Professional Documents
Culture Documents
Caruso Gillespie Olson 08-01-2008
Caruso Gillespie Olson 08-01-2008
Thomas M. Caruso, TRC Engineers, Inc., Mount Laurel, New Jersey, USA
Melissa L. Gillespie, TRC Engineers, Inc., Mount Laurel, New Jersey, USA
Craig H. Olson, TRC Engineers, Inc., Mount Laurel, New Jersey, USA
The presence, consistency and thickness of • Potential group effects based on anticipated
alluvial and residual overburden materials were pile configurations.
highly variable across the site. Furthermore,
there was no identifiable trend associated with Based on the results of analyses performed for
the location or thicknesses of severely this project, total required rock anchor lengths
weathered and slightly to moderately weathered (severely and moderately to slightly weathered
rock types. The severely weathered and slightly rock) were on the order of 25 to 35 ft, with a
to moderately weathered rock was found to be minimum of 15 to 25 ft being in moderately to
inter-layered. Quartzite seams of variable slightly weathered rock. In all cases, the length
thickness, weathering and hardness were also of rock anchor required for mobilization of a
encountered within the mica schist at sufficient mass of rock to support the applied
approximately half of the test borings advanced load, including consideration for group effects,
for this project. At two test boring locations, was the controlling factor in the design.
approximately 10 to 12 ft of decomposed mica
schist was encountered below a 2 to 5 ft “ledge” SUMMARY OF CONSTRUCTION PHASE
of weathered mica schist. This relatively wide ACTIVITIES
distribution of rock quality is not unusual for the
Wissahickon formation. Figures 1a and 1b Construction of the NSD was performed in two
illustrate the variability in subsurface conditions separate phases. Phase 1 rock anchor
encountered at the project site. Figures 2, 3 and construction generally encountered relatively
4 illustrate the variability in rock recovery (REC), favorable rock conditions, consisting of
rock quality designation (RQD) and unconfined decomposed and weathered mica schist
compressive strength (UC) with depth. throughout the length of the rock socket.
However, highly variable and often problematic
SUMMARY OF ROCK SOCKET DESIGN soil and rock conditions were encountered
during Phase 2 construction. Figure 5 presents
As indicated above the large lateral loads to be a schematic of the ship dock construction areas.
imposed on the NSD are to be resisted by Because the intent of this paper is to discuss
groups of battered piles. Maximum anticipated complications related to complex geologic
pile compression and uplift loads are on the conditions, the proceeding sections focus on
order of 150 to 250 kips per pile. Anticipated Phase 2 rock anchor construction.
compression loads could be achieved in/on the
Figure 1a and 1b – Generalized Subsurface Profile between Main Dock Structure and Bravo Dolphin (see
Figure 5)
Downriver Upriver
2
?
3
4 ?
Downriver Upriver
3
1a
2
3 4
4
Strata Definitions:
1 – Alluvial SILT
1a – Alluvial SAND and GRAVEL
2 – Decomposed MICA SCHIST
3 – Highly Weathered MICA SCHIST
4 – Slightly to Moderately Weathered MICA SCHIST with interbedded QUARTZITE
Figure 2 – Distribution of REC vs Depth from ROCK ANCHOR CONSTRUCTION
Test Boring Data
Prior to rock anchor construction, an open-end
REC 24 in. diameter, steel pipe pile with 0.5 in. wall
0 20 40 60 80 100
thickness was driven to the required capacity at
40
each of the rock anchor location using an ICE I-
50 46. Capacities of all piles driven were verified
using Pile Dynamic Analysis (PDA). It was
60
expected that the majority of the pipe piles were
Depth (ft)
70
the pile. This movement of compressed air
80 thrust water, overburden materials, and drill
cuttings from within the pipe pile casing and was
90 effective in removing most overburden materials
100
for both the 15 and 17 in. diameter rock sockets.
Additionally, upon completion of socket drilling
110 and immediately prior to rock socket grouting,
overburden materials that remained within the
Figure 5 – Schematic of Ship Dock Construction Areas
pipe pile or that had sloughed into the rock intervals and measuring the elapsed time for
socket were removed via a suction system advancement of each of the intervals (or portion
developed by the Contractor. After removal of of an interval). A decrease in hammer
soil materials, a 2.5 in. diameter continuously penetration rate during drilling was generally
threaded steel bar and associated structural associated with an increase in rock quality.
