nish Jan 8, '18 Jan 15, '18 Jan 22, '18 Jan 29, '18
Mode S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 SURVEY LOKASI / TEMPAT USAHA 8 days Mon 1/8/18 Wed 1/17/18
2 Pembersihan lokasi/tempat Usaha 1 day Mon 1/8/18 Mon 1/8/18
3 Renovasi 2 days Tue 1/9/18 Wed 1/10/18
4 Pengecatan 2 days Thu 1/11/18 Fri 1/12/18
5 Dekorasi Ruangan 3 days Mon 1/15/18 Wed 1/17/18
6 Pembelian Alat‐alat 1 day Thu 1/18/18 Thu 1/18/18
7 Persiapan Pembukaan 10 days Fri 1/19/18 Thu 2/1/18
8 Promosi Media Mosial 5 days Fri 1/19/18 Thu 1/25/18
9 Promosi Dengan Media Cetak 5 days Fri 1/26/18 Thu 2/1/18
10 Grand Opening 1 day Thu 2/1/18 Thu 2/1/18
11 Pembelian bahan Masakan 1 day Thu 2/1/18 Fri 2/2/18
12 Pembukaan Hari Pertama 1 day Thu 2/1/18 Fri 2/2/18