Professional Documents
Culture Documents
6149061
6149061
SAN/RA 50239-SDGE-0001
a
HEBER GEOTHERMAL BINARY DEMONSTRATION PROJECT
This report was prepared a s an account of work performed by San Diego Gas
& Electric; sponsored by t h e E l e c t r i c Power Research I n s t i t u t e , t h e
Imperial I r r i g a t i o n D i s t r i c t , t h e California Department of Water
Resourcesc and t h e Southern California Edison Company, h e r e i n a f t e r c a l l e d
Sponsors; and supported by t h e U. S. Department of Energy, an agency of
t h e United S t a t e s Government. Neither San Diego Gas & E l e c t r i c , nor t h e
Sponsors, nor t h e United S t a t e s Government nor any agency thereof, nor
any of t h e i r employees o r subcontractors, makes any warranty, express or
implied, o r assumes any l e g a l l i a b i l i t y o r r e s p o n s i b i l i t y f o r t h e
accuracy, completeness, or usefulness of any information, apparatus,
w product, o r process disclosed, o r represents t h a t i t s use would not
i n f r i n g e p r i v a t e l y owned r i g h t s . Reference herein t o any s p e c i f i c
commercial product, process, o r service by trade name, trademark,
manufacturer, o r otherwise, does not necessarily c o n s t i t u t e o r imply i t s
endorsement o r recommendation by San Diego Gas & E l e c t r i c , o r t h e
Sponsors, o r t h e United S t a t e s Government o r any agency thereof. The
Y views and opinions of authors expressed herein do not necessarily s t a t e
o r r e f l e c t those of San Diego Gas & E l e c t r i c , o r t h e Sponsors, o r t h e
United S t a t e s Government o r any agency thereof.
TABLE OF CONTENTS
r, PAGE
SUMMARY 1
TECHNICAL PROGRESS 3
* INTRODUCTION 3
II *
FIGURE 5 - ERTEC (;EOTECfINICAL INVESTIGATION
OF FIELD ACTIVITY 26
I
FIGURE 6 - FOR
BRINE REQUIREME FOR THE PLANT
THE FLOATING COOL ODE OF OPERATION 27
Y
FIGURE 7 - OF
SIMPLIFIED PROCESS-FL AGRAM
THE BINARY CONVERSION SYTEM 28
3
o a
SUMMARY
W
Recognizing the desirability of demonstrating the operation of the binary
cycle process for commercial-scale electric production, San Diego Gas &
Electric Company (SDGSrE) has formed a consortium of participant utilities
to carry out the Heber Geothermal Binary Demonstration Project.
Additional cost-sharing support is being provided by the Electric Power
Research Institute (EPRI) and the United States Department of Energy
(DOE).
The purpose of the Heber Binary Project is to design, construct, and
operate a nominal 65 Mwe (gross) commercial-scale, binary cycle power
& plant and to demonstrate the technical and economic feasibility of
geothermal power generation. The Project will be the first
commercial-scale hydrothermal generating facility in the United States
utilizing liquid-dominated resources and the first comercial-scale plant
in the world using the binary energy conversion process. It is expected
that information developed by this demonstration project will be
Y applicable to a wide range of moderate-temperature, low-salinity
hydrothermal reservoirs. Geothermal generation from the Project offers
the possibility of displacing 525,000 barrels of oil per year that would
otherwise have to be burned in Southern California. Figure 1 shows an
artist’s rendering of the Project and Figure 2 shows the location.
Y This quarterly report describes progress for the period beginning with
the commencement of the DOE/SDG&E Cooperative Agreement on September 15,
1980, and extending through March 31, 1981.
Funding agreements for the Project were executed with DOE, EPRI, and a
consortium of utilities (DWR, IID, and SCE), with SDGsJE assuming the
0 leadership/management role (See Figure 3 ) .
Y -1-
testimony has been given to describe the merits of the Project, and all
other Project efforts are proceeding based on an assumption of retained
Y federal funding.
