Why Cost and Schedule Overruns On Mega Oil Sands Projects?: Dr. Janaka Ruwanpura and Dr. George Jergeas, P.Eng

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

TECHNICAL A RTICLE PEER REVIEWED

billion international airport was close to


200 percent.
Why Cost and Schedule Overruns Flyvbjerg also quotes and supports
studies regarding the calamitous history of
previous cost overruns of very large projects.
on Mega Oil Sands Projects? The assertion is that too many projects are
completed that should not have been done.
Dr. Janaka Ruwanpura and Dr. George Jergeas, P.Eng He questioned and criticized the credibility
of front-end analyses that are routinely
ABSTRACT: Developing and constructing oil sands mega projects are huge technological, engi- carried out as part of mega project
neering, and construction achievements for Alberta and Canada. Thousands of engineering preparation work. These typically include
and project management professionals and workers are contributing to the current effort with cost-benefit analyses, financial analyses, and
great pride and sense of satisfaction. But recent large capital oil sands construction projects have environmental and social impact
all experienced significant cost and schedule overruns. There are a number of reasons for these
statements He adds that, “mega project
overruns. This article provides a definition of a “mega project”, illustrates the challenges in de-
livering oil sands mega projects, and lists a number of reasons for cost and schedule overruns
development is currently a field where little
can be trusted not even—some would say
KEY WORDS: Cost overrun, mega projects, oil sands, and schedule overruns especially not—numbers produced by
analysts”.
More and more mega projects are built

T
he Alberta oil sands, which many factors [10]. Included are the
despite the poor performance record of
represent one of the world’s largest apparent “management” deficiency in
many projects. According to Flyvbjerg, the
hydrocarbon deposits, are found in managing scope, time, quality, cost,
main causes of the mega project overrun
three regions in northern Alberta, Canada. productivity, tools, scaffold, equipment,
are the inadequate deliberation about risk
These are the Athabasca sands that materials and lack of leadership. While
and a lack of accountability in the project
surround the town of Fort McMurray, the these projects are normally successful from
decision making process.
Peace River sands to the west, and the Cold an engineering, operational and safety
Specifically he lists the following:
Lake sands to the southeast. standpoint, the cost and schedule overruns
According to Alberta government are a cause for concern and the reason for
• Lack of realism in initial cost estimates.
statistics, 1.6 trillion barrels of oil are locked this research work.
• The length and cost of delays are
in the sandy bitumen under the forest and
underestimated.
muskeg. Of that, 175 billion barrels are Cost Overrun: Literature Search
• Contingencies are set too low.
proven reserves that can be recovered using There is no single cause for cost and
• Changes in project specifications and
current technology. Current production in schedule overruns on construction and
designs are not sufficiently taken into
Alberta exceeds 1 million barrels per day. It engineering projects. The Construction
account.
is projected that production will triple to 3 Industry Institute (CII) has identified many
• Changes in exchange rates between
million barrels a day by 2015 [3]. reasons for cost overruns, including but not
currencies are underestimated or
Currently, oil can be extracted from the limited to the following.
ignored.
sands using two commercial methods: strip
• Underestimation of the geological risk.
mining and in situ mining. • front-end planning;
• Quantity and price changes are
Alberta oil sands development projects • design;
undervalued. And,
are mega engineering and construction • procurement;
• Undervalued expropriation costs and
undertakings. Each ranges between $8-10 • start-up and operations;
safety and environmental demands.
billion in capital investment. Each • human resources issues;
• Underestimation of technological
employs thousands of workers, engineers, • organization
innovation with high risk. This is
suppliers, contractors, and support staff. • project processes, and
mainly because of the unproven nature
These oil sands developments are • project control [1].
of new ideas.
facing many challenges including those
associated with environmental impacts, According to Bent Flyvbjerg, many
Cost overruns continue to be a major
water requirements and supply, labor infrastructure mega projects have strikingly
challenge facing governments and
availability and construction productivity, poor performance records in terms of
organizations in the infrastructure and
energy requirements, infrastructure economy, environment and public support
mega projects environment. The latest
constraints and market conditions. It is not [5]. He cited many examples of
examples are the new Wembley Stadium
uncommon for these projects to experience infrastructure mega projects that
and the London Olympic Games in 2012.
cost overruns of up to 100 percent of the experienced major cost overruns, such as
The new Wembley Stadium, which was
original cost estimates, and limited the channel tunnel and the Denver
opened in March 2007, became the
schedule overruns. international airport. The channel tunnel,
costliest arena ever built at US $1.54
A study conducted for the government which was opened in 1994 at a construction
billion. The bill for the London Olympic
of Alberta, Canada found that cost and cost of £4.7 billion, overrun by 80 percent,
Games rose from £2.3 billion to £9.35
schedule overruns on large oil and gas while the cost overrun for Denver’s US $5
billion in less than two years, since the City
construction projects were the result of

