a median values of the 401 stochastic sequences base yield of 580 million m3/a (Scenario A)
percentage of its capacity. For the lowest analysed, and were selected as representa- and the 1 in 50 year yields with a seawater
trigger levels of 45 percent and 15 percent, tive values for calculating URVs. In order to desalination plant as derived from the
the seawater desalination plant would not illustrate the possible stochastic variability in WRYM analysis (Scenario B), as shown in
be operational for the entire analysis period. supply from the desalination plant, the 5th and Figure 9. Based on this approach, a 150 Mℓ/
Similar plots prepared for 300 Mℓ/day and 95th percentile annual values were plotted for day seawater desalination plant would meet
450 Mℓ/day plants show that, as the seawater Scenario C and for Scenario D with a 70 per- the system demands until 2017, a 300 Mℓ/
desalination plant capacity increases, the cent trigger level, as shown in Figure 7. day plant would meet the demands until
supply from the plant as a percentage of its For Scenario C the maximum stochastic 2021 and a 450 Mℓ/day plant would meet the
capacity decreases. range varies between -28% and +9% from the requirements until 2024.
Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017 17
Sub-system curtailment – Ex+BRD+Sup – Decision month (2)
5.0
4.8
4.6
4.4
4.2
4.0 1 in 200 year curtailment level
3.8 1 in 100 year curtailment level
3.6
3.4
3.2
Curtailment level
3.0
2.8
2.6
2.4
2.2
2.0
1.8
1.6
1.4
1.2
1.0
0.8
0.6 1 in 20 year curtailment level
0.4
0.2
0
2014 2026
2013/12
2014/12
2015/12
2016/12
2017/12
2018/12
2019/12
2020/11
2021/11
2022/11
2023/11
2024/11
2025/11
2026/11
2027/11
2028/11
2029/11
2030/11
2031/11
2032/11
Year
Figure 10 S ystem curtailment for base scenario with no seawater desalination plant (Scenario A)
Table 2 Level of restrictions used in WRPM analyses Figure 10 shows a box-and-whisker plot
of the subsystem curtailment for the base
Restricted water demand as a
Acceptable frequency percentage of normal demand scenario (Scenario A) from 2013 to 2032 as
Level of curtailment
of restrictions derived from the WRPM analysis. The criti-
Domestic Agricultural
cal lines or whiskers which correspond to 1
0 1 in 10 years 100% 100% in 20 year, 1 in 100 year and 1 in 200 year
curtailment levels are labelled.
1 1 in 20 years 93% 75%
Curtailment Level 1 would be reached
2 1 in 100 years 85% 50% (approximately) at a frequency of 1 in 20
years by 2018. Curtailment Level 2 would
3 1 in 200 years 71% 20%
be reached at a frequency of 1 in 100 years
by 2016, and curtailment Level 3 would be
Table 3 Year at which curtailment level would be reached for all scenarios reached at an assurance of 1 in 200 years by
2016. These critical points are marked with
1 in 20 1 in 100 1 in 200 1 in 20 1 in 100 1 in 200 1 in 20 1 in 100 1 in 200
year year year year year year year year year circles. Considering these three trigger years,
Scenario
the earliest that a new water supply interven-
150 Mℓ/day plant 300 Mℓ/day plant 450 Mℓ/day plant
tion would be required for the WCWSS in
B 2021 2019 2019 2024 2021 2021 2027 2025 2023 order to ensure that the frequency of curtail-
C 2021 2019 2019 2024 2021 2021 2027 2025 2023 ments stays within acceptable limits would
be 2016.
