1. SCOPE
a. This section includes materials and installation of fire fighting system, and related works
required under the Contract.
b. Reference
2. GENERAL
a. Fire fighting system shall consist of fire extinguishers as shown on the Drawings.
b. All accessories or attachments of above facilities necessary to facilitate the system shall be
included and provided by the Contractor even though not specifically shown on the Drawings
or not specified herein.
d. Submittals.
Refer to SECTION 1H, SUBMITTALS and SECTION 4E, GENERAL MECHANICAL
WORK.
- Fire Extinguishers
4. INSTALLATION
Fire extinguishers shall be installed according to the following schedule. Appropriate type of fixing
and fastening devices to prevent installed fire extinguishers from falling down shall be provided in
a manner approved by the Engineer.
5. FINISHES
Painting of pipelines including fittings and accessories and all metal surfaces not factory-painted
shall be applied in accordance with SECTION 3H, FINISHES.
4G Sheet 1 of 2