24 Cost Engineering Vol. 52/No. 1 JANUARY 2010


of London won the bid to stage the games different activities per day, will result in additional premium and loss of
[7]. 100,000 individual jobs during a 10 day productivity costs.
shift. • Craft wage increases to attract to the
Research Method Each job requires a combination of the location personnel that possess the
The results and findings outlined in the correct materials, location, access, tools, local governmental requirements to
following sub-sections are part of a larger equipment, scaffold, safety, quality, rigging, work in the region. (Craft licensing and
research work, which will be reported on at consumables, welding, x-ray and many language requirements/limitations
a future date. The author surveyed and other inputs to allow the worker to get his or result in a smaller qualified work
incorporated the opinion of 90 her job done. force.)
international senior project managers. This task belongs to management, • Regional and national demands on
These were from both owner and which to date has not been able to plan, labor, including demands from other
engineering procurement and construction organize, or execute in a manner that has mega projects, which restricts the
(EPC) organizations. The purpose of the resulted in lower than anticipated labor availability of craft labor.
survey was to verify the findings of this productivity. If labor is not carefully • Under estimation of the labor
study. These 90 project managers came managed, budgets double. And this has productivity loss, associated with
from Canada, the US, Norway, UK, historically occurred. working in cold weather climates, and
Germany, Australia, India, and Finland. Job sites, past and present, on mega locations with severely shorter daylight
projects have been characterized by hours in northern regions. (Weather
Defining Mega Projects confusion, insufficient use of tools, conditions such as low temperatures,
Participants of this research agree that equipment, material and labor, work high winds, precipitation, and reduced
mega projects can be defined as being over instructions are vague, and engineering is daylight hours, can significantly reduce
$1 billion in total installed cost, excluding not prioritized. The result has been no labor efficiency.)
development costs (expended prior to the predictability of costs and schedules [11]. • Shortages of skilled labor and lower
project being formally approved). Mega There are many aspects in each mega than anticipated labor productivity
projects are huge in magnitude and are project that must be done and completed because of mismanagement of the
characterized by significant number of properly, if the overall results are going to be construction phase.
interfaces, interdependencies, complexity successful. The engineering and • High labor turnover mainly resulting
and risks. Some of these must be managed construction efforts illustrated above, show from the harsh working environment
at a level above the project team. the complexity and huge magnitude of the and competition between employers
Designing and constructing a $3 scope. This requires a huge level of project trying to attract the best labor. This
billion mega oil sands project for example, management effort to achieve success. instability on mega projects can be
may involve the following. further aggravated by senior
Research Findings management changes on the owner’s
Engineering Effort This investigation revealed the side.
• 3.5 million work hours at a cost of following reasons for cost and schedule • Transportation costs (including custom
$100/hr. overruns. cost) are generally underestimated for
• 40-50,000 design drawings. And, permanent materials, construction
• 10-20,000 vendor and shop drawings. •. Unrealistic or overly optimistic original equipment, personal, staff, etc.
(AFE) cost estimate and schedules. • Environmental and regulatory
Construction Effort The underestimation of project costs compliance costs are not given
• Construction hours or field labor, may be explained by many reasons, sufficient consideration during the
approximately 5000 work hours per including the following. contract negotiation period, by both
million dollars of capital (i.e. 10-15 the client and engineering firms.
million worker hours at $85 to $100 per • The under appreciation of project Projects often are not “grandfathered”
hour). complexity, interfaces, with respect to governmental
• Labor force of 10,000 workers, with a interdependencies, and risks associated regulations, which can change with
turnover of 30,000 people. with the mega project environment. local political and environmental
• Supported by 500-800 staff personnel. Some of the risks are outside the specialty group pressure.
And, control of the project management - Material cost for both permanent
• Organize order, store, and retrieve team. facilities and temporary facilities are
80,000,000 material items. • Under estimating the cost to attract and not sufficiently escalated during the
maintain the labor (craft) work force project budget development phase.
Constructing a $3 billion mega project (including camp development and These escalation cost are often
in Fort McMurray may require at peak operations cost. Also, costs to transport qualified or limited by the EPC
defining and scheduling work for 10,000 personnel into and out of the remote contractor, or passed along to the
people every day, with a personnel turnover regions where the mega projects tend client. (i.e. Craft labor escalated 20 to
that can reach 300 percent annually. to be located. 30 percent in 2006, and the norm is
Managing a craft mix of 10,000 workers, • Underestimating the direct and closer to 3 to 4 percent per year. Nickel
who work in pairs doing at least two indirect costs of overtime, including used in SS increased over 100 percent