D (90%) 2021 2019 2019 2027 2021 2022 2027 2024 2023
D (70%) 2021 2018 2019 2023 2021 2019 2027 2023 2023 Seawater desalination plant
D (45%) 2020 2017 2016 2020 2018 2018 2021 2018 2018
scenarios in the WRPM
Plots similar to Figure 10, showing curtail-
D (15%) 2019 2017 2016 2020 2018 2018 2020 2018 2018 ment levels, were extracted from the WRPM
No desalination plant for the various seawater desalination operat-
ing scenarios and capacities. A summary of
A 2018 2016 2016 2018 2016 2016 2018 2016 2016
the critical points at which the acceptable
frequency of curtailments are exceeded are
Base scenario using the WRPM WRPM analyses. As shown in Table 2, Level provided in Table 3. The earliest dates at
In the WCWSS analysis in the WRPM and 1 curtailments cannot be applied more than which an intervention is required in each
part of the recent study on the development once in every 20 years, Level 2 curtailments case are highlighted in bold.
of integrated annual and real time operating no more than once in every 100 years and Considering Scenario B, the addition
rules for the WCWSS, revised water restric- Level 3 curtailments no more than once of a 150 Mℓ/day plant to the system would
tion levels were developed. The scenario in every 200 years. Stricter curtailments delay the date at which a new intervention is
which Aurecon found to be the most realistic are applied to agricultural demands than required to 2019. A plant capacity of 300 Mℓ/
is provided in Table 2, and was used in the domestic demands. day would provide a further two years to
18 Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017
Table 4 U
RVs for all scenarios and seawater desalination plant capacities derived from WRPM analyses
150 Mℓ/day plant 300 Mℓ/day plant 450 Mℓ/day plant
Scenario
5th 50 th 95th 5th 50 th 95th 5th 50 th 95th
percentile percentile percentile percentile percentile percentile percentile percentile percentile
D (90%) R10.96 R12.21 R14.56 R10.38 R11.71 R13.48 R9.83 R11.11 R12.47
D (70%) R11.16 R15.49 R22.77 R10.69 R14.79 R19.90 R10.33 R13.71 R17.71
D (45%) R37.06 R99.00* R99.00* R28.43 R99.00* R99.00* R24.22 R99.00* R99.00*
D (15%) R54.68 R99.00* R99.00* R36.71 R99.00* R99.00* R31.35 R99.00* R99.00*
2021, and a capacity of 450 Mℓ/day, an addi- For Scenario D the plant would have to sup- scenarios and with other possible interven-
tional two years to 2023. For Scenario C and ply up to 1 500 Mℓ/day in 2023, increasing to tions. The 5th and 95th percentile URVs are
Scenario D with a 90 percent trigger level, 2 100 Mℓ/day by 2033. also shown in order to provide an indication
the results are identical to those of Scenario The problem with adopting this approach of the possible stochastic range of the costs.
B, suggesting that the decision regarding is that it does not allow for any failures over Considering the median (50th percentile)
whether to operate the seawater desalination the analysis period, i.e. for Scenario D with a values in Table 4, it would appear that, for
plant 100 percent of the time or only when 70 percent trigger level, a 1 500 Mℓ/day plant all capacities, the URV increases as the trig-
the dams are not spilling would not be influ- would meet the demands until 2023 with a ger level decreases. It therefore seems that
enced by curtailment requirements. 100 percent assurance of supply. This differs operating the seawater desalination plant as
As the trigger levels decrease, the benefit from the normal risk allowance that would an emergency type scheme, as exemplified by
of the seawater desalination plant in terms of be applied in planning for a water supply the 45 percent and 15 percent trigger levels,
delaying the requirement for a new scheme system in South Africa. would be expensive. Although the annual
is reduced. For the lowest trigger levels the operating costs would be much lower for an
seawater desalination plant provides almost Comparison of costs emergency scheme, the initial capital cost
no benefit in terms of reducing curtailments, would be the same regardless of the actual
suggesting that there is very little benefit in Traditional approach to calculating URVs seawater desalination plant output. The
using the desalination plant as an emergency The research of Van Niekerk and Du Plessis results suggest that this initial capital cost
supply source. (2013a:551) showed that the traditional outweighs any reduction in operating costs
approach to calculating URVs uses the water when the seawater desalination plant output
Unlimited desalination plant capacity supply from a scheme calculated based on is reduced.