components were installed through the entire
length of the uncased rock anchor and inner The characteristics of the rock cuttings expelled
diameter steel casing. The piles were then during drilling were also monitored for
tremie grouted using ready mix grout. assessment of rock quality. Cuttings expelled
during drilling through apparent decomposed
VERIFICATION OF ROCK CONDITIONS rock material were generally very soft. Although
the color and “fabric” of the material expelled
Due to the variability of the quality of the rock resembled that of the underlying parent bedrock,
underlying the project site, accurate assessment the consistency of these materials was similar to
of rock conditions encountered during rock that of a “stiff” / “dense” soil (i.e., a lump of silty
anchor installation, namely determining the and/or clayey sand) with only small quantities of
extent of weathering/decomposition or brittle rock fragments. Cuttings observed during
competency of the rock material through which drilling through severely weathered rock were
each rock anchor was installed, was a critical generally stronger and harder than those
part of the quality assurance process. Precise observed within decomposed rock; however, the
methods of determining rock quality during majority of the rock fragments could be broken
drilling were not available; therefore, field manually. Cuttings expelled during drilling
representatives relied on the information through more competent rock were primarily
obtained from the test borings and observations hard, strong mica schist rock fragments that
made during rock anchor drilling in order to could not be broken manually and also
confirm that design requirements were satisfied appeared to indicate the presence of quartzitic
at each rock anchor location. The two most and gneissic rock materials. Generally, the size,
important observations made in assessing rock or equivalent diameter, of the cuttings appeared
conditions encountered included observations of to decrease with increasing rock quality.
hammer penetration rate during drilling and
observations of the characteristics of rock Another “secondary” observation used to verify
cuttings expelled during drilling. rock quality included monitoring of the behavior
of the hammer during the course of rock socket
Penetration rates of the equipment were drilling. This included observations of the sound
monitored and recorded as the rock socket was of the rock hammer during drilling and the
advanced through apparent decomposed, frequency of blows from the pneumatic hammer
weathered, and competent rock strata. This was during drilling. During drilling through
accomplished by marking the drill rod at five foot decomposed and severely weathered rock, the
hammer produced a dull sound against the cuttings are primarily observed to be strong,
underlying rock material, and there were hard rock fragments.
intervals where hammer firing stopped
momentarily. During drilling through higher Field personnel were in communication with
quality rock material, the hammer produced a design engineers throughout the course of
louder sound and continuous drilling. These construction. Decisions regarding the need for
observations were especially useful in identifying modifications to minimum required rock socket
the transition zone between decomposed and lengths were efficiently made on case-by-case
weathered rock material, and identifying basis depending on actual conditions
decomposed rock seams that existed within encountered at each pile location.
higher quality rock material. However, these
“secondary” observations could not be used to COMPLICATIONS ENCOUNTERED DURING
further distinguish between the severely CONSTRUCTION
weathered and moderately to slightly weathered
rock. This was due to the fact that these Increased Penetration Rate
observations did not vary significantly within the As indicated above, penetration rates, hammer
more intact weathered rock material. behavior and performance, and observations of
cuttings were carefully monitored through the
Observations regarding hammer penetration course of rock anchor drilling.
rates, hammer behavior and performance, and
characteristics of cuttings, as described above, The above criteria were developed based on
were compared with the test boring data in order initial observations during drilling, primarily
to establish criteria to be applied in assessing through mica schist bedrock. However, as
rock quality throughout the project. For the previously indicated, the rock formation contains
majority of the rock sockets drilled, observations quartzite inclusions. Observed drilling
made during socket drilling remained relatively penetration rates were greatly affected by the
consistent. The rock hammer generally began presence of the much harder quartzite rock.
to “fire” in the “dense to very dense” plug within This was first observed during drilling at the first
the lower portion of the pile casing. The mooring dolphin upriver of the main dock
penetration rate of the drill was observed to vary structure (see Figure 1). During initial drilling,
from less than 0.5 to 1.0 minute per ft through the penetration rates and cutting observations
this material. Observations of cuttings expelled appeared consistent with the criteria indicated
from within the pile during drilling through the above. However, at varying depths below the
plug were indicative of decomposed rock bottom of the pile, the penetration rate
material. Penetration rates generally decreased decreased to approximately 10 minutes per ft to
once the hammer reached the bottom of the pile, up to 45 minutes per ft. Cuttings expelled during
and again at the transition from severely drilling appeared to be white, coarse sand to fine
weathered to moderately to slightly weathered gravel sized, hard rock fragments, indicative of
rock. After careful consideration of the above- quartzite. The quartzite at these locations
mentioned construction observations and data persisted for approximately 2 to 10 ft, with a total
from test borings closest to the drilling locations, drill time within the quartzite of up to 5 hours.
the following general criteria were established Similar observations were noted at several other
for evaluation of rock quality for this project: upriver mooring dolphin locations during drilling
within the quartzite zones. The increased
y Penetration rates ranging from less than 0.5 amount of time required for completion of the
to 1 minute per ft, with soil-like cuttings are rock anchors in this area became of significant
indicative of decomposed rock. concern, especially when considering the overall
project schedule.
y Penetration rates from 1 to 2 minutes per ft,
with rock fragments of varying strength and A minor enhancement was made to the drilling
hardness are indicative of decomposed to equipment in an attempt to increase drill
severely weathered rock. penetration rates. This enhancement included
increasing air pressure of the compressor used
y Penetration rates of above 2 minutes per ft to drive the pneumatic hammer. The goal was
are indicative of competent (slightly to to increase the frequency of repetitions of the
moderately weathered) rock, provided that rock hammer on the underlying rock material.