3
0
-2-
TECHNICAL PROGRESS
r"
0
WBS 1.3 - POWER PLANT DEMONSTRATION
This t a s k c o n s i s t s of t h e work by SDG&E t o operate t h e power p l a n t f o r a
two-year period t o achieve t h e basic objectives of t h e Project. The t a s k
includes s e r v i c e s , r e p a i r s , c i l i t i e s , . o v e r h a u l , cleaning, consmables,
t e s t i n g , spare p a r t s , and t ry t o operate t h e p l a n t i n a
s a f e and r e l i a b l e manner.
u
WBS 1 . 4 - DATA ACQUISITION AND DISSEHINATION
-3-
The WBS will serve several functions. It divides the work into discrete '
WBS 1.1
ID P R O D U C T I O N T I O N s m
c , ,
3
OBJECTIVE :
This WBS element will be performed and funded entirely by the heat
supplier. It will include work to design, build, and test production and
injection systems necessary to deliver fluid from the reservoir to the
c3 power plant and, after use, return the fluid into the reservoir.
STATUS :
3 Negotiations with Chevron Resources Company for the heat sales
contract prohressed to the point where the final position of both
parties was established. Ssn Diego decided not to execute the
agreement, in view of the uncertainty of continued federal funding
for the Project. SDG&E has initiated discussions with Union Oil for
the heat sales agreement, with the objective of obtaining more
w favorable terms and conditions.
U Work on this WBS element will commence with the execution of the
heat sales contract.
I
u3
cri
r,
0 -5-
9 .
ms 1.2
R PLANT DESIGN AND CONSTRUCTIOH
3
The objective of this WBS element is to obtain the necessary permits and
provide environmental studies and monitoring to facilitate plant design
and ensure compliance with government regulations for plant construction
u3 and operation.
STATUS :
Prior to the signing of the DOE Cooperative Agreement, the following
3 items were accomplished.
Three permits were obtained from the County of Imperial.
1. Zone change for Geothermal (G) Overlay Zone of 7,320 acres on
us the Heber reservoir.
Y
u 2. Heber Geothermal Project Final Master Environmental Impact
Report 11213-79, December 1979.
-6-
Jrs
..~ . . .
t
*.
I
1 After the execution of the DOE Cooperative Agreement, the following items
were accomplished.
-7-
4 .
19
I
3
i
(3
3 -8-
-_-BS 1 . 2 . 2
W - POWER PLANT ENGINEERING, DESIGN, AND PROCUREMENT
3
OBJECTIVE :
STATUS :
d
Three contracts were issued:
a
-
Fugro, Inc. The geotechnical services contract with Fugro, Inc.
was approved by DOE in October 1980 and executed by Fugro in
November 1980.
3
Fluor Power Services, Inc. -
The agreement with Fluor Power Services
(FPS) for engineering and procurement services was executed on
December 29, 1980. DOE approved the contract on December 23, 1980.
An initial meeting was held on January 13, 1981, with FPS, SDG&E,
and DOE to review the schedule covering activities from
cle, January-March 1981.
-
Pickard, Lowe and Garrick The contract with Pickard, Lowe and
Garrick (PUG) for the Availability Enhancement Program, which will
assess and improve the availability of the power plant, was executed
on March 26, 1981, and the work is in progress. SDG&E will request
r3 DOE ratification.
3
Fugro's work covered two areas: a soils investigation to determine
the load-bearing capability of the soil; and work to update the
seismic criteria developed for the former Heber Project, using data
from the October 1979 Imperial Valley earthquake.