The results are derived from assumed sea- a water balance between annual demands For a trigger level of 70 percent, the URV
water desalination plant capacities of 150, and a 1 in 50 year system yield. As a start- for a 150 Mℓ/day plant is much more reason-
300 and 450 Mℓ/day. The reverse of this ing point, this traditional approach was able at R15.49/m3, decreasing to R12.21/m3
approach would be to ask: “What desalina- applied for calculating the URV of the for a 90 percent trigger level. For Scenario B
tion plant capacity is required in order to seawater desalination plant. For a discount and Scenario C the desalination plant would
meet future demands for the next 10 or 20 rate of 8 percent, the traditional approach be fully operational once constructed, giving
years?” Based on the traditional approach, yielded URVs of R11.35/m3 for a 150 Mℓ/ a URV of R10.96/m3. Based on these values
a 400 Mℓ/day seawater desalination plant day seawater desalination plant, R11.46/m3 it would appear that the lowest possible
would meet the system requirements up to for a 300 Mℓ/day seawater desalination plant URV occurs when the desalination plant is
2023, and a 1 000 Mℓ/day plant would meet and R11.48/m3 for a 450 Mℓ/day seawater 100 percent operational.
the requirements up to 2033. The WRPM desalination plant. Comparing the three capacities that were
results confirm that, with a 450 Mℓ/day analysed, the URVs decrease slightly with
desalination plant, curtailments would be WRPM-based approach to an increase in seawater desalination plant
kept within acceptable limits until 2023. calculating URVs capacity. This suggests that it would be more
However, from the WRPM results it is not In the WRPM-based approach, as applied beneficial from an economic perspective to
possible to confirm what capacity is required for this research, capital and operating costs construct a larger seawater desalination plant
to meet the demands beyond this point. were calculated for each scenario using the now, rather than phasing it in smaller lanes.
The WRPM analyses were repeated for annual supply from the seawater desalination Comparing the results from the tra-
Scenarios C and D (with a 70 percent trigger plant as derived from the WRPM analyses. ditional approach to the WRPM-based
level only) with a seawater desalination plant Using these costs and the associated sea- approach, the results for a 150 Mℓ/day plant
of unlimited capacity. The monthly supply water desalination plant supply, URVs were are actually similar to Scenario B/C. This
from the seawater desalination plant over calculated for each scenario and seawater suggests that, although the annual sup-
the analysis period was determined, based desalination plant capacity as presented in ply from the seawater desalination plant
on the median values of the 401 stochastic Table 4. The values highlighted in bold are differs vastly between the traditional and
sequences. The maximum monthly supply the median values (50th percentile) which WRPM approaches in the initial years,
for Scenario C would be 2 100 Mℓ/day in were considered to be the most reasonable both approaches suggest that the seawater
2023, increasing to 2 900 Mℓ/day in 2033. for the purposes of comparison between the desalination plant would be 100 percent
Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017 19
operational in the later years, meaning trigger level. Generic equations were considered, and the model was applied to
that the calculated URVs are similar. The developed which could be used to esti- the specific case of the WCWSS, hence
traditional approach, however, suggests an mate the increase in historic firm yield the results are mostly case-specific. As
increase in the URV with an increase in and 1 in 50 year yield of the WCWSS for part of further research, it would be
capacity, which differs from the WRPM any seawater desalination plant capacity worthwhile to repeat the methodology
approach. For the lower trigger level sce- and reservoir trigger level. and analysis procedure for other large
narios, the WRPM-based approach has much ■■ The maximum increase in yield occurs water supply schemes in South Africa,
higher URVs than the traditional approach. when the seawater desalination plant is and for other sources such as water reuse.