Increasing air pressure was not observed to sized rocks were observed to be expelled from
have any significant impact on drilling within the pile during re-advancement of the
penetration rates. After discussion with the rod/hammer system. During the second attempt
Contractor, project Geotechnical Engineers re- at drilling, the drill rod/hammer again became
evaluated the rock anchor design to determine if locked within the socket zone. The drilling rods
a 15 in. diameter rock socket would be viable were subsequently detached from the crane
from a geotechnical perspective. This was leads and the drill rod/hammer system removed
thought to be a potentially viable solution using a vibratory hammer. Rock anchor drilling
because a smaller hammer operating under the at this was temporarily abandoned and anchor
same weight of drill rod and air pressure, would drilling continued at the next scheduled location.
exert a greater amount of energy and pressure
on a smaller rock surface area, thereby The driven depth of the temporarily abandoned
increasing production drilling rates. Upon re- pile location was evaluated with respect to the
evaluation, it was concluded that because the information from the closest test borings. Due to
design was not governed by the bond shear the fact that the pile was installed on batter
strength along the rock-grout interface, a angles of 2V to 1H, the tip of the pipe pile
reduction of rock socket diameter to 15 in. would extended a horizontal distance of approximately
not compromise the rock anchor tension 20 ft (in the inshore direction) from the top of the
capacity from a geotechnical perspective. At the pile. The borings located closest to the vertical
direction of the General Contractor, in surface projection of the pile tip encountered an
conjunction the Structural Engineer, the size of approximately 5 ft thick layer of alluvial gravel
the rock hammer was reduced to 15 in. and cobbles with varying quantities of sand
diameter. The reduction in socket diameter was (likely an intrusion of the Trenton Gravel
effective in increasing penetration rates, Formation, predominant on the New Jersey side
especially during drilling through zones of of the Delaware River). This gravel and cobble
quartzite material. Penetration rates through layer was encountered at an approximate
quartzite using the smaller diameter hammer elevation that corresponded with the tip
were observed at no greater than 10 minutes elevation of the pile of concern. It was
per ft, as opposed to up to 45 minutes per ft concluded that during driving of the pipe pile at
during drilling with the 17 in. diameter rock this location, the pile achieved the required
hammer. capacity within the gravel and cobble layer.
While this layer was able to provide adequate
Socket Cave-In bearing resistance, it did not provide the sealing
As previously discussed, it was anticipated that affect that was provided by penetration into
the 24 in. diameter pipe piles were driven though decomposed rock material. Once the socket
alluvial river sediments and dense decomposed drill hammer was advanced past the pile tip, this
rock to the top of the competent weathered rock gravelly material was no longer confined and
surface. Based on this assumption, the potential was readily washed into the socket zone under
for caving of overburden materials into the hydrostatic pressure. After discussion of
socket zone at the location of the pile tip was possible remediation schemes between TRC
believed to be minimal due to the tight seal that and the General Contractor, the Contractor
would be created by the decomposed rock attempted to stabilize the breached area by
materials. However, during rock socket drilling pumping a flowable grout mixture through tremie
at the Bravo Dolphin, the rock hammer and drill tubes advanced to a location near the tip of the
rod appeared to “jam” at a depth of 10 ft below pipe pile. However, re-drilling at this location
the bottom of the socket. Due to the observed was unsuccessful as the hammer continued to
jamming, the Contractor attempted to lift the drill become lodged at a depth of 5 ft below the tip of
rod and hammer from within the socket. Lifting the pile. At the direction of the General
of the drill rod/hammer was observed to Contractor, the pile was spliced with an
encounter a substantial amount of resistance. additional 15 ft section and re-driven to a depth
Once raised above the socket zone, the that corresponded to the depth of the weathered
Contractor attempted to set the drill rod/hammer rock surface indicated on the borings. Socket
system back in the excavation; however, it could drilling was then completed at this location
not be lowered beyond the tip of the pile without further complications.
(approximately 10 ft above the depth previously
drilled). Furthermore, large cobble to gravel
Pile Damage at Bravo Dolphin Figure 6 – Impedance Change Observed in
As indicated, PDA testing was performed on all Blow Record during PDA at the MDS
piles driven during Phase 2 construction. PDA
provides close estimates of pile capacities, Impedance change at
determined in real-time (during driving). PDA is
also advantageous in monitoring stresses at the 2 feet from toe.
top and bottom of the pile, evaluating hammer
efficiency, and detecting damage to the pile
during driving.