3 -9-
0 or Power Services: Inc,
W
Review and updating of the EPRI ER-1099 document was essentially
completed with issuance of the Project Design Guide. Significant
changes from EPRI ER-1099 were as follows:
-11-
Work in progress includes preparation of schedules and budgets for
the following Work Packaes :
3
DO01 - DO02 Brine and Hydrocarbon System Engineering
EO01 - EO10 Auxiliary System Engineering
FOOl
GOO1 -- FOOZ
GOO3
Site/Plot Plan and Model Development
Civil/Structural/Architectural Engineering
and Design
9 JOOl - 5003 Turbine-Generator Engineering
KO01 - KO06 Piping Engineering and Design
LOO1 - LO04 Electrical System Engineering and Design
MOO1 - MOO4 Control Systems (I&C) Engineering and Design
NO0 1 Insulation and Coatings Engineering
PO01 - PO05 Procurement
ru QOOl - 4006 Omnibus Activities
ROO1 - ROO3 Switchyard Engineering and Design
I
I TO02 Long Term Makeup Water Treatment
Evaluation of Floating Cooling Operation
The Project will incorporate a floating cooling cycle instead of the
0 originally planned fixed cooling cycle, since it will permit the
optimization of yearly power output by taking advantage of varia-
tions in wet bulb temperatures. In contrast, a fixed cooling cycle
operates at a constant condensing temperature and delivers constant
power during the time that the design wet bulb temperature is not
0
exceeded. By incorporating the floating cooling concept, the plant
average efficiency is improved (with a corresponding reduction in
brine requirements) while maintaining an average gross power output
of 65 Mw. Figure 6 depicts the brine requirements for the floating
cooling mode of operawon.
G -12-
Data supplied by turbine vendors were used to determine the power
output for the floating cooling mode of operation. Brine
U
requirements and cycle efficiencies were determined, the gross and
net power output as a function of seasonal wet bulb variation was
determined, and delta capital investment for the turbine-generator
configurations was estimated.
Turbine-Generator Engineering
Planning and initial efforts to prepare this key specification were
started by Fluor's mechanical discipline. The technical
specification was issued for SDG&E review in April.
Power Cycle Conceptual Design
Computer runs were made to generate thermodynamic and physical
property data for the 90 mole percent isobutane-10 mole percent
isopentane mixture. Preliminary heat and material balances and
process flow diagrams for the overall power cycle defined in EPRI
ER-1099 were started. Figure 7 is a simplified process-flow diagram
of the binary conversion system. Applicable results of this work
3
were incorporated in the Project Design Guide.
Preliminary power cycle equipment selection parameters were
established. Conceptual design of the auxiliary systems was
started.
V
Seismic Design Critieria
I For the Project, it has been established that all structures and
equipment vital to power generation and safety will be designed for
a minimum seismic force of 0.3W in one direction plus 0.1W in the
u two other perpendicular directions, where W denotes the combined
dead loads and live loads during operation.
Electrical System Engineering and Design
The original 1978 one-line electrical diagram in the EPRI baseline
report is being re-evaluated in light of the increasing energy
0 costs. It may be possible to reduce energy losses by reconfiguring
the one-line diagram. FPS has completed preliminary calculations
and evaluations. It appears that constraints as to allowable
voltage dip during starting of large motors will largely determine
the final design.
v
Work also was under en to provide preliminary electrical system
load data to S D W in preparation for meetings with IID regarding
. offsite power system requirements.
Y
-13-
I
STATUS :
A Construction Manager will be hired to review engineering design.
He will be responsible for dividing construction work into
manageable packages and issuing invitations for competitive bidding
on lump-sum, fixed-price contracts. He will evaluate the bids
received and make recommendations based on his review of them. The
Construction Manager also will monitor subcontractors' work, provide
reports on subcontractor progress and cash flow to aid in the
budgeting process, inspect the subcontractors' work for compliance
with engineers drawings, and turn over finished construction to the
San Diego start-up team.
Y
A scope of work document for the Construction Manager was prepared.
Potential contractors were interviewed, including Fluor, Parsons,
Stone & Webster, Gilbert/Commonwealth, United Engineers and
Constructors, Dravo, Lummus, and Bechtel. The RFP was issued in
April 1981.
8 A study was performed which indicated that the existing IID
transmission system will be adequate to handle the construction
power requirements. IID has furnished preliminary design
information concerning transmission line upgrading, construction and
start-up power, and operational requirements.