Considering the 5th and 95th percentile used as a base supply, operational all the ■■ The main limitation of this research is
values, it appears that the possible stochastic time. The increase in yield decreases with that only the cost of the desalination
range increases with a decrease in the trigger a decrease in the reservoir trigger level, scheme was considered in the analysis.
level and with an increase in capacity. Hence, meaning that there is little benefit in As part of future research, it may be
for a fairly predictable scenario in terms of using the seawater desalination plant as worthwhile to consider developing a cost-
seawater desalination plant supply (when an emergency supply source. ing model for the WCWSS as a whole and
it will be operational most of the time), the ■■ With a 150 Mℓ/day desalination plant, attempting to optimise the overall system
stochastic variability in stream flows in curtailment requirements would be cost with the implementation of a desali-
the existing system would have little effect kept within acceptable levels until 2019, nation plant. Under such an approach,
on the URVs and would not be too far off with a 300 Mℓ/day plant until 2021 and reducing the desalination plant output
from URVs calculated using the traditional a with a 450 Mℓ/day plant until 2023, may prove to be more cost-effective.
approach. However, for a less predictable for a desalination plant which is 100 Desalination technology has advanced
operating scenario, using the seawater desali- percent operational. Using the plant as an rapidly in the last few years, and as a
nation plant as an emergency type scheme, emergency supply source would add little result capital and operating costs today
the stochastic variability in the URV would benefit in terms of limiting curtailment are likely to be lower than those estimat-
be more noticeable, and hence the selection requirements. ed using the methodology of Du Plessis et
of an appropriate percentile for reporting on ■■ URVs for the seawater desalination plant al (2006) used in this research. Updating
the costs would become more important. decrease as the percentage of time for of the costing methodology could form
which the seawater desalination plant is part of further research; however, it is
operational increases. This means that expected that adjustments to the costing
CONCLUSIONS the lowest possible cost per cubic metre would not affect the applicability of the
Through the current WCWSS planning of water supplied is when the seawater analysis methodology and relevance of
processes, seawater desalination has been desalination plant is operational 100 per- the conclusions.
earmarked as a potential future supply cent of the time (R10.96/m3 for a 150 Mℓ/
source for the area. In order to maximise the day plant).
benefits and minimise the costs of a seawater ■■ It would also appear that the URVs NOTES
desalination plant, it needs to be considered decrease with an increase in seawater 1. The following exchange rates were issued in the
as an integral part of the current system. In desalination plant capacity, meaning costing analyses and comparison of known costs
order to undertake integrated system analy- that constructing a larger seawater (South African Reserve Bank 2014):
sis, the WRYM and WRPM were selected desalination plant upfront may be more ■ 1 Australian Dollar (AUS$) is equivalent to R9.80
as the most appropriate tools. Short-term cost-effective. However, it would have to ■ 1 United States Dollar (US$) is equivalent to
and long-term analyses were completed for be constructed in small enough lanes to R10.70
a variety of possible seawater desalination enable restriction of the output when the ■ 1 Euro (€) is equivalent to R14.70
plant operating scenarios and capacities in total supply is not required, and cogni- 2. DWS (Department of Water and Sanitation) was
order to determine the increase in system sance would have to be taken of other rel- previously the Department of Water Affairs and
yield and the annual supply from the sea- evant factors, such as availability of other Forestry (prior to 2009) and subsequently the
water desalination plant. First-order capital schemes already in place and growth in Department of Water Affairs (from 2009 to 2014).
and operating costs were estimated using the water demands. In this paper, the department is referred to by
South African methodology of Du Plessis et ■■ The lower the reservoir trigger level, the its current designation (DWS), apart from in the
al (2006). Combined with the annual supply larger the stochastic variation in the sup- references, where the name at the time of publication
values from the WRPM, these costs were ply from the seawater desalination plant, of the referenced document is used.
