Typical CPM of a One – Storey House

Activities Description Time( weeks) Manpower

1-2 Lot preparation 1 7 A


1-3 Preparation of preliminary materials 2 4 B
2-3 Excavation 1 8 C
3-4 Lay the foundation 4 10 D
4-5 Install the type of floor (slab) 4 15 E
4-6 Framing of walls 8 10 F
5-7 Dummy 0 G
6-7 Roof framing 3 8 H
7-8 Installation of mech. and elec. services 2 5 I
7-9 Installation of doors and windows 4 7 J
8-10 Insulations and ceilings 3 10 K
9-10 Paintings and finishing works 6 5 L
10-11 Installation of appliances and utilities 3 7 M
11-12 Move in 1 5 N

DATA SHEET

(The Network Diagram)


WEEK
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Lot preparation
Preparation of preliminary materials
Excavation
Lay the foundation
Install the type of floor (slab)
Framing of walls
Dummy
Roof framing
Installation of mech and elec services
Installation of doors and windows
Insulations and ceilings
Paintings and finishing works
Installation of appliances and utilities
Move in

GANTT CHART

Note: Dummy Activity (look into page 97) for definition.

Data Sheet (page 129)

Example ito ng Gantt na may dummy. Ang dummy, wala man itong actual works efforts
and do not consume time.