WBS 1 . 2 . 4 - POWER PLANT START-UP
OBJECTIVE :
The objective of t h i s WBS element i s t o s t a r t - u p , check-out, and t e s t t h e
completed power p l a n t . This e f f o r t s h a l l include t h e necessary personnel
t r a i n i n g and t h e correction of equipment o r system problem areas
i d e n t i f i e d during p l a n t start-up.
STATUS :
A s t a r t - u p schedule has been developed, with t e n t a t i v e dates f o r
s t a r t and completion of p l a n t systems check-out and start-up. A
copy of t h i s schedule has been s e n t t o FPS f o r inclusion i n t h e
Project Master Schedule.
9
I
I
1
0
1
I
,I)
ri
-16-
Y
I
.
II
I
I
~
1
WBS 1.2.5 - PROJECT MANAGEMENT
OBJECTIVE :
STATUS:
The DOE Cooperative Agreement was executed by SDGsrE on September 26
and by DOE on September 27, 1980. A signing ceremony was held
0 October 8, 1980, in El Centro, California, to formalize the
Agreement.
The Participation Agreement between SDG&E and the Electric Power
Research Institute (EPRI) was executed by SDG&E on October 3, 1980,
and by EPRI on October 21, 1980.
Y
The Participation Agreement among SDG&E, Imperial Irrigation
District, California Department of Water Resources, and Southern
California Edison was executed by all parties in early December 1980
and was retroactive to October 1, 1980.
Id -17-
I
I
I
-.
I
1 meters, and such a grant would help reduce SDG&E's financial
1 exposure. Hearings on AB 51 began in early 1981. The bill is being
actively supported by the California Public Utilities Commission,
WBS 1.4
I DIS-
w
STATUS:
rp
The scope of work document for the data management contract was put
in final form, and the following firms were selected to submit bids
for the contract: WESTEC Services, Woodward-Cycle Consultants,
Science Applications, Stanford Research Institute, and PFR
r)
Engineering Systems. Preliminary evaluation criteria were developed
in November 1980. The first draft of the Invitation to Bid was
prepared, however, solicitation has been delayed because of the
uncertainity of conti federal funding.
4B
\
0
-3
3 -21-
c c c c t c CE c t I
ARTIST’S RENDERING
I
to
to
I
c c d c t c t c e 4 0
FUNDING OWNERSHIP
PARTICIPANT PERCENT t NTEREST
100.0% 100.0%
*SCE is a Participating Contributor and may assume a prorata ownership share prior to March 31,1982
6
FIGURE 4
HEBER BINARY PROJECT
WORK BREAKDOWN STRUCTURE
nGeothermal
Binary
Demonstration
-- I
I
PawerPlantDesign
Production & & Construction
Injection Systems (SDG&E & Fhor)
1.2
I
I
Power Plant
,
Power Plant
1
Project
I I
Environmental Construction Management
Studies & Permits (SDG&E & Fluor) (SDG&E)
(SDG&E) 1.2.1 1.2.3 . 1.2.5
I -i I 1
Data Collection Acquisition Anal.
I
Public Interface
Demonstration Operation & Project
Team (SDG&E) Maintenance Management System & Dissemination (SDGIE)
1.3.1 (SDG&E) (SDGW 1.3.3 (Subcontractor) (Subcontractor)
f.4.1 i
1.4.2 1.4.3
W PLATE LOAD TEST @ BORING AND CPT
150 300 FEET
FIGURE 6
BRINE REQUIREMEIUTS FOR THE PLANT
HE FLOATING COOLING MODE OF OPERATION
9.0 -
NOES:
- - - - - - - - -
8.86 65 MW (GROSS) CONSTANT
@ 80°F WET BULB TEMPERATURE
- START OF RUN
CONDITIONS
- AXIAL TURBINE
7.95
II
c c c c L c t
*
FlGURE 7
I
h3
00
I
CoMmG WATER
HYDROCARBON
COWMIPSATE pullllps