Cost Engineering Vol. 52/No. 1 JANUARY 2010 25


in cost in the past year, whereas normal commissioning services. These to adversarial relationships and
material escalation is estimated at 2 ½ strategies are driven by time rather than protracted disputes.
to 4 percent per year.) cost, assuming safety and quality are • Poor site organization and layout
- Requirements for local content can given requirements. leading to excessive time wastage and
add inefficiency and additional • Design strategies such as contributions productivity loss during construction.
training cost to staff a project. These from client business, operation, project • Joint venture (JV) of project partners,
requirements can also eliminate lower team, contractors and suppliers. contractors and engineering firms that
cost vendors and fabrication facilities • Procurement strategies including are not aligned or not set up to work
in order to meet the “local content” preferred suppliers, progressing, effectively due to different cultures,
requirements. inspection and expediting, receipt, internal JV conflicts and diverging
storage and management, spares and visions of the way that the EPC project
Incomplete Scope Definition or documentation. should structured and managed.
Inadequate Front End Loading • Construction strategies, including site
Incomplete scope definition and management and organization, site Recommendations
inadequate front end loading are mainly layout, power, utilities and drainage, Mega projects are challenging, complex
because of the fast-tracking nature of mega work breakdown structure, and risky with a large number of interfaces
projects. Also, ongoing changing customer construction method, off-site and interdependencies. Fast tracking in
requirements result in scope changes prefabrication and assembly, schedule combination with scope changes at the
throughout the life cycle of the project. A and milestones, industrial relations, front end stages needs to be anticipated,
lack of understanding of the cumulative and pre-commissioning. monitored and controlled by project teams.
impact of scope changes on project cost and • Commissioning strategies including Owners must implement processes that
schedule add another dimension to this responsibilities, schedule and detect and curb systematic cost
issue. integration with construction, underestimation, scope changes, and
The client’s and engineering firms’ resources, training and validation, schedule deviations, as early as possible and
practice of pushing work to the field early, engineering and trade support, and take necessary and timely actions. ◆
puts construction under an unrealistic provision of operating materials.
compressed schedule with increased REFERENCES
overtime requirements and often with little Mismanagement of the Construction 1. Construction Industry Institute (CII)
or no cost consideration for the field cost. Phase Work Packaging for Project Control,
Engineering firms and clients have Mismanagement of the construction SD-28, University of Texas at Austin,
typically used the approach that it is phase may be caused by the following. US, 1987.
cheaper to force schedule compression on 2. Creswell, J. Qualitative Inquiry and
the construction work, based on • Later than anticipated engineering, Research Design: Choosing Among
construction labor being less expensive vendor data, equipment and material Five Traditions. Thousand Oaks, CA:
than engineering cost. However, the all-in- deliveries. Sage, 1998.
craft labor cost, including camp cost, is • Poor project controls. Nobody on the 3. Dunbar, R., M. Strogran, and P. Chan.
currently in the $120 to $180 per hour project has single point responsibility Potential Supply and Costs of Crude
range, which far outweighs the minimal except the client who does not control Bitumen and Synthetic Oil in Canada
cost to work engineering overtime to much of the work. 2003-2017, Canadian Energy Research
maintain or recover the design deliverable • Inadequate plan of execution and Institute (CERI), Study No. 108,
schedule. poorly defined tasks and division of March 2004.
responsibility. 4. European Construction Institute
Inappropriate Project Strategies for the • Lack of knowledgeable leadership in (ECI). The Fast Track Manual: A
Mega Oil Sands Environment the engineering, procurement, Guide to Schedule Reduction for
Some project strategies deployed, do construction and start-up of Clients and Contractors on
not properly consider the level of scope mega/major facilities. Engineering and Construction
definition, the fast track nature of the mega • Inexperienced or poorly equipped Projects, ECI, Loughborough, UK,
project environment, market condition, project management personnel and 2002.
owner participation, owner control and supervisors, coupled with the inability 5. Flyvbjerg, B., N. Bruzelius, and W.
owner risk. Improper or late consideration to understand, plan, adapt, implement Rothengatter. Megaprojects and Risk:
of the following project strategies adds to project management procedures or An Anatomy of Ambition, Cambridge
cost overruns [4]. systems. University Press, UK, 2003.
• Lack of standardization and fit-for- 6. Herzog, L. Building Collaborating
• Project management strategies such as purpose including inadequate use of Team Trust, MSc thesis, University of
risk management, project control, shop fabrication, modularization Calgary, Calgary, Alberta, Canada,
change control, communications, strategy and constructability reviews. 2000.
organization and responsibilities. • Poor communication, team work and 7. Hughes, R. An Outcry in Britain on
• Contract strategies relating to alignment between the players leading Games’ Rising Cost, article in the
management, design, construction and

