CHECK LIST FOR FIRE HYDRANT

LOCATION: Zone Ref : Contract No:

GRID REFERENCE: SYSTEM SERVICE:

DRAWING NO.:

REFERENCE IRE NO.:


DATE:

REFERENCE ITP NO.: Q11017-0100D-LPS-STA-PK2-QMS-ITP-00040

No. Activities Approved Remarks

A. Pre installation checks YES NO


1 Installation Checks As per ITP & QCS 2014 S2P2 clause 2.1.4
2 Checks drawings are approved
3 Check the material are approved and have proper MIR
B Installation Inspection of Fire Hydrant
1 Works has been carried out as per approved drawing
2 Check & Ensure the depth of the pit is as per the QCDD
3 Check any defects in hydrants
4 Final Paint completed
Ensure the installed underground piping size and level as per the
5
QCDD approved drawing.
6 Ensure the duck foot is fixed properly in the concrete bottom slab.
7 Check the tightness of the hydrant
Check the direction of valve opening is correctly aligned as per the
8
approved drawing.
Check for leakage at the flanges, operating nut, nozzles and nozzle
9
caps
If hydrant is equipped with safety chains, ensure the chains are
10
loose and do not bind on the cap
11 check the Surface box covers shall be marked clearly.
12 Testing is completed and recorded.
13 Proper housekeeping done

REMARKS:………………………………………………………………………………………
……………………………………………………………………………..………………………
ALL ABOVE ACTIVITES CHECKED, VERIFIED AND READY FOR INSPECTION

ORGANIZATION L&P JV GSIC JV KEO


NAME
SIGNATURE
DATE
Doc No: Q11017-0100D-LPS-GEN-PKS-QMS-FRM-00039

You might also like