used to calculate and compare the URVs of and hence the larger the variation in the
the desalinated water. URVs. Hence, for a seawater desalination
The following conclusions can be drawn plant operational as a base supply source, REFERENCES
from the results of the modelling and cost undertaking stochastic modelling to Basson, M S, Allen, R B, Pegram, G G S & Van Rooyen,
analyses: calculate URVs is less important than for G A 1994. Probabilistic Management of Water
■■ It is possible to model a desalination plant an emergency supply source. Resource and Hydropower Systems. Littleton, CO:
as an integral part of a surface water sup- Water Resources Publications.
ply system. With the appropriate costing Department of Water Affairs 2007. Western Cape Water
tools, a similar analysis approach could LIMITATIONS AND Supply System Reconciliation Strategy. Cape Town:
be applied to other non-conventional FURTHER RESEARCH Department of Water Affairs, South Africa.
resources, such as water reuse. In concluding, the following limitations and Department of Water Affairs 2010. Integrated Water
■■ The increase in system yield as a result areas for further research should be noted: Resource Planning for South Africa: A Situation
of the desalination plant appears to be ■■ Of the available non-conventional supply Analysis 2010. Pretoria: Department of Water
logarithmically related to the reservoir sources, only seawater desalination was Affairs, South Africa.
20 Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017
Department of Water Affairs 2011. Western Cape Water Ghaffour, N, Missimer, T M & Amy, G I 2013. Shand, M & Sparks, A 2004. Optimisation of system
Supply System Reconciliation Strategy, Progress Technical review of the economics of water operating rules for the Western Cape Water Supply
Report of the Strategy Steering Committee. Cape desalination: Current and future challenges for System. s.l.:s.n.
Town: Department of Water Affairs, South Africa. better water supply sustainability. Desalination, 309: South African Reserve Bank 2014. Selected
Department of Water Affairs 2013a. Support to the 197–207. historical rates. Available at: https://www.
Continuation of the Water Reconciliation Strategy Hoffman, J J & Du Plessis, J A 2008. Water demand resbank.co.za/REsearch/Rates/Pages/
for the Western Cape Water Supply System: Status management: An economic viable option. WISA, SelectedHistoricalExchangeAndInterestRates.aspx
Report October 2013. Cape Town: Department of 147–163. [accessed on 11 September 2014].
Water Affairs, South Africa. Karagiannis, I C & Soldatos, P G 2008. Water Van Niekerk, P H & Du Plessis, J A 2013a. Hydrologic-
Department of Water Affairs 2013b. National Water desalination cost literature: Review and assessment. economic appraisal of lifecycle costs of inter-basin
Resource Strategy: Water for an Equitable and Desalination, 223: 448–456. water transfer projects. Water SA, 39(4): 539–548.
Sustainable Future. Pretoria: Department of Water Mallory, S J L, Ballim, F, Pashkin, J & Ntuli, C 2013. Van Niekerk, P H & Du Plessis, J A 2013b. Unit
Affairs, South Africa. Introducing desalination plants into system Reference Value: Application in appraising inter-
Department of Water Affairs and Forestry 2008. operating rules for bulk water supply systems. basin water transfer projects. Water SA, 39(4):
Water for Growth and Development in South Africa. Unpublished paper delivered at the 16th South 549–554.
Pretoria: Department of Water Affairs and Forestry, African National Hydrology Symposium, 1 October, Wittholz, M K, O’Neill, B K, Colby, C B & Lewis, D
South Africa. Pretoria. 2008. Estimating the cost of desalination plants
Du Plessis, J A, Burger, A J, Swartz, C D & Musee, Onishi, N 2010. Arid Australia sips seawater, but using a cost database. Desalination, 229(2008):
N 2006. A Desalination Guide for South African at a cost. Available at: http://www.nytimes. 10–20.
Municipal Engineers. Pretoria: Department of Water com/2010/07/11/world/asia/11water.html?_r=0
Affairs, South Africa. [accessed on 23 March 2012].
Journal of the South African Institution of Civil Engineering • Volume 59 Number 1 March 2017 21