26 Cost Engineering Vol. 52/No. 1 JANUARY 2010


International Herald Tribune, March
17-18, 2007.
8. Lavingia, N. Best Practices in Cost
Engineering, Transactions of the 48th
AACE International Annual Meeting,
Washington, US, 2004.
9. Lavingia, N. How to Create a World
Class Project Management
Organization, Transactions of the 50th
AACE International Annual Meeting,
Las Vegas, US, 2006.
10. McTague, R. and G.F. Jergeas.
Productivity Improvements on Alberta
Major Construction Projects, Alberta
Economic Development
htt://www.Alberta-Canada.com/stat
pub/pdf/ConprodStudy02.pdf, 2002.
11. McTague, R. Construction
Productivity, A Presentation to ENCI
691 Class, University of Calgary,
Alberta, Canada, 2006.

ABOUT THE AUTHORS


Dr. Janaka Ruwanpura and Dr. George
F. Jergeas , P.Eng., are with the Department
of Civil Engineering, University of Calgary,
2500 University Drive NW, Calgary, AB,
T2N 1N4, Canada. They can be reached
by sending e-mail to: janaka@ucalgary.ca
and to: gjergeas@hotmail.com.

McDonough Bolyard Peck receives an


CMAA 2009 National Project Achievement Award
Danelle Prezioso, MBP Director of Communications & Marketing

M
cDonough Bolyard Peck, Inc. (MBP) has been se- at CMAA's National Conference on October 27, 2009 in Or-
lected by the Construction Management Associa- lando, Florida.
tion of America (CMAA) for an Honorable “We are extremely honored to have been chosen for this
Mention in the 2009 National Project Achievement Awards in award,” states Charles E. Bolyard, Jr., PSP, CFCC, MBP's
the category of Infrastructure Project with a constructed value Chairman and CEO. Mr. Bolyard is a member of AACE Inter-
less than $150 million for the I-64 Battlefield Interchange Re- national. “The I-64 Battlefield Boulevard Reconstruction project
construction Project in Hampton Roads, Virginia. This is visibly manifests MBP’s core values of teamwork, quality and
MBP’s second consecutive Project Achievement Award recog- hard work.”
nition. The I-64/Battlefield Boulevard Interchange Project was also
This I-64/Battlefield Boulevard Interchange Project con- profiled in the cover story for the June 2009 issue of Public
sisted of the first braided collector-distributor lanes in the Hamp- Works Magazine and has achieved other honors such as 9th Best
ton Roads area. This phased construction project included 5.88 Road of 2009 by Roads & Bridges Magazine and communica-
lane miles of paving with the expansion of Interstate 64 from six tions awards including the Pinnacle Award, Hermes Platinum
lanes to fourteen lanes, four new interstate bridges, and phased Award, and Communicator Award of Distinction. ◆
demolition and replacement of the existing Battlefield Boule-
vard Bridge over Interstate 64.
The national Project Achievement Awards program recog-
nizes excellence in construction and program management.
More than 150 project entries were received and reviewed by a
panel of more than 20 judges. The award was presented to MBP

Cost Engineering Vol. 52/No. 1 JANUARY 2010 27

You might also like