Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

CASE STUDY: DESIGN, INSTALLATION AND QUALITY ASSURANCE TESTING OF HIGH

CAPACITY SOCKETED PILES IN A COMPLEX GEOLOGIC ENVIRONMENT

Thomas M. Caruso, TRC Engineers, Inc., Mount Laurel, New Jersey, USA
Melissa L. Gillespie, TRC Engineers, Inc., Mount Laurel, New Jersey, USA
Craig H. Olson, TRC Engineers, Inc., Mount Laurel, New Jersey, USA

Construction of a new ship dock at a major Philadelphia area refinery required


geotechnical design and field consultation. The new dock, which consists of a system of
mooring dolphins and platforms, will be capable of docking the Stena V-MAX Oil Tanker
(V-MAX). The 1100 ft long V-MAX is currently the largest tanker to travel the Delaware
River and will induce significant lateral loads on the new ship dock. Lateral loads
induced on the dock will be resisted by over 200 pipe piles installed on a batter. The piles
used for support of the dock included 20 and 30 in. diameter reinforced, concrete filled
pipe piles. Complete construction of each pile included driving of the pile to the design
ultimate capacity, flushing the pipe pile casing clean of overburden materials followed by
drilling rock sockets into the underlying Wissahickon Formation. Variations in depth to
bedrock, rock quality and degree of weathering and presence of very hard quartzite
lenses created a complex geologic environment that presented challenges for the
pile/rock socket design and installation. The design of the pile system, installation
methods, QA/QC and testing (Pile Dynamic Analysis), as well as the challenges that
were encountered through the duration of the project are presented and discussed.

BACKGROUND batter angles so as to transmit these lateral


loads as axial loads (tension and compression).
TRC Engineers, Inc. was retained as the In compression, piles readily obtain required toe
geotechnical consultant for the design of a New capacity from the underlying rock material. In
Ship Dock at a refinery located on the Delaware tension, however, the shaft resistance generated
River in Trainer, PA. TRC also performed field from the river sediments is marginal. Therefore,
construction quality assurance activities for this rock anchor installation below the tip of the pipe
project [including construction oversight and Pile piles, or driving of steel H-pile stinger section
Dynamic Analysis (PDA) for driven piles], and into the underlying bedrock was required. This
TRC geotechnical design engineers provided paper includes a brief discussion of rock anchor
consultation services during the course of design. Its focus is on installation and QA/QC
construction. procedures implemented during construction
and associated challenges resulting from site
The need for a New Ship Dock (NSD) was due geologic conditions.
to the load demands of larger oil tankers that will
be docking at this refinery in the future. REGIONAL GEOLOGY
Specifically, the NSD was designed to dock the
Stena V-MAX Oil Tanker (V-MAX), which is The project site is located on the Atlantic
currently the largest tanker to travel the Coastal Plain Physiographic Province,
Delaware River. approximately 5 to 10 miles southeast of the Fall
Line, which is the physiographic / geologic
The New Ship dock consists of a series of boundary between the crystalline rock
mooring dolphins and breasting cells supported formations of the Piedmont Province and the
on steel pipe piles with either drilled rock sediments of the Atlantic Coastal Plain Province.
sockets or H-pile stingers. The mooring
dolphins and breasting cells will be subjected to The area in the project vicinity is underlain by
very high lateral loads. The most prevalent recent river deposits of sand, silt, clay, and
overburden material encountered at the site gravel which overly metamorphic rock of the
consists of very soft river sediments (primarily Wissahickon formation. Rock of the
silt). Due to the fact that the river sediments Wissahickon formation is a heterogeneous
provide a relatively low resistance to deflection regional unit of schists, gneisses, and phyllites.
under lateral loading, the piles were installed at The general rock type found in the project area
is mica schist. Predominant mineralogy of this mica schist bedrock encountered at the site
mica schist consists of quartz, muscovite, biotite, using several pile alternatives. However, based
feldspar, and chlorite. Weathering profiles in the on consideration for the relatively large uplift
mica schist tend to be highly irregular. loads anticipated for this project and the extreme
variability in the presence and consistency of
The site is also located near the contact of the overburden soils at the site, driven pipe piles
Wissahichon Formation with the Trenton Gravel with rock anchors were selected for support of
Formation. The Trenton Gravel formation is the NSD.
generally a gray to pale reddish-brown, very
gravelly sand. From a geotechnical perspective, the rock
anchor design included consideration for the
SITE SUBSURFACE CONDITIONS length required to resist failure along the rock-
grout interface and the length required to
A total of 26 test borings were drilled for this mobilize a sufficient mass of rock to support the
project. Subsurface conditions encountered at applied load. Multiple calculations were
the site consisted primarily of alluvial deposits of performed for each component of the proposed
silts underlain by sand and gravel, residual soil NSD based on the following items:
resulting from in-place weathering of the parent
rock (very dense portions referred to as • The range of possible subsurface conditions
decomposed mica schist herein), and mica to be encountered based on available test
schist bedrock varying from severely weathered boring information.
to slightly to moderately weathered, and with
occasional interbedded quartzite. • Anticipated pile loading conditions.

The presence, consistency and thickness of • Potential group effects based on anticipated
alluvial and residual overburden materials were pile configurations.
highly variable across the site. Furthermore,
there was no identifiable trend associated with Based on the results of analyses performed for
the location or thicknesses of severely this project, total required rock anchor lengths
weathered and slightly to moderately weathered (severely and moderately to slightly weathered
rock types. The severely weathered and slightly rock) were on the order of 25 to 35 ft, with a
to moderately weathered rock was found to be minimum of 15 to 25 ft being in moderately to
inter-layered. Quartzite seams of variable slightly weathered rock. In all cases, the length
thickness, weathering and hardness were also of rock anchor required for mobilization of a
encountered within the mica schist at sufficient mass of rock to support the applied
approximately half of the test borings advanced load, including consideration for group effects,
for this project. At two test boring locations, was the controlling factor in the design.
approximately 10 to 12 ft of decomposed mica
schist was encountered below a 2 to 5 ft “ledge” SUMMARY OF CONSTRUCTION PHASE
of weathered mica schist. This relatively wide ACTIVITIES
distribution of rock quality is not unusual for the
Wissahickon formation. Figures 1a and 1b Construction of the NSD was performed in two
illustrate the variability in subsurface conditions separate phases. Phase 1 rock anchor
encountered at the project site. Figures 2, 3 and construction generally encountered relatively
4 illustrate the variability in rock recovery (REC), favorable rock conditions, consisting of
rock quality designation (RQD) and unconfined decomposed and weathered mica schist
compressive strength (UC) with depth. throughout the length of the rock socket.
However, highly variable and often problematic
SUMMARY OF ROCK SOCKET DESIGN soil and rock conditions were encountered
during Phase 2 construction. Figure 5 presents
As indicated above the large lateral loads to be a schematic of the ship dock construction areas.
imposed on the NSD are to be resisted by Because the intent of this paper is to discuss
groups of battered piles. Maximum anticipated complications related to complex geologic
pile compression and uplift loads are on the conditions, the proceeding sections focus on
order of 150 to 250 kips per pile. Anticipated Phase 2 rock anchor construction.
compression loads could be achieved in/on the
Figure 1a and 1b – Generalized Subsurface Profile between Main Dock Structure and Bravo Dolphin (see
Figure 5)

1a – Borings Outshore of Mooring Dolphins


Mean Low Water – Elev. 0.0

Downriver Upriver

2
?
3
4 ?

1b – Borings Inshore of Mooring Dolphins


Mean Low Water – Elev. 0.0

Downriver Upriver

3
1a

2
3 4
4

Strata Definitions:
1 – Alluvial SILT
1a – Alluvial SAND and GRAVEL
2 – Decomposed MICA SCHIST
3 – Highly Weathered MICA SCHIST
4 – Slightly to Moderately Weathered MICA SCHIST with interbedded QUARTZITE
Figure 2 – Distribution of REC vs Depth from ROCK ANCHOR CONSTRUCTION
Test Boring Data
Prior to rock anchor construction, an open-end
REC 24 in. diameter, steel pipe pile with 0.5 in. wall
0 20 40 60 80 100
thickness was driven to the required capacity at
40
each of the rock anchor location using an ICE I-
50 46. Capacities of all piles driven were verified
using Pile Dynamic Analysis (PDA). It was
60
expected that the majority of the pipe piles were
Depth (ft)

70 installed through the dense decomposed rock to


80
the top of the intact, weathered rock surface.
However, some exceptions to this assumption,
90 determined through observations during rock
100 anchor construction, are discussed below.
110
Drilling of 15 in. and 17 in. diameter rock sockets
was performed using an alternative drilling
method to that generally used for this type of
Figure 3 – Distribution of RQD vs Depth from construction. Typically, rock sockets are
Test Boring Data advanced using conventional rotary drilling
equipment, whereby the drill string is assembled
RQD in segments as the drilling progresses. For this
0 20 40 60 80 100
project, individual drilling rod sections were
40
connected into one continuous 110 ft section
50 with a Hammerdrill XL 12 down-the-hole
hammer at the bottom of the rods. Torque was
60
applied to the hammer/drill rod system using an
Depth (ft)

70 ICE 35AT auto-torque top drive auger.


Compressed air, used to operate both the auto-
80
torque top drive auger and the down-the-hole
90 hammer, was injected through the top of the drill
rod. The 110 ft hammer/drill rod system traveled
100
up and down tracks inside swinging leads
110 through the permanent steel casings
constructed of 24 in. diameter pipe piles.

The majority of the overburden materials within


Figure 4 – Distribution of Unconfined the pipe pile casing were removed during
Compressive Strength (UC) vs Depth from advancement of the drill hammer through the
Laboratory Test Data pile. This was accomplished through
UC (tsf) continuously pumping water into the pile casing.
0 500 1000 1500 The drilling operations created turbulent
40 conditions within the casing, loosening the
overburden materials adhering to the pile walls.
50
As the pneumatic hammer was periodically lifted
60 from the rock surface, compressed air was
forced down through the drill bit and up through
Depth (ft)

70
the pile. This movement of compressed air
80 thrust water, overburden materials, and drill
cuttings from within the pipe pile casing and was
90 effective in removing most overburden materials
100
for both the 15 and 17 in. diameter rock sockets.
Additionally, upon completion of socket drilling
110 and immediately prior to rock socket grouting,
overburden materials that remained within the
Figure 5 – Schematic of Ship Dock Construction Areas

pipe pile or that had sloughed into the rock intervals and measuring the elapsed time for
socket were removed via a suction system advancement of each of the intervals (or portion
developed by the Contractor. After removal of of an interval). A decrease in hammer
soil materials, a 2.5 in. diameter continuously penetration rate during drilling was generally
threaded steel bar and associated structural associated with an increase in rock quality.
components were installed through the entire
length of the uncased rock anchor and inner The characteristics of the rock cuttings expelled
diameter steel casing. The piles were then during drilling were also monitored for
tremie grouted using ready mix grout. assessment of rock quality. Cuttings expelled
during drilling through apparent decomposed
VERIFICATION OF ROCK CONDITIONS rock material were generally very soft. Although
the color and “fabric” of the material expelled
Due to the variability of the quality of the rock resembled that of the underlying parent bedrock,
underlying the project site, accurate assessment the consistency of these materials was similar to
of rock conditions encountered during rock that of a “stiff” / “dense” soil (i.e., a lump of silty
anchor installation, namely determining the and/or clayey sand) with only small quantities of
extent of weathering/decomposition or brittle rock fragments. Cuttings observed during
competency of the rock material through which drilling through severely weathered rock were
each rock anchor was installed, was a critical generally stronger and harder than those
part of the quality assurance process. Precise observed within decomposed rock; however, the
methods of determining rock quality during majority of the rock fragments could be broken
drilling were not available; therefore, field manually. Cuttings expelled during drilling
representatives relied on the information through more competent rock were primarily
obtained from the test borings and observations hard, strong mica schist rock fragments that
made during rock anchor drilling in order to could not be broken manually and also
confirm that design requirements were satisfied appeared to indicate the presence of quartzitic
at each rock anchor location. The two most and gneissic rock materials. Generally, the size,
important observations made in assessing rock or equivalent diameter, of the cuttings appeared
conditions encountered included observations of to decrease with increasing rock quality.
hammer penetration rate during drilling and
observations of the characteristics of rock Another “secondary” observation used to verify
cuttings expelled during drilling. rock quality included monitoring of the behavior
of the hammer during the course of rock socket
Penetration rates of the equipment were drilling. This included observations of the sound
monitored and recorded as the rock socket was of the rock hammer during drilling and the
advanced through apparent decomposed, frequency of blows from the pneumatic hammer
weathered, and competent rock strata. This was during drilling. During drilling through
accomplished by marking the drill rod at five foot decomposed and severely weathered rock, the
hammer produced a dull sound against the cuttings are primarily observed to be strong,
underlying rock material, and there were hard rock fragments.
intervals where hammer firing stopped
momentarily. During drilling through higher Field personnel were in communication with
quality rock material, the hammer produced a design engineers throughout the course of
louder sound and continuous drilling. These construction. Decisions regarding the need for
observations were especially useful in identifying modifications to minimum required rock socket
the transition zone between decomposed and lengths were efficiently made on case-by-case
weathered rock material, and identifying basis depending on actual conditions
decomposed rock seams that existed within encountered at each pile location.
higher quality rock material. However, these
“secondary” observations could not be used to COMPLICATIONS ENCOUNTERED DURING
further distinguish between the severely CONSTRUCTION
weathered and moderately to slightly weathered
rock. This was due to the fact that these Increased Penetration Rate
observations did not vary significantly within the As indicated above, penetration rates, hammer
more intact weathered rock material. behavior and performance, and observations of
cuttings were carefully monitored through the
Observations regarding hammer penetration course of rock anchor drilling.
rates, hammer behavior and performance, and
characteristics of cuttings, as described above, The above criteria were developed based on
were compared with the test boring data in order initial observations during drilling, primarily
to establish criteria to be applied in assessing through mica schist bedrock. However, as
rock quality throughout the project. For the previously indicated, the rock formation contains
majority of the rock sockets drilled, observations quartzite inclusions. Observed drilling
made during socket drilling remained relatively penetration rates were greatly affected by the
consistent. The rock hammer generally began presence of the much harder quartzite rock.
to “fire” in the “dense to very dense” plug within This was first observed during drilling at the first
the lower portion of the pile casing. The mooring dolphin upriver of the main dock
penetration rate of the drill was observed to vary structure (see Figure 1). During initial drilling,
from less than 0.5 to 1.0 minute per ft through the penetration rates and cutting observations
this material. Observations of cuttings expelled appeared consistent with the criteria indicated
from within the pile during drilling through the above. However, at varying depths below the
plug were indicative of decomposed rock bottom of the pile, the penetration rate
material. Penetration rates generally decreased decreased to approximately 10 minutes per ft to
once the hammer reached the bottom of the pile, up to 45 minutes per ft. Cuttings expelled during
and again at the transition from severely drilling appeared to be white, coarse sand to fine
weathered to moderately to slightly weathered gravel sized, hard rock fragments, indicative of
rock. After careful consideration of the above- quartzite. The quartzite at these locations
mentioned construction observations and data persisted for approximately 2 to 10 ft, with a total
from test borings closest to the drilling locations, drill time within the quartzite of up to 5 hours.
the following general criteria were established Similar observations were noted at several other
for evaluation of rock quality for this project: upriver mooring dolphin locations during drilling
within the quartzite zones. The increased
y Penetration rates ranging from less than 0.5 amount of time required for completion of the
to 1 minute per ft, with soil-like cuttings are rock anchors in this area became of significant
indicative of decomposed rock. concern, especially when considering the overall
project schedule.
y Penetration rates from 1 to 2 minutes per ft,
with rock fragments of varying strength and A minor enhancement was made to the drilling
hardness are indicative of decomposed to equipment in an attempt to increase drill
severely weathered rock. penetration rates. This enhancement included
increasing air pressure of the compressor used
y Penetration rates of above 2 minutes per ft to drive the pneumatic hammer. The goal was
are indicative of competent (slightly to to increase the frequency of repetitions of the
moderately weathered) rock, provided that rock hammer on the underlying rock material.
Increasing air pressure was not observed to sized rocks were observed to be expelled from
have any significant impact on drilling within the pile during re-advancement of the
penetration rates. After discussion with the rod/hammer system. During the second attempt
Contractor, project Geotechnical Engineers re- at drilling, the drill rod/hammer again became
evaluated the rock anchor design to determine if locked within the socket zone. The drilling rods
a 15 in. diameter rock socket would be viable were subsequently detached from the crane
from a geotechnical perspective. This was leads and the drill rod/hammer system removed
thought to be a potentially viable solution using a vibratory hammer. Rock anchor drilling
because a smaller hammer operating under the at this was temporarily abandoned and anchor
same weight of drill rod and air pressure, would drilling continued at the next scheduled location.
exert a greater amount of energy and pressure
on a smaller rock surface area, thereby The driven depth of the temporarily abandoned
increasing production drilling rates. Upon re- pile location was evaluated with respect to the
evaluation, it was concluded that because the information from the closest test borings. Due to
design was not governed by the bond shear the fact that the pile was installed on batter
strength along the rock-grout interface, a angles of 2V to 1H, the tip of the pipe pile
reduction of rock socket diameter to 15 in. would extended a horizontal distance of approximately
not compromise the rock anchor tension 20 ft (in the inshore direction) from the top of the
capacity from a geotechnical perspective. At the pile. The borings located closest to the vertical
direction of the General Contractor, in surface projection of the pile tip encountered an
conjunction the Structural Engineer, the size of approximately 5 ft thick layer of alluvial gravel
the rock hammer was reduced to 15 in. and cobbles with varying quantities of sand
diameter. The reduction in socket diameter was (likely an intrusion of the Trenton Gravel
effective in increasing penetration rates, Formation, predominant on the New Jersey side
especially during drilling through zones of of the Delaware River). This gravel and cobble
quartzite material. Penetration rates through layer was encountered at an approximate
quartzite using the smaller diameter hammer elevation that corresponded with the tip
were observed at no greater than 10 minutes elevation of the pile of concern. It was
per ft, as opposed to up to 45 minutes per ft concluded that during driving of the pipe pile at
during drilling with the 17 in. diameter rock this location, the pile achieved the required
hammer. capacity within the gravel and cobble layer.
While this layer was able to provide adequate
Socket Cave-In bearing resistance, it did not provide the sealing
As previously discussed, it was anticipated that affect that was provided by penetration into
the 24 in. diameter pipe piles were driven though decomposed rock material. Once the socket
alluvial river sediments and dense decomposed drill hammer was advanced past the pile tip, this
rock to the top of the competent weathered rock gravelly material was no longer confined and
surface. Based on this assumption, the potential was readily washed into the socket zone under
for caving of overburden materials into the hydrostatic pressure. After discussion of
socket zone at the location of the pile tip was possible remediation schemes between TRC
believed to be minimal due to the tight seal that and the General Contractor, the Contractor
would be created by the decomposed rock attempted to stabilize the breached area by
materials. However, during rock socket drilling pumping a flowable grout mixture through tremie
at the Bravo Dolphin, the rock hammer and drill tubes advanced to a location near the tip of the
rod appeared to “jam” at a depth of 10 ft below pipe pile. However, re-drilling at this location
the bottom of the socket. Due to the observed was unsuccessful as the hammer continued to
jamming, the Contractor attempted to lift the drill become lodged at a depth of 5 ft below the tip of
rod and hammer from within the socket. Lifting the pile. At the direction of the General
of the drill rod/hammer was observed to Contractor, the pile was spliced with an
encounter a substantial amount of resistance. additional 15 ft section and re-driven to a depth
Once raised above the socket zone, the that corresponded to the depth of the weathered
Contractor attempted to set the drill rod/hammer rock surface indicated on the borings. Socket
system back in the excavation; however, it could drilling was then completed at this location
not be lowered beyond the tip of the pile without further complications.
(approximately 10 ft above the depth previously
drilled). Furthermore, large cobble to gravel
Pile Damage at Bravo Dolphin Figure 6 – Impedance Change Observed in
As indicated, PDA testing was performed on all Blow Record during PDA at the MDS
piles driven during Phase 2 construction. PDA
provides close estimates of pile capacities, Impedance change at
determined in real-time (during driving). PDA is
also advantageous in monitoring stresses at the 2 feet from toe.
top and bottom of the pile, evaluating hammer
efficiency, and detecting damage to the pile
during driving.

As mentioned above, the presence of the


quartzite was problematic across the project
site. During the initial driving operations for one
of the Bravo piles, the PDA recorded observable
signs of impedance changes in the pile at
approximately 3 feet from the pile toe. The pile Upon recommendation, the pile was extracted
was removed and damage was verified at the and the extent of the damage is shown in Photo
pile toe as illustrated in Photo 1. 2.

Photo 1 - Pile Damage at Bravo Dolphin Photo 2 - Pile Damage at MDS

The pile was re-driven without PDA monitoring


Based on observations of the damage, TRC
to a final driving resistance of 10 blows per inch
concluded that pile damage was likely caused
and was successfully drilled out for a rock
by steel and timber obstructions that had been
socket in subsequent construction operations. It
part of the old ship dock.
is the opinion of TRC that the pile encountered a
hard quartzite layer which created local stress
In both cases, the occurrence of pile damage
concentrations that caused the pile damage.
was correctly predicted based on review of PDA
data; the piles were subsequently extracted and
Pile Damage at the Main Dock Structure successfully re-driven. In these cases, the use
During rock socket drilling at one of the Main of the PDA to obtain real time QA data helped
Dock Structure (MDS) piles, the drill hammer construction-phase personnel take a proactive
was observed to encounter refusal to further approach to identifying and mitigating potential
advancement at a depth that corresponded to problems encountered during pile installation,
the tip of the pipe pile. Several attempts were thereby preventing situations that could
made at drilling past this depth, however, all potentially cause significant delays during rock
attempts were unsuccessful. Upon review of the anchor drilling and also the potential for damage
PDA data, indications of impedance change of the drilling equipment. As a result, increased
were observed in several of the blow records at PDA testing frequency was critical to keep the
approximately 2 ft above the pile toe. This project on schedule considering the problematic
impedance change is illustrated in Figure 6. nature of the highly variable rock formation
encountered at the site.
OBSERVATIONS AND CONCLUSIONS were to be installed highlighted the importance
of quality control activities. Observations
Complex geologic conditions were encountered regarding hammer penetration rates, hammer
at the site of a proposed new ship dock (NSD) behavior and performance and characteristics of
located along the Delaware River in Trainer, cuttings expelled as excavations for rock
Pennsylvania. The presence, consistency and anchors were advanced, were used in
thickness of alluvial and residual overburden conjunction with the test boring data to establish
materials were highly variable across the site, as general criteria to be applied in assessing rock
was the location and quality of site bedrock. quality throughout the project. The rock hammer
Bedrock encountered at the site, predominantly generally began to “fire” in the “dense to very
mica schist of the Wissahickon Formation, dense” plug within the lower portion of the pile
exhibited varying degrees of weathering and casing. Penetration rates were slowest through
hardness. There was no identifiable trend this material and generally increased once the
associated with the location or thicknesses of hammer reached the bottom of the pile, and
highly weathered zones, which were often inter- again at the transition from severely weathered
layered with more intact rock. Additionally, to moderately to slightly weathered rock. The
quartzite seams of variable thickness, following general criteria to were established
weathering and hardness were also and used to evaluate rock quality for this project:
encountered within the mica schist. This
relatively wide distribution of rock quality is not y Penetration rates ranging from less than 0.5
unusual for the Wissahickon Formation. These to 1 minute per ft, with soil-like cuttings are
complex geologic conditions encountered at the indicative of decomposed rock.
site created challenges for design and
construction of foundation support systems for y Penetration rates from 1 to 2 minutes per ft,
the ship dock. with rock fragments of varying strength and
hardness are indicative of decomposed to
Based on consideration for the relatively large severely weathered rock.
uplift loads anticipated for this project and the
extreme variability in the subsurface conditions y Penetration rates of above 2 minutes per ft
encountered at the site, driven pipe piles with are indicative of competent (slightly to
rock anchors were selected for support of the moderately weathered) rock, provided that
NSD. From a geotechnical perspective, the rock cuttings are primarily observed to be strong,
anchor design included consideration for the hard rock fragments.
length required to resist failure along the rock-
grout interface and the length required to This information was also used to assess the
mobilize a sufficient mass of rock to support the need for modifications to minimum required rock
applied load. Multiple calculations were required socket lengths on a case-by-case basis
to account for the range of possible subsurface considering actual conditions encountered at
conditions that might be encountered across the each pile location.
site; anticipated pile loading conditions for each
component of the NSD; and potential group Construction of the NSD was performed in two
effects based on anticipated pile configurations separate phases. The first phase of rock anchor
for each component of the NSD. Total required construction progressed without notable difficulty
rock anchor lengths (including severely and or delays. However, highly variable and often
moderately to slightly weathered rock) were on problematic soil and rock conditions were
the order of 25 to 35 ft, with a minimum of 15 to encountered during the second phase of
25 ft required in moderately to slightly weathered construction. Complications included extremely
rock. In all cases, the length of rock anchor slow drilling penetration rates at times, cave-in
required for mobilization of a sufficient mass of of alluvial overburden materials into the rock
rock to support the applied load, including socket zone, and pile damage that was
consideration for group effects, was the prohibitive of rock anchor construction.
controlling factor in the design. Interaction and collaboration between field
inspection personnel, design engineers, and
Construction quality control is an essential contractor representatives allowed for exchange
aspect of every project; however, the geologic of ideas and timely decision-making with regard
environment in which foundations for this project to approaches for remediation of problematic
conditions. This minimized disruption to the encountered during rock socket drilling
overall project schedule and provided valuable operations. Attempting to advance rock drilling
insight for consideration on future projects of a equipment through the damaged pile section
similar nature. could also have resulted in damage to drilling
equipment. The additional time spent during
Use of PDA as a QA tool was also beneficial on unsuccessful rock socket drilling and/or damage
this project because it allowed for prediction of to rock drilling equipment would have been very
pile damage. This pile damage would not have costly and would have resulted in significant
otherwise been realized until problems were impacts to the overall project schedule